Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 93968: 2010-001-00 CAP UPPER WENATCHEE FLOODPLAIN IMPLEMENTATION
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
93968
Contract Title:
2010-001-00 CAP UPPER WENATCHEE FLOODPLAIN IMPLEMENTATION
Contract Continuation:
Previous: Next:
91590: 2010-001-00 EXP UPPER WENATCHEE FLOODPLAIN 60% TO FINAL DESIGN
Contract Status:
Issued
Contract Description:
This contract is for Phase 5 of the Upper Wenatchee Floodplain Reconnection Project.

During Phase 5 the construction contracting process will be completed and the project will be implemented. We will continue to respond to inquiries regarding the construction bid packages released during Phase 4, and will select and contract with contractors to complete ground-based and helicopter-based construction tasks. We will also renew our contract with the design engineering firm (Natural Systems Design - NSD) that has been part of this project since the beginning, and expect to contract with a landscaping firm for assistance with post-construction planting tasks.

We will work with these contractors to prepare for 2024 construction (approximately July through October). Upon contract execution and notice to proceed, the construction contractors will begin preparations needed to complete the project including, but not limited to, obtaining materials and supplies and preparing construction submittals (e.g., Dewatering and Isolation Plan, Temporary Erosion and Sediment Control Plan, Temporary Bridge Drawings, etc.). During construction, they will mobilize to the site and complete tasks necessary to implement the project. NSD will assist with review and approval of contractor submittals, and will provide construction oversite during project implementation. A landscaping firm be subcontracted to assist with tree and shrub planting needed to rehabilitate areas disturbed during project construction. In addition to the contracting mentioned above and other project administration, CCNRD will work with USFS to assure compliance with all applicable environmental regulations. CCNRD will order supplies and materials and complete all actions needed to implement the recreational safety, fish use monitoring and water quality monitoring plans during project implementation and will provide construction management and oversite during project implementation. This scope also includes post-implementation environmental compliance, including fulfillment of requirements under WDFW's Hydraulic Project Approval (HPA) permit, and grant reporting.

CCNRD has received $600,058 in cost share funding from WA RCO and USFS to support this phase.


Completed Work To Date via BPA Funding:

Phase 1 (contract #: 82854), which was vetted by the Regional Technical Team (RTT), completed pre-conceptual work and development of 15% conceptual designs.

Phase 2 (contract # 86732), included development of a 30% design package; coordination among project proponents and key stakeholders (Chelan County Natural Resources Department (CCNRD), BPA, the U.S. Forest Service (USFS), Washington Department of Fish & Wildlife (WDFW), the Upper Columbia Salmon Recovery Board (UCSRB), and others); an assessment of access feasibility; bedrock profiling using seismic refraction to aid in the determination of siting and structural stability requirements needed for design work; and preparation of a draft recreation safety plan.

Phase 3 (contract # 89494), included development of a permit-ready (60%) design package; wetland delineation field work and reporting; cultural resources survey and reporting; preparation of JARPA and HPA permit applications; coordination with Washington DNR to achieve Aquatic Use Authorization (AUA - including preparation of Public Safety Checklist for Large Woody Debris Projects, a required component of the DNR AUA process). In addition, USFS initiated ESA and NEPA consultations, and we met with USFWS, NOAA Fisheries and WDFW staff to discuss potential for in-water work window extension.

Phase 4 (contract # 91590), the design package was advanced to construction-ready, construction bid documents were prepared and disseminated to prospective construction contractors, and a pre-bid meeting was held. In addition, CCNRD continued working with USFS staff to complete necessary regulatory consultations (including ESA, NEPA, tribal consultations, etc.), and work needed to secure necessary permits was continued. We also applied for and received cost-share funding through the Washington State Salmon Recovery Funding Board (SRFB). SRFB funds are administered by the Recreation and Conservation Office, and more details regarding the cost share agreement are provided elsewhere in this Contract. USFS has previously agreed to provide an additional $100,000 in funding towards implementation, and has agreed to allow some tree harvest to provide materials for project use.

Project Background:

The Upper Wenatchee River is a major spawning area for spring Chinook and steelhead. The project area is also likely to provide spawning habitat for summer Chinook and rearing and migration habitat for bull trout. As a result, the RTT identified the Upper Wenatchee Assessment Unit as the #2 priority sub-watershed for restoration actions in the Wenatchee basin prior to initiation of the Phase 1 contract for this project. In its updated prioritization, RTT has ranked the Upper Wenatchee as Tier 1 priority for both spring Chinook and steelhead and as Tier 2 priority for bull trout. Accordingly, focal species for this project are steelhead and spring Chinook.

A variety of actions are expected to be completed between approximately river miles 37.0 and 37.9 as a result of this project. These include installation of engineered log jams (ELJ) and pilot channel excavation to direct mainstem flows onto river left floodplain, and construction of  ELJs and placement of boulder clusters in the main channel and installation of large wood along an existing river left side channel to add in-stream structure.

This contract will contain subcontracts.
Account Type(s):
Capital
Contract Start Date:
01/04/2024
Contract End Date:
01/03/2026
Current Contract Value:
$1,300,000
Expenditures:
$1,109,114

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Coop
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Scott Bailey Chelan County Yes Contract Manager scott.bailey@co.chelan.wa.us (509) 679-2131
Victoria Bohlen Bonneville Power Administration Yes COR vlbohlen@bpa.gov (503) 230-3506
Meghan Camp Upper Columbia Salmon Recovery Board No Interested Party meghan.camp@ucsrb.org (509) 630-8226
Jay Chong Bonneville Power Administration Yes Contracting Officer jxchong@bpa.gov (503) 230-4007
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Timothy Hanrahan Bonneville Power Administration Yes F&W Approver TPHanrahan@bpa.gov (503) 230-3938
Mike Kaputa Chelan County Yes Supervisor mike.kaputa@co.chelan.wa.us (509) 667-6584
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Comply with Applicable Regulations and Permits A: 165. Environmental Compliance 01/03/2025
Effective implementation management and timely contract administration B: 119. Project Management and Administration 01/03/2025
Watershed Coordination Summary Memo C: 191. CCNRD will coordinate with USFS, UCSRB, WDFW, RTT, USACE, USFWS, NOAA and BPA 01/03/2025
In-Stream Restoration Actions Complete D: 29. Increase Aquatic Complexity and Floodplain Connectivity 01/03/2025
Completed channel construction E: 30. Pilot Channel Construction 01/03/2026
Floodplain Reconnection F: 180. Floodplain Reconnection 01/03/2026
Completed Wetland Enhancement G: 181. Wetland Enhancement 01/03/2026
Construction Management Complete H: 100. Construction Management 01/03/2026

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 180 Enhance Floodplain/Remove, Modify, Breach Dike
  • 1 instance of WE 181 Create, Restore, and/or Enhance Wetland
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance
B 119 Project Management and Administration
C 191 CCNRD will coordinate with USFS, UCSRB, WDFW, RTT, USACE, USFWS, NOAA and BPA
D 29 Increase Aquatic Complexity and Floodplain Connectivity
E 30 Pilot Channel Construction
F 180 Floodplain Reconnection
G 181 Wetland Enhancement
H 100 Construction Management
I 185 Periodic Status Reports for BPA
J 132 Annual Project Summary to UCSRB