Contract 95685: 1993-056-00 EXP USFWS ADVANCE HATCHERY REFORM RESEARCH
Project Number:
Title:
Advance Hatchery Reform Research
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
95685
Contract Title:
1993-056-00 EXP USFWS ADVANCE HATCHERY REFORM RESEARCH
Contract Continuation:
Previous: Next:
93368: 1993-056-00 EXP USFWS ADVANCE HATCHERY REFORM RESEARCH
Contract Status:
Issued
Contract Description:
The USFWS contract supports two objectives for Project 1993-056-00 (Advance Hatchery Reform Science): 1) Improve survival and reduce fitness loss in Columbia River steelhead smolts by minimizing unnatural selection on body size and other smolt characteristics, and 2) Identify behavioral and physiological traits under selection through laboratory-scale research.

In the FY25 performance period, staff of the USFWS will collaborate with NOAA on the following activities in support of the two project objectives.

Objective 1:

Finding an effective rearing method that maximizes smoltification without accelerating maturation is key to reducing domestication which is strongly associated with fitness loss of hatchery reared steelhead.  Project 1993-056-00 has raised several brood years of age-2 steelhead smolts at the WNFH in standard raceways, and at the NOAA Manchester Research Station in circular tanks, but achieved very different results.  Age-2 steelhead raised in circular tanks at Manchester have significantly lower precocious maturation rates and higher rates of smoltification than steelhead reared at WNFH.  In the FY24 performance period the USFWS and NOAA determined it was feasible to install circular tanks at the WNFH for a pilot study, NOAA transferred the necessary rearing tanks to the USFWS, and the USFWS started preparations for a pilot study using circular tanks for rearing age-2 steelhead.  

In the FY25 performance period, the USFWS and NOAA will install the remaining tanks, and begin rearing age-2 steelhead smolts for the pilot study.  The age-2 smolts will be assessed in the FY26 performance period when they are ready for release. Infrastructure upgrades are scheduled for the WNFH in the near future and include replacement of some aging concrete raceways with large circular rearing vessels. If rearing in circular tanks improves smoltification and reduces maturation, as seen at the laboratory-scale experiments at Manchester and pilot-scale experiments at the WNFH, the new circular tanks at WNFH may also improve survival and reduce fitness loss in these populations of summer steelhead.  The pilot study will provide guidance to scale up production of age-2 smolts upon completion of the infrastructure upgrades and reduce the risks (poor growth, survival, or smoltification) associated with abrupt changes to established raceway rearing practices.  

Objective 2:

In FY25, the USFWS will continue to provide steelhead obtained from natural-origin broodstock for the laboratory studies to determine behavioral and physiological traits under selection in hatcheries.

The USFW service will also continue to collaborate in data analysis and the production of manuscripts based on the data collected from the hatchery- and laboratory-scale studies.


Account Type(s):
Expense
Contract Start Date:
10/01/2024
Contract End Date:
09/30/2025
Current Contract Value:
$26,710
Expenditures:
$6,277

* Expenditures data includes accruals and are based on data through 31-Dec-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Iaa
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Deliverable: Obtain BPA Environmental Clearance B: 165. Provide appropriate documentation to BPA environmental compliance staff 09/30/2025
Produce accessible, error-checked datasets C: 157. Initiate pilot study of circular tank rearing for steelhead 09/30/2025
Effective implementation management and timely contract administration D: 119. Manage contract 09/30/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 165 Provide appropriate documentation to BPA environmental compliance staff
C 157 Initiate pilot study of circular tank rearing for steelhead 07/24/2024
D 119 Manage contract
E 132 Provide information to NOAA for the calendar year 2024 annual report