View and print project details including project summary, purpose, associations to Biological Opinions, and area. To learn more about any of the project properties, hold your mouse cursor over the field label.
Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
38350 SOW | NTT America, Inc. | 2008-008-00 TAURUS OFFSITE HOSTING SERVICE | History | $62,472 | 7/18/2008 - 7/17/2010 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 0 |
Completed: | 0 |
On time: | 0 |
Status Reports | |
---|---|
Completed: | 0 |
On time: | 0 |
Avg Days Late: | None |
Project Relationships: |
This project Merged To 2008-009-00 effective on 7/1/2010 Relationship Description: Starting in July, 2010, hosting service will be implemented under project 2008-009-00. |
---|
Name | Role | Organization |
---|---|---|
Benjamin Zelinsky | Project Manager | Bonneville Power Administration |
Gregory Dondlinger (Inactive) | Supervisor | Bonneville Power Administration |