Province | Subbasin | % |
---|---|---|
Columbia Plateau | Umatilla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Diana Butts | Oregon Department of Fish and Wildlife | No | Administrative Contact | diana.e.butts@state.or.us | (503) 947-6135 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Jonathan McCloud | Bonneville Power Administration | Yes | COR | jmmccloud@bpa.gov | (503) 230-3110 |
Sandra Sovay | Oregon Department of Fish and Wildlife | No | Administrative Contact | sandy.e.sovay@state.or.us | (503) 947-6189 |
Danny St. Hilaire | Oregon Department of Fish and Wildlife | Yes | Technical Contact | danny.r.sthilaire@state.or.us | (541) 276-2344 |
Linda Stokes | Oregon Department of Fish and Wildlife | No | Administrative Contact | linda.r.stokes@state.or.us | |
Trevor Watson | Oregon Department of Fish and Wildlife | No | Supervisor | trevor.m.watson@odfw.oregon.gov | (541) 575-1167 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Deliverable complete | A: 175. Prepare Channel Surveys/Assessments and Project Design | 09/30/2005 | ||
Deliverable complete | B: 157. Locate and Collect Reference Reach Data | 09/30/2005 | ||
Deliverable complete | C: 118. Land Owner Coordination (Birch Creek) | 09/09/2005 | ||
Deliverable complete | D: 114. Manage and Prioritize Potential Projects | 09/09/2005 | ||
Deliverable complete | E: 118. Land Owner Coordination (Meacham Creek) | 09/09/2005 | ||
Deliverable complete | F: 174. Develop Gauge Station Implementatin Plan | 09/09/2005 | ||
Deliverable complete | G: 114. Initiate Landowner Contacts and Develop Working Relationships | 09/09/2005 | ||
Deliverable complete | H: 40. Construct Livestock Exclusion Fence | 09/30/2005 | ||
Deliverable complete | I: 34. Construct Off-Site Livestock Water Developments | 09/30/2005 | ||
Deliverable complete | J: 148. Install Stream Flow/Temperature Gauging Stations | 09/09/2005 | ||
Deliverable complete | K: 18. Maintain Birch Creek Livestock Exclusion Fences | 09/09/2005 | ||
Deliverable complete | L: 19. Maintain Birch Creek Bank Stability Structures and Stable Channel Design Projects | 09/30/2005 | ||
Deliverable complete | M: 22. Maintain Birch Creek Riparian Planting Projects | 09/30/2005 | ||
Deliverable complete | N: 53. Birch Creek Invasive Weed Control | 09/30/2005 | ||
Deliverable complete | O: 47. Plant Birch Creek Riparian Vegetatin | 09/09/2005 | ||
Deliverable complete | P: 22. Irrigate Birch Creek Riparian Plantings | 09/30/2005 | ||
Deliverable complete | Q: 157. Operate Birch Creek Stream Flow Gauges | 09/30/2005 | ||
Deliverable complete | R: 18. Maintain Meachan Creek Livestock Exclusion Fences | 09/09/2005 | ||
Deliverable complete | S: 157. Photo Docmentation at Birch, East Birch, West Birch, Meacham and Two-Mile Creeks | 09/09/2005 | ||
Deliverable complete | T: 157. Collect & Summarize Temperature Data | 09/09/2005 | ||
Deliverable complete | U: 157. Biological Surveys/Fish Sampling | 09/30/2005 | ||
Deliverable complete | V: 157. Channel/Habitat Data Collection/Monitoring | 09/30/2005 | ||
Deliverable complete | W: 156. Establish Channel/Habitat Monitoring Transects on East Birch Creek | 09/30/2005 | ||
Deliverable complete | X: 118. Interagency Communicatin/Coordination | 09/30/2005 | ||
Deliverable complete | Y: 99. Program Presentations/Inforation Sessions | 09/09/2005 | ||
Deliverable complete | Z: 118. Landowner Coordination/Education | 09/09/2005 | ||
Deliverable complete | AA: 118. Participation in Umatilla RM&E Planning Process | 09/09/2005 | ||
Deliverable complete | AB: 119. Project management/Review of Project Activities | 09/30/2005 | ||
Deliverable complete | AC: 119. Riparian Lease Preparation/Review | 09/30/2005 | ||
Deliverable complete | AD: 119. Contract preparation/Review | 09/09/2005 | ||
Deliverable complete | AE: 132. Annual Summary Report Preparation/Submission | 09/09/2005 | ||
Deliverable complete | AF: 119. Manage and Administer Projects | 09/30/2005 | ||
Deliverable complete | AG: 119. Prepare Annual Work Plans/Supervise Program Activities | 09/30/2005 | ||
Deliverable complete | AH: 174. Develope Five-Year Implementation Plan | 09/30/2005 |
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 175 | Prepare Channel Surveys/Assessments and Project Design | |||||||
B | 157 | Locate and Collect Reference Reach Data | |||||||
C | 118 | Land Owner Coordination (Birch Creek) | |||||||
D | 114 | Manage and Prioritize Potential Projects | |||||||
E | 118 | Land Owner Coordination (Meacham Creek) | |||||||
F | 174 | Develop Gauge Station Implementatin Plan | |||||||
G | 114 | Initiate Landowner Contacts and Develop Working Relationships | |||||||
H | 40 | Construct Livestock Exclusion Fence | |||||||
I | 34 | Construct Off-Site Livestock Water Developments | |||||||
J | 148 | Install Stream Flow/Temperature Gauging Stations | |||||||
K | 18 | Maintain Birch Creek Livestock Exclusion Fences | |||||||
L | 19 | Maintain Birch Creek Bank Stability Structures and Stable Channel Design Projects | |||||||
M | 22 | Maintain Birch Creek Riparian Planting Projects | |||||||
N | 53 | Birch Creek Invasive Weed Control | |||||||
O | 47 | Plant Birch Creek Riparian Vegetatin | |||||||
P | 22 | Irrigate Birch Creek Riparian Plantings | |||||||
Q | 157 | Operate Birch Creek Stream Flow Gauges | |||||||
R | 18 | Maintain Meachan Creek Livestock Exclusion Fences | |||||||
S | 157 | Photo Docmentation at Birch, East Birch, West Birch, Meacham and Two-Mile Creeks | |||||||
T | 157 | Collect & Summarize Temperature Data | |||||||
U | 157 | Biological Surveys/Fish Sampling | |||||||
V | 157 | Channel/Habitat Data Collection/Monitoring | |||||||
W | 156 | Establish Channel/Habitat Monitoring Transects on East Birch Creek | |||||||
X | 118 | Interagency Communicatin/Coordination | |||||||
Y | 99 | Program Presentations/Inforation Sessions | |||||||
Z | 118 | Landowner Coordination/Education | |||||||
AA | 118 | Participation in Umatilla RM&E Planning Process | |||||||
AB | 119 | Project management/Review of Project Activities | |||||||
AC | 119 | Riparian Lease Preparation/Review | |||||||
AD | 119 | Contract preparation/Review | |||||||
AE | 132 | Annual Summary Report Preparation/Submission | |||||||
AF | 119 | Manage and Administer Projects | |||||||
AG | 119 | Prepare Annual Work Plans/Supervise Program Activities | |||||||
AH | 174 | Develope Five-Year Implementation Plan | |||||||
AI | 185 |