Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 20536: PI 1999-010-00 PINE HOLLOW WATERSHED ENHANCEMENT
Project Number:
Title:
Pine Hollow and Jackknife Watershed Restoration
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
20536
Contract Title:
PI 1999-010-00 PINE HOLLOW WATERSHED ENHANCEMENT
Contract Continuation:
Previous: Next:
11356: 1999-010-00 PINE HOLLOW WATERSHED ENHANCEMENT
  • 24460: 199901000 EXP PINE HOLLOW WATERSHED ENHANCEMENT
Contract Status:
History
Contract Description:
Workplan:
The following work plan outlines the series of activities, including methods, products, timeline and cost, to be implemented as part of the Pine Hollow / Jackknife Watershed Project by the Sherman County Soil and Water Conservation District (SWCD) from October 1, 2004 to September 30, 2005.

Partners:
Sherman County SWCD
Pine Hollow / Jackknife Watershed Council
USDA Natural Resources Conservation Service
Oregon Dept of Fish & Wildlife, John Day Basin
Bureau of Land Management
Wasco County SWCD
PG & E Gas Transmission Northwest
Oregon Watershed Enhancement Board
Landowners

Background:
One major source of water quality impairment is runoff originating from uplands.  In extreme runoff events, upland and riparian vegetation has been removed by flooding, resulting in undesirable plants and nonfunctioning riparian areas.  Riparian areas have been over grazed and damaged due to a lack of available livestock drinking water outside the streams.  Implementation of best management practices began to reduce erosion in the 1960's.  Erosion continues to be a factor affecting water quality and agricultural stability within the watershed and surrounding areas.  Many landowners see the need to tighten their conservation plans and practices, but lack the funds to do so because market prices for wheat and livestock have been below the cost of production for most of the past 25 years.

Location of Project Work:
Watershed enhancement projects are planned on 7 ranching operations in the Pine Hollow / Jackknife watershed, which is located in the southeastern corner of Sherman County.  Projects will include off-stream water systems (pipeline, trough, and protective fencing), spring developments, water and sediment control basins (WASCBs), and pasture cross fencing.

ESA and Cultural Resources Coverage Documentation:
All projects sponsored by the Sherman County Soil & Water Conservation District are planned and implemented using the USDA-Natural Resources Conservation Service standards and specifications.  All projects are subjected to literature surveys for Threatened and Endangered Species and Cultural Resources.  Surveys that show a possible or known presence of T & E Species or Cultural Resources will not be implemented until documentation is completed stating that projects are in compliance with federal NEPA and SHPO requirements.  All documentation will be submitted for approval by NEPA specialists at BPA before groundbreaking begins.

Project Goals:
To implement Fish Habitat Improvement Projects with landowners in the Pine Hollow and Jackknife watersheds.  This will be accomplished through practices that reduce the impact of peak flow events, enhance summer flows, and reduce summer stream temperatures, while reducing soil erosion and sediment delivery to streams.  Projects will be implemented using NRCS standards and specifications that provide design, technical, and engineering assistance for project implementation.  Maps will be created for project management and for T&E and Cultural Resource Surveys.  Funds for technical assistance and maps come out of BPA project 2002-015-00, through in kind work by the Sherman County SWCD and Watershed Councils, and through cost share funding provided by the Oregon Watershed Enhancement Board (OWEB).
Account Type(s):
Expense
Contract Start Date:
12/01/2004
Contract End Date:
09/30/2005
Current Contract Value:
$6,338
Expenditures:
$6,338

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
None
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Deliverable Complete & Accepted A: 165. Obtain Environmental Compliance For Upland Projects 09/28/2005
Deliverable complete O: 34. 6 Off-Stream Watering Facilities From Existing Water Source, Landowners #6 (PH-11) & #7 (PH-13) 09/30/2005
Deliverable complete P: 34. Install Off-Stream Water Facilities - 4 Spring Development, Landowners #6 (PH-12) & #7 (PH-13) 09/30/2005
Deliverable complete Q: 40. Install 1,600 Feet Of Cross Fence, Landowner #2, Project #: PH-03 09/28/2005
Deliverable complete R: 40. Install 1,700 Feet Of Cross Fence, Landowner #2, Project #: PH-04 09/28/2005
Deliverable complete S: 132. FY04 Annual Report 09/28/2005
Deliverable complete T: 119. Manage & Administer Project 09/28/2005

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Environmental Compliance For Upland Projects
B 55 Construct WASCB - Landowner #1, Project #: PH-01 - POSTPONED
C 55 Construct WASCB - Landowner #2, Project #: PH-02 - POSTPONED
D 55 Construct WASCB - Landowner #2, Project #: PH-02 - POSTPONED
E 55 Construct WASCB - Landowner #3, Project #: PH-05 - POSTPONED
F 55 Construct WASCB - Landowner #3, Project #: PH-05 - POSTPONED
G 55 Construct WASCB - Landowner #4, Project #: PH-06
H 55 Construct WASCB - Landowner #4, Project #: PH-06
I 55 Construct WASCB - Landowner #4, Project #: PH-07 - POSTPONED
J 55 Construct WASCB - Landowner #5, Project #: PH-08 - POSTPONED
K 55 Construct WASCB - Landowner #5, Project #: PH-09 - INFEASIBLE
L 55 Construct WASCB - Landowner #5, Project #: PH-10 - POSTPONED
M 55 Construct WASCB - Landowner #5, Project #: PH-10 - POSTPONED
N 55 Construct WASCB - Landowner #6, Project #: PH-12 - POSTPONED
O 34 6 Off-Stream Watering Facilities From Existing Water Source, Landowners #6 (PH-11) & #7 (PH-13)
P 34 Install Off-Stream Water Facilities - 4 Spring Development, Landowners #6 (PH-12) & #7 (PH-13)
Q 40 Install 1,600 Feet Of Cross Fence, Landowner #2, Project #: PH-03
R 40 Install 1,700 Feet Of Cross Fence, Landowner #2, Project #: PH-04
S 132 FY04 Annual Report
T 119 Manage & Administer Project
U 185 Pisces Status Reports - Red/Yellow/Green