Province | Subbasin | % |
---|---|---|
Mountain Snake | Clearwater | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Rossana Callejas | Bonneville Power Administration | No | Interested Party | rxcallejas@bpa.gov | (503) 230-7558 |
Ed Donahue | Fishpro, Inc. | No | Supervisor | ed.donahue@hdrinc.com | (253) 858-5262 |
Daniel Gambetta | Bonneville Power Administration | Yes | Env. Compliance Lead | dagambetta@bpa.gov | (503) 230-3493 |
Sherry Jeffery | HDR Engineering, Inc. | Yes | Contract Manager | sherry.jeffery@hdrinc.com | (253) 858-5262 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Jonathan McCloud | Bonneville Power Administration | Yes | COR | jmmccloud@bpa.gov | (503) 230-3110 |
Donald Rose | Bonneville Power Administration | Yes | Interested Party | dlrose@bpa.gov | (503) 230-3796 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Gregory (HDR) Wolfe | HDR Engineering, Inc. | No | Interested Party | gregory.wolfe@hdrinc.com | (509) 546-2071 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Permits/Authorizations Acquired and submitted to BPA | A: 165. Environmental Compliance | 06/30/2013 | 06/30/2013 | |
QA/QC Submittals | B: 122. QA/QC Reviews | 06/30/2013 | 06/30/2013 | |
Alternatives Feasibility Assessment | C: 174. Alternatives Feasibility Assessment | 09/30/2011 | 09/30/2011 | |
Pre-design and Permitting Requirements Summary Memo | D: 174. Predesign and Permitting Requirements Summary Memo | 06/30/2013 | 06/30/2013 | |
Lolo Creek Weir Final Design | E: 175. Final Design | 06/30/2013 | ||
Management of Project & Year End Accrual | G: 119. Manage Project and Subconsultants | 06/30/2013 | 06/30/2013 | |
Workshop with Stakeholders | I: 191. Workshop with Stakeholders | 06/30/2013 | 06/30/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental Compliance | 08/15/2010 | ||||||
B | 122 | QA/QC Reviews | 08/15/2010 | ||||||
C | 174 | Alternatives Feasibility Assessment | 08/15/2010 | ||||||
D | 174 | Predesign and Permitting Requirements Summary Memo | 08/15/2010 | ||||||
E | 175 | Final Design | 08/15/2010 | ||||||
F | 132 | NO REPORT REQUIRED | 08/15/2010 | ||||||
G | 119 | Manage Project and Subconsultants | 08/15/2010 | ||||||
H | 185 | Periodic Status Reports for BPA | 08/15/2010 | ||||||
I | 191 | Workshop with Stakeholders | 08/16/2010 |