Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 26506: 199801800 CAP JOHN DAY WATERSHED RESTORATION
Project Number:
Title:
John Day Watershed Restoration
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
26506
Contract Title:
199801800 CAP JOHN DAY WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
21629: PI 1998-018-00 JOHN DAY WATERSHED RESTORATION
Contract Status:
History
Contract Description:
This project is a continuation of the ongoing watershed restoration program in the John Day basin.  The individual implementation projects are intended to improve water quality and quantity, aquatic habitat, and fish production; reduce bank instability, sedimentation, bedload movement, and summer water temperatures thereby improving water quality; reduce or eliminate migratory delays from passage impediments; and improve riparian condition.  The project also includes continued implementation of an annual monitoring program to evaluate each of the implementation projects.

Projects planned for 2006 include the Tier 1 projects for the Grant SWCD that include a pump station at the City of Dayville plus 4 lay-flat diversions st Chandlers, Emmels, Smith, and Smith/Medor.
Tier 2 projects are in place to use available funds and to prevent lost oppertunities in the event of a project dely form tier 1. These projects include one RFC  at Nelsons, and 5 lay-flat diversion structures. The number of tier 2 projects reflects the dollar requests for the tier 1 projects.

Projects planned for 2006 for the Wheeler SWCD include 4 culvert replacements or repairs including rock wier step pools for passage of all life stages.

Additional education and outreach projects are planned as well as 3 off channel water developments.
Account Type(s):
Capital, Expense
Contract Start Date:
02/01/2006
Contract End Date:
01/31/2007
Current Contract Value:
$590,947
Expenditures:
$590,947

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
John Baugher Bonneville Power Administration Yes COR jrbaugher@bpa.gov (503) 230-4512
Linda Brown Confederated Tribes of Warm Springs Yes Technical Contact jdborestoration@ortelco.net (541) 820-3568
Lisa Gang Bonneville Power Administration Yes Contracting Officer lrgang@bpa.gov (503) 230-3893
Brad Houslet Confederated Tribes of Warm Springs No Supervisor brad.houslet@ctwsbnr.org (541) 553-2039
Rosemary Mazaika Bonneville Power Administration Yes F&W Approver rxmazaika@bpa.gov (503) 230-5869
Donald Rose Bonneville Power Administration No Env. Compliance Lead dlrose@bpa.gov (503) 230-3796
Lori Switzler Confederated Tribes of Warm Springs No Administrative Contact lswitzler@wstribes.org (541) 553-3487


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
BPA Project Administration Requirements A: 119. Manage Administer Projects 01/31/2007 01/31/2007
Signed landowner agreements. B: 118. Landowner and Agency Project Coordination 01/31/2007 04/30/2007
Choose sites for 2007 construction year. C: 114. Identify and Select Projects 11/30/2006 10/05/2006
Environmental Compliance D: 165. Produce Environmental Compliance Documentation 07/28/2006 10/05/2006
Participate in community education activities E: 99. Outreach and Education 01/31/2007 08/31/2007
Monitoring Data stored Electronicly and in Hard Copy Form F: 160. Manage and Maintain Database 01/31/2007 01/02/2007
Monitoring Report G: 157. Collect/Generate/Validate field and lab data 01/31/2007 10/05/2006
Monitoring Report H: 162. Analyze / Interpret Data 01/31/2007 01/31/2007
Submit Copies of shared data to cooperating agencies I: 159. Submit/Acquire Data 12/01/2006 11/02/2007
Annual Report J: 132. Produce Annual Report 06/30/2006 10/05/2006
Greenhouse and Nursery Maintained L: 186. Native Plants Nursery Maintenance and operation 01/31/2007 10/05/2006
Control of non-native plants and noxious weeds. M: 22. Maintain Vegetation 12/28/2006 10/05/2006
3,000 cuttings and plants planted at construction sites and other riparian locations. N: 47. Plant Vegetation 06/30/2006 07/01/2006
Alternative water sources developed. O: 34. Develop Alternative Water Source 01/31/2007 10/05/2006
Project Designs for 2006 Construction Projects P: 175. Produce Design and/or Specifications - GSWCD 01/31/2007 07/01/2006
Chandler Diversion Q: 84. Remove/Install Diversion (River Mile 08/31/2006 09/01/2006
Emmel/Smith Lower Island Ditch Diversion R: 84. Remove/Install Diversion (River Mile 08/31/2006 09/01/2006
Mike Smith 486 Ditch Diversion S: 84. Remove/Install Diversion (River Mile 08/31/2006 09/01/2006
Mike Smith Medor Ditch Diversion T: 84. Remove/Install Diversion (River Mile 08/31/2006 09/01/2006
Dayville Pump Station U: 84. Remove/Install Diversion ( R.M. .5 SFJD) 01/31/2007
Baccum Diversion Canyon Creek - Tier Two V: 84. Remove/Install Diversion -Tier Two 09/28/2006 09/01/2006
Lawrence Diversion - Tier Two W: 84. Remove/Install Diversion -Tier Two 09/28/2006 09/01/2006
Morgan Diversion Tier Two X: 84. Remove/Install Diversion -Tier Two 01/02/2007
Elmwood Diversion - Tier Two Y: 84. Remove/Install Diversion -Tier Two 09/28/2006 09/01/2006
Jacobs Roberts Creek - Tier Two Z: 84. Remove/Install Diversion -Tier Two 09/28/2006 07/01/2006
Nelson Return Flow Cooling System AA: 149. Install Pipeline - Tier Two 01/02/2007
Clausen Return Flow System AB: 149. Install Pipeline - Tier Two 01/02/2007
Project Designs for 2006 Construction Projects AC: 175. Produce Design and/or Specifications - WSWCD 01/31/2007 10/05/2006
Installed Fish Passage Structure - Culvert #4 AD: 184. Butte Creek Culvert Replacement 08/31/2006 10/05/2006
COPY: Installed Fish Passage Structure - Culvert #6 AE: 184. Butte Creek Culvert Replacement 08/31/2006 09/01/2006
Installed Fish Passage Structure - Culvert #7 AF: 184. Butte Creek Culvert Replacement 08/31/2006 10/05/2006
Installed Fish Passage Structure - Culvert #8 AG: 184. Butte Creek Culvert Realingnment - step-wier installation 08/31/2006 09/01/2006

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Fish
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 8 instances of WE 84 Remove/Install Diversion
  • 4 instances of WE 184 Install Fish Passage Structure
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 159 Transfer/Consolidate Regionally Standardized Data
  • 1 instance of WE 162 Analyze/Interpret Data
All Anadromous Salmonids
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage Administer Projects
B 118 Landowner and Agency Project Coordination
C 114 Identify and Select Projects
D 165 Produce Environmental Compliance Documentation
E 99 Outreach and Education
F 160 Manage and Maintain Database
G 157 Collect/Generate/Validate field and lab data
H 162 Analyze / Interpret Data
I 159 Submit/Acquire Data
J 132 Produce Annual Report
K 185 Periodic Status Reports for BPA
L 186 Native Plants Nursery Maintenance and operation
M 22 Maintain Vegetation
N 47 Plant Vegetation
O 34 Develop Alternative Water Source
P 175 Produce Design and/or Specifications - GSWCD
Q 84 Remove/Install Diversion (River Mile
R 84 Remove/Install Diversion (River Mile
S 84 Remove/Install Diversion (River Mile
T 84 Remove/Install Diversion (River Mile
U 84 Remove/Install Diversion ( R.M. .5 SFJD)
V 84 Remove/Install Diversion -Tier Two
W 84 Remove/Install Diversion -Tier Two
X 84 Remove/Install Diversion -Tier Two
Y 84 Remove/Install Diversion -Tier Two
Z 84 Remove/Install Diversion -Tier Two
AA 149 Install Pipeline - Tier Two
AB 149 Install Pipeline - Tier Two
AC 175 Produce Design and/or Specifications - WSWCD
AD 184 Butte Creek Culvert Replacement
AE 184 Butte Creek Culvert Replacement
AF 184 Butte Creek Culvert Replacement
AG 184 Butte Creek Culvert Realingnment - step-wier installation