Project 1998-018-00 - John Day Watershed Restoration

Please Note: This project is the product of one or more merges and/or splits from other projects. Historical data automatically included here are limited to the current project and previous generation (the “parent” projects) only. The Project Relationships section details the nature of the relationships between this project and the previous generation. To learn about the complete ancestry of this project, please review the Project Relationships section on the Project Summary page of each parent project.

Project Number:
1998-018-00
Title:
John Day Watershed Restoration
Summary:
See Contract description
Proposer:
None
Proponent Orgs:
Confederated Tribes of Warm Springs (Tribe)
Starting FY:
2004
Ending FY:
2017
Stage:
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Purpose:
Habitat
Emphasis:
Restoration/Protection
Focal Species:
All Anadromous Fish
All Anadromous Salmonids
Bass, Smallmouth
Carp, Common
Catfish
Cutthroat Trout, Westslope
Freshwater Mussels
Pikeminnow, Northern
Trout, Brook
Trout, Bull
Trout, Interior Redband
Trout, Rainbow
Wildlife
Species Benefit:
Anadromous: 100.0%   Resident: 0.0%   Wildlife: 0.0%
Tags:
None
Special:
None
BiOp Association:
None

Description: Page: 7 Resource-Photo 1: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 685 x 507

Description: Page: 8 Resource-Photo 2: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 503 x 350

Description: Page: 10 Resource-Photo 3: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 675 x 452

Description: Page: 11 Resource-Photo 4: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 499 x 375

Description: Page: 13 Background-Photo 1: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 630 x 433

Description: Page: 14 Background-Photo 2: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 563 x 400

Description: Page: 14 Background-Photo 3: No caption provided.

Project(s): 1998-018-00

Document: P103767

Dimensions: 552 x 414

Description: Page: 15 Description-Photo 1: Juniper encroachment in the John Day Basin.

Project(s): 1998-018-00

Document: P103767

Dimensions: 613 x 403

Description: Page: 16 Description-Photo 2: Juniper Cutting at Holliday Castle Creek site

Project(s): 1998-018-00

Document: P103767

Dimensions: 440 x 330

Description: Page: 17 Description-Photo 3: Water Development for Wildlife and Livestock Use.

Project(s): 1998-018-00

Document: P103767

Dimensions: 1000 x 632

Description: Page: 18 Description-Photo 4a: Installation of Off-Channel water developments.

Project(s): 1998-018-00

Document: P103767

Dimensions: 536 x 380

Description: Page: 18 Description-Photo 4b: Installation of Off-Channel water developments.

Project(s): 1998-018-00

Document: P103767

Dimensions: 534 x 376

Description: Page: 20 Description-Photo 6: Planted Cuttings along the Middle Fork John Day River

Project(s): 1998-018-00

Document: P103767

Dimensions: 469 x 352

Description: Page: 20 Description-Photo 5: Young trees Planted in the Native Plants Nursery at the Forrest Mainstem Property.

Project(s): 1998-018-00

Document: P103767

Dimensions: 469 x 352

Description: Page: 25 Overview-Photo 1: Prior to construction with push up diversion installed.

Project(s): 1998-018-00

Document: P103767

Dimensions: 494 x 371

Description: Page: 26 Overview-Photo 2a: Smith Diversion During construction summer of 2006

Project(s): 1998-018-00

Document: P103767

Dimensions: 476 x 357

Description: Page: 26 Overview-Photo 2b: Smith Diversion During construction summer of 2006

Project(s): 1998-018-00

Document: P103767

Dimensions: 471 x 354

Description: Page: 26 Overview-Photo 3a: Smith Diversion Post construction showing fish passage slot located in middle of stream channel.

Project(s): 1998-018-00

Document: P103767

Dimensions: 475 x 357

Description: Page: 26 Overview-Photo 3b: Smith Diversion Post construction showing fish passage slot located in middle of stream channel.

Project(s): 1998-018-00

Document: P103767

Dimensions: 474 x 357

Description: Page: 27 Overview-Photo 4a: Bacuum diversion installed prior to replacement.

Project(s): 1998-018-00

Document: P103767

Dimensions: 471 x 353

Description: Page: 27 Overview-Photo 4b: Bacuum diversion installed prior to replacement.

Project(s): 1998-018-00

Document: P103767

Dimensions: 463 x 346

Description: Page: 27 Overview-Photo 5a: Photos of construction showing passage during construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 480 x 639

Description: Page: 27 Overview-Photo 5b: Photos of construction showing passage during construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 514 x 387

Description: Page: 27 Overview-Photo 5c: Photos of construction showing passage during construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 506 x 379

Description: Page: 28 Overview-Photo 6a: Diversion with passage ladder installed during irrigation season, post construction and replacement of previous push-up diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 477 x 357

Description: Page: 28 Overview-Photo 6b: Diversion with passage ladder installed during irrigation season, post construction and replacement of previous push-up diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 479 x 360

Description: Page: 28 Overview-Photo 7a: Chandler Diversion prior to replacement.

Project(s): 1998-018-00

Document: P103767

Dimensions: 482 x 363

Description: Page: 28 Overview-Photo 7b: Chandler Diversion prior to replacement.

Project(s): 1998-018-00

Document: P103767

Dimensions: 487 x 364

Description: Page: 28 Overview-Photo 8a: During Construction of the Chandler

Project(s): 1998-018-00

Document: P103767

Dimensions: 446 x 336

Description: Page: 28 Overview-Photo 8b: During Construction of the Chandler

Project(s): 1998-018-00

Document: P103767

Dimensions: 446 x 335

Description: Page: 29 Overview-Photo 9: During final construction – passage on near side.

Project(s): 1998-018-00

Document: P103767

Dimensions: 394 x 526

Description: Page: 29 Overview-Photo 10: Post construction of Chandler Diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 1005 x 754

Description: Page: 30 Overview-Photo 11: Emmel prior to replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 459 x 344

Description: Page: 30 Overview-Photo 12a: Post replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 487 x 368

Description: Page: 30 Overview-Photo 12b: Post replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 500 x 375

Description: Page: 31 Overview-Photo 13a: Lawrence pre construction – limited passage.

Project(s): 1998-018-00

Document: P103767

Dimensions: 465 x 349

Description: Page: 31 Overview-Photo 13b: Lawrence pre construction – limited passage.

Project(s): 1998-018-00

Document: P103767

Dimensions: 463 x 347

Description: Page: 31 Overview-Photo 14a: During construction – shows minimal bank disturbance.

Project(s): 1998-018-00

Document: P103767

Dimensions: 462 x 616

Description: Page: 31 Overview-Photo 14b: During construction – shows minimal bank disturbance.

Project(s): 1998-018-00

Document: P103767

Dimensions: 469 x 385

Description: Page: 32 Overview-Photo 15a: Finished project – passage for all life stages.

Project(s): 1998-018-00

Document: P103767

Dimensions: 500 x 373

Description: Page: 32 Overview-Photo 15b: Finished project – passage for all life stages.

Project(s): 1998-018-00

Document: P103767

Dimensions: 494 x 371

Description: Page: 32 Overview-Photo 16a: Mike Smith Lower Diversion - Prior to installation of fish friendly diversion structure.

Project(s): 1998-018-00

Document: P103767

Dimensions: 494 x 371

Description: Page: 32 Overview-Photo 16b: Mike Smith Lower Diversion - Prior to installation of fish friendly diversion structure.

Project(s): 1998-018-00

Document: P103767

Dimensions: 493 x 370

Description: Page: 33 Overview-Photo 17: Mike Smith Lower Diversion - Diversion of water on far side during construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 506 x 378

Description: Page: 33 Overview-Photo 18: Mike Smith Lower Diversion - Minimal flows through site during construction, sediment barriers in place down stream of project.

Project(s): 1998-018-00

Document: P103767

Dimensions: 511 x 384

Description: Page: 33 Overview-Photo 19a: Post construction at Smith lower diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 465 x 349

Description: Page: 33 Overview-Photo 19b: Post construction at Smith lower diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 464 x 349

Description: Page: 34 Overview-Photo 20a: Roberts Creek Prior to construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 455 x 339

Description: Page: 34 Overview-Photo 20b: Roberts Creek Prior to construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 455 x 340

Description: Page: 34 Overview-Photo 21a: Roberts Creek during Construction and stabilization of head cut.

Project(s): 1998-018-00

Document: P103767

Dimensions: 471 x 352

Description: Page: 34 Overview-Photo 21b: Roberts Creek during Construction and stabilization of head cut.

Project(s): 1998-018-00

Document: P103767

Dimensions: 475 x 356

Description: Page: 34 Overview-Photo 22a: Roberts Creek - Post construction and during winter flows.

Project(s): 1998-018-00

Document: P103767

Dimensions: 465 x 349

Description: Page: 34 Overview-Photo 22b: Roberts Creek - Post construction and during winter flows.

Project(s): 1998-018-00

Document: P103767

Dimensions: 468 x 353

Description: Page: 35 Overview-Photo 23a: South Reynolds Ditch - No passage during installation of this push up diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 488 x 366

Description: Page: 35 Overview-Photo 23b: South Reynolds Ditch - No passage during installation of this push up diversion.

Project(s): 1998-018-00

Document: P103767

Dimensions: 493 x 370

Description: Page: 35 Overview-Photo 24a: South Reynolds Ditch - Sediment at minimal bank disturbance also minimal with the installation of these type fish friendly diversions.

Project(s): 1998-018-00

Document: P103767

Dimensions: 482 x 363

Description: Page: 35 Overview-Photo 24b: South Reynolds Ditch - Sediment at minimal bank disturbance also minimal with the installation of these type fish friendly diversions.

Project(s): 1998-018-00

Document: P103767

Dimensions: 481 x 361

Description: Page: 35 Overview-Photo 25a: South Reynolds Ditch - Full passage post construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 482 x 316

Description: Page: 35 Overview-Photo 25b: South Reynolds Ditch - Full passage post construction.

Project(s): 1998-018-00

Document: P103767

Dimensions: 422 x 316

Description: Page: 36 Overview-Photo 26: Butte Creek Culvert #1 - Pre Replacement, Collapsed and high velocity.

Project(s): 1998-018-00

Document: P103767

Dimensions: 714 x 538

Description: Page: 36 Overview-Photo 27: Butte Creek Culvert #1 - Post Replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 707 x 353

Description: Page: 37 Overview-Photo 28: Butte Creek Culvert #2 - Pre Replacement, Perched Culvert

Project(s): 1998-018-00

Document: P103767

Dimensions: 754 x 568

Description: Page: 37 Overview-Photo 29: Butte Creek Culvert #2 - Post Replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 504 x 671

Description: Page: 38 Overview-Photo 30: Butte Creek Culvert #3 - Pre replacement, skewed, high velocities, perched.

Project(s): 1998-018-00

Document: P103767

Dimensions: 1024 x 768

Description: Page: 38 Overview-Photo 31: Butte Creek Culvert #3 - Post Replacement

Project(s): 1998-018-00

Document: P103767

Dimensions: 726 x 544

Description: Page: 39 Overview-Photo 32: Butte Creek Culvert #4 - Pre replacement - Perched, shallow jump pool

Project(s): 1998-018-00

Document: P103767

Dimensions: 744 x 558

Description: Page: 39 Overview-Photo 33: Butte Creek Culvert #4 - Post Construction

Project(s): 1998-018-00

Document: P103767

Dimensions: 739 x 552


Summary of Budgets

To view all expenditures for all fiscal years, click "Project Exp. by FY"

To see more detailed project budget information, please visit the "Project Budget" page

No Decided Budget Transfers

Pending Budget Decision?  No


Actual Project Cost Share

Current Fiscal Year — 2025
Cost Share Partner Total Proposed Contribution Total Confirmed Contribution
There are no project cost share contributions to show.
Previous Fiscal Years
Fiscal Year Total Contributions % of Budget
There are no cost share summaries to display from previous years.

Contracts

The table below contains contracts with the following statuses: Active, Closed, Complete, History, Issued.
* "Total Contracted Amount" column includes contracted amount from both capital and expense components of the contract.
Capital Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
4282 SOW Confederated Tribes of Warm Springs 1998-018-00 INSTALL IRRIGATION DITCH DIVERSIONS History $1,707,204 4/2/2001 - 1/31/2005
21629 SOW Confederated Tribes of Warm Springs PI 1998-018-00 JOHN DAY WATERSHED RESTORATION History $718,009 2/1/2005 - 1/31/2006
26506 SOW Confederated Tribes of Warm Springs 199801800 CAP JOHN DAY WATERSHED RESTORATION History $590,947 2/1/2006 - 1/31/2007
Expense Contracts:
Number Contractor Name Title Status Total Contracted Amount Dates
492 REL 2 SOW Confederated Tribes of Warm Springs 1998-018-00 JOHN DAY WATERSHED RESTORATION Terminated $417,252 4/1/2000 - 3/31/2001
21629 SOW Confederated Tribes of Warm Springs PI 1998-018-00 JOHN DAY WATERSHED RESTORATION History $718,009 2/1/2005 - 1/31/2006
26506 SOW Confederated Tribes of Warm Springs 199801800 CAP JOHN DAY WATERSHED RESTORATION History $590,947 2/1/2006 - 1/31/2007



Annual Progress Reports
Expected (since FY2004):2
Completed:2
On time:2
Status Reports
Completed:8
On time:4
Avg Days Late:23

                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
4282 21629, 26506 199801800 CAP JOHN DAY WATERSHED RESTORATION Confederated Tribes of Warm Springs 04/02/2001 01/31/2007 History 8 56 0 0 4 60 93.33% 0
Project Totals 13 81 0 0 31 112 72.32% 0


Historical from: 1998-017-00
                Count of Contract Deliverables
Earliest Contract Subsequent Contracts Title Contractor Earliest Start Latest End Latest Status Accepted Reports Complete Green Yellow Red Total % Green and Complete Canceled
6257 26818 1998-017-00 EXP GRAVEL PUSH-UP DAM REMOVAL Monument Soil and Water Conservation District (SWCD) 08/15/2001 12/31/2006 History 5 25 0 0 27 52 48.08% 0
Project Totals 13 81 0 0 31 112 72.32% 0


The table content is updated frequently and thus contains more recent information than what was in the original proposal reviewed by ISRP and Council.

Review: FY07-09 Solicitation Review

Council Recommendation

Assessment Number: 1998-018-00-NPCC-20090924
Project: 1998-018-00 - John Day Watershed Restoration
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments:
Assessment Number: 1998-017-00-NPCC-20090924
Project: 1998-017-00 - Gravel Push-Up Dam Removal Low
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: This work will be funded as part of project 199801800.
Assessment Number: 2007-365-00-NPCC-20090924
Project: 2007-365-00 - Canyon Creek Culvert Replacements
Review: FY07-09 Solicitation Review
Approved Date: 10/23/2006
Recommendation: Fund
Comments: ISRP comments will be addressed in comments to Council.This work will be funded as part of project 199801800.

Independent Scientific Review Panel Assessment

Assessment Number: 1998-018-00-ISRP-20060831
Project: 1998-018-00 - John Day Watershed Restoration
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
This project would benefit from a program level review with a site visit following, perhaps, distribution of a ten-year summary report in 2008 of their biological and physical habitat results.

The explanation for priority setting and reference to priorities in the Subbasin Plan is brief but reasonable. The sponsors go beyond just prioritization by opportunity. Their prioritization process works out two ways: they evaluate projects that come forward against their prioritization, and they actively pursue actions in priority areas. Nevertheless, this project was hard to review because many of the proposed actions aren't well described and by the next review cycle, those actions will have been implemented. A more explicit description of the criteria used to prioritize projects would be beneficial and should be documented by the next review cycle. A flow chart describing proposed activities from prioritization to monitoring to adaptive management would be helpful.

The sponsors provided sound bites of results but didn't provide the data or graphs supporting the results. Although this is a good first step, the ISRP is in the position to have to take these statements at face value. Some context should be added to the data. The sponsors can make more of the data that they do have. They should incorporate better reporting in their next annual report.

Much of the proposal's focus is for benefits to the range system, with some benefits to fish; however, this is a balanced approach for activities ongoing in the John Day Basin. Objectives as taken from the Subbasin Plan are reasonable, but in future the sponsors should make more effort to include these and priority areas in their proposal in measurable form.

The response to why detailed information is not available on all work elements (projects in development) was somewhat reasonable, provided that there is some mechanism for review of work plans as they are developed. However, even in the development stage, projects should have relevant design detail to report. Research design can't be only opportunistic.

Narrative summaries of biological outcomes of ongoing work were presented. These would have enhanced the proposal and should have been included with supporting data and interpretive evaluation. The project should routinely monitor and report these types of response measures. Much more emphasis should be given to the analysis and interpretation of these indicators in future proposals.
Documentation Links:
Assessment Number: 1998-017-00-ISRP-20060831
Project: 1998-017-00 - Gravel Push-Up Dam Removal Low
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Meets Scientific Review Criteria
Final Round ISRP Comment:
This well-written project proposal describes activities to improve habitat connectivity and riparian habitat conditions in selected tributaries to the North Fork and Mid-mainstem of the John Day River by replacing between 18 and 25 problematic irrigation diversions, culverts, and other artificial structures with fish-friendly structures. The culverts were identified through a prioritization process. The focal species include Mid-Columbia Summer Steelhead, redband trout, specific life histories of Mid-Columbia Spring Chinook, and Pacific Lamprey.

This is a solid proposal that demonstrates its activities are linked to priority needs from regional and subbasin planning documents and that is making steady progress toward achieving its objectives. Much of the proposal and planned work is straightforward with simple monitoring planned to document that anticipated results are actually achieved.

No termination date is identified for the project even though sponsor comments indicate that approximately 10-13 years work will be needed to address passage issues in the John Day Basin. Even though such a termination date is uncertain and is some years out, a termination date should be identified for projects, rather than leaving them open-ended.

The ISRP has a programmatic concern on all projects proposing culvert replacement.
1. Prioritization of specific culvert?
2. How much habitat is made available?
3. What is the "quality" of the habitat?
This project has addressed these concerns within its proposal.

Technical and scientific justification: Fixing fish passage barriers is the focus of this project. Primary barriers are culverts and push-up dams. Excellent descriptions of problems with push-up dams and culverts at the specific watershed sites to be addressed by this project are included in the proposal. These are effectively illustrated with maps, graphs, and photographs of problem areas and fish-friendly alternatives.

Push-up dams and old makeshift diversion dams are to be replaced with removable flashboard dams and/or rock step-pool weirs, while poorly-installed culverts and other problematic road crossings (collapsed log bridges, etc) will be replaced with properly-sized culverts, bottomless arch culverts or small bridges. Funding is requested for $1,328,764 over the 3-year project period.

Priority areas are consistent with those identified in the John Day Subbasin Plan. Fish passage has been identified in the subbasin plan as a high-priority limiting factor.

Relationship of activities under this project to the Fish and Wildlife Program and to the subbasin plan is clear. The actions in this project are directly tied to specific priority restoration strategies in the subbasin plan. The proposal also discusses relationship to the draft recovery plan (not yet released) for Mid-Columbia steelhead. Project actions relate to RPA 149 in the 2000 BiOp.

Relationships to other projects: Examples are given of other projects this group works with: ODFW fish screens, multi-agency riparian habitat restoration, Oregon Water Trust irrigation efficiency projects, other SWCD upland conservation. The project will build on previous passage work of these SWCDs and others.

Project history: To date, this project has replaced 15 problematic irrigation diversions with fish friendly alternatives, with another 8 scheduled for replacement in 2006 (Map G). This represents over 60% of the problematic diversions in the initial project area. As initially developed, the project focused on eliminating push-up dams on the lower mainstem of the North Fork John Day. In 2003, sponsors started to emphasize works in tributaries, as low-flow passage barriers typically have much more impact in small streams that do provide summer habitat to salmonids.

Objectives: Five project objectives are clearly specified with quantitative measures of progress. Brief but clear descriptions of the intent of each objective are included. Timelines are not included.

Tasks (work elements) and methods: Work elements are specifically described. Methods have previously demonstrated effectiveness. Note is made of the need for voluntary cooperation of landowners, and that this may limit project success. However, a history of positive working relationships of the SWCD and landowners make failure unlikely.

Monitoring and evaluation: The project includes basic monitoring of effectiveness of actions -- habitat response to project implementation. Population response monitoring is done by other projects (ODFW, NOAA/BOR). Work elements are included for project effectiveness monitoring to collect data on: site changes (photopoints) and stream temperature. Monitoring, data collection, and analysis are done in collaboration with Monument SWCD. Primary use of project-generated monitoring is to assess effectiveness and guide project implementation.

The project also includes a monitoring component, which aims to 1) document the changes at project sites over time through photo monitoring, and 2) determine whether in fact push-up dams result in warming of downstream flows. Photo documentation has show gradual riparian recovery at the sites of old push-up dams. The temperature monitoring that has been collected has documented that specific types of push-up dams (in particular, ones that create long artificial side-channels in summer low flow conditions) can elevate water temperatures. Other types of push up dams do not have as clear a temperature signal.

Facilities, equipment, and personnel: Facilities are reasonable. A history of collaboration among SWCDs and among SWCDs and landowners make these groups uniquely qualified to implement these types of projects on private lands.

Information transfer: Project results to be reported in SWCD newsletters, reports and other publications of the SWCDs and watershed councils, local and regional media. If monitoring shows broadly applicable results, sponsors intend to summarize in more broadly distributed reports.
Documentation Links:
Assessment Number: 2007-365-00-ISRP-20060831
Project: 2007-365-00 - Canyon Creek Culvert Replacements
Review: FY07-09 Solicitation Review
Completed Date: 8/31/2006
Final Round ISRP Date: None
Final Round ISRP Rating: Response Requested
Final Round ISRP Comment:
Canyon Creek passage improvements are a high priority in the subbasin plan. Steelhead (mid Columbia ESU), spring Chinook (mid-Columbia ESU), interior redband trout and westslope cutthroat are all likely to realize long-term benefits from expanded spawning and rearing habitat. It is stated in the proposal that the culverts are partial barriers to adults and complete barriers to juveniles, but no data, even a cursory analysis showing that, is provided. Although this may be a worthwhile project, there is no evidence of even a preliminary fisheries assessment indicating the extent of the passage problem. It would not be expensive for the Forest Service to conduct a brief, straightforward evaluation verifying that a problem exists and to what extent. These data could become the "before" component of an effectiveness monitoring plan, currently lacking.

Even some information explaining the nature of the culvert, the height of the drop, and literature indicating the likelihood of a problem would help. The lack of a fisheries participant in this proposal showed in the choice of only general fisheries references and lack of any fisheries data from this site or elsewhere that could justify this expenditure. A response is needed with problems and benefits more clearly documented, and detail on what will be monitored and how. Methods seem reasonable and appropriate, but broader data sharing is needed.
Documentation Links:

Legal Assessment (In-Lieu)

Assessment Number: 1998-018-00-INLIEU-20090521
Project Number: 1998-018-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: Problems May Exist
Cost Share Rating: 3 - Does not appear reasonable
Comment: Multiple watershed restoration activities; multiple other entities authorized/required to perform; need confirmation that screening or other criteria ensures that BPA not funding activities others are required to perform; need confirmation that cost share is adequate.
Assessment Number: 1998-017-00-INLIEU-20090521
Project Number: 1998-017-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: Problems May Exist
Cost Share Rating: 3 - Does not appear reasonable
Comment: Fish screening or other passage alternatives for private irrigation facilities/push up dams in creeks; irrigators authorized/required to perform; are BPA funds being used to provide screens or other facilities that are required/have been ordered to replace/upgrade their screens?
Assessment Number: 2007-365-00-INLIEU-20090521
Project Number: 2007-365-00
Review: FY07-09 Solicitation Review
Completed Date: 10/6/2006
In Lieu Rating: No Problems Exist
Cost Share Rating: None
Comment: Another entity authorized/required (FS roads), assume covered by BPA-FS MOU.

Capital Assessment

Assessment Number: 1998-018-00-CAPITAL-20090618
Project Number: 1998-018-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None
Assessment Number: 1998-017-00-CAPITAL-20090618
Project Number: 1998-017-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None
Assessment Number: 2007-365-00-CAPITAL-20090618
Project Number: 2007-365-00
Review: FY07-09 Solicitation Review
Completed Date: 2/27/2007
Capital Rating: Does Not Qualify for Capital Funding
Capital Asset Category: None
Comment: None

Project Relationships: This project Merged From 1998-017-00 effective on 2/26/2007
Relationship Description: Move work and budgets to 1998-018-00 to improve fish passage and riparian habitat for species with limited productivity.

This project Merged From 2007-365-00 effective on 2/26/2007
Relationship Description: The work has been incorporated into project 1998-018-00.

This project Merged To 2007-397-00 effective on 1/30/2008
Relationship Description: Move expense budgets from 1998-018-00 to 2007-397-00 so a single project number is used for Expense and Capital work.


Name Role Organization
Linda Brown (Inactive) Project Lead Confederated Tribes of Warm Springs
John Baugher (Inactive) Project Manager Bonneville Power Administration
Mike Welden (Inactive) Supervisor Confederated Tribes of Warm Springs