BPA Project Administration Requirements |
A: 119. Manage Administer Projects |
|
01/31/2007 |
01/31/2007 |
Signed landowner agreements. |
B: 118. Landowner and Agency Project Coordination |
|
01/31/2007 |
04/30/2007 |
Choose sites for 2007 construction year. |
C: 114. Identify and Select Projects |
|
11/30/2006 |
10/05/2006 |
Environmental Compliance |
D: 165. Produce Environmental Compliance Documentation |
|
07/28/2006 |
10/05/2006 |
Participate in community education activities |
E: 99. Outreach and Education |
|
01/31/2007 |
08/31/2007 |
Monitoring Data stored Electronicly and in Hard Copy Form |
F: 160. Manage and Maintain Database |
|
01/31/2007 |
01/02/2007 |
Monitoring Report |
G: 157. Collect/Generate/Validate field and lab data |
|
01/31/2007 |
10/05/2006 |
Monitoring Report |
H: 162. Analyze / Interpret Data |
|
01/31/2007 |
01/31/2007 |
Submit Copies of shared data to cooperating agencies |
I: 159. Submit/Acquire Data |
|
12/01/2006 |
11/02/2007 |
Annual Report |
J: 132. Produce Annual Report |
|
06/30/2006 |
10/05/2006 |
Greenhouse and Nursery Maintained |
L: 186. Native Plants Nursery Maintenance and operation |
|
01/31/2007 |
10/05/2006 |
Control of non-native plants and noxious weeds. |
M: 22. Maintain Vegetation |
|
12/28/2006 |
10/05/2006 |
3,000 cuttings and plants planted at construction sites and other riparian locations. |
N: 47. Plant Vegetation |
|
06/30/2006 |
07/01/2006 |
Alternative water sources developed. |
O: 34. Develop Alternative Water Source |
|
01/31/2007 |
10/05/2006 |
Project Designs for 2006 Construction Projects |
P: 175. Produce Design and/or Specifications - GSWCD |
|
01/31/2007 |
07/01/2006 |
Chandler Diversion |
Q: 84. Remove/Install Diversion (River Mile |
|
08/31/2006 |
09/01/2006 |
Emmel/Smith Lower Island Ditch Diversion |
R: 84. Remove/Install Diversion (River Mile |
|
08/31/2006 |
09/01/2006 |
Mike Smith 486 Ditch Diversion |
S: 84. Remove/Install Diversion (River Mile |
|
08/31/2006 |
09/01/2006 |
Mike Smith Medor Ditch Diversion |
T: 84. Remove/Install Diversion (River Mile |
|
08/31/2006 |
09/01/2006 |
Dayville Pump Station |
U: 84. Remove/Install Diversion ( R.M. .5 SFJD) |
|
01/31/2007 |
|
Baccum Diversion Canyon Creek - Tier Two |
V: 84. Remove/Install Diversion -Tier Two |
|
09/28/2006 |
09/01/2006 |
Lawrence Diversion - Tier Two |
W: 84. Remove/Install Diversion -Tier Two |
|
09/28/2006 |
09/01/2006 |
Morgan Diversion Tier Two |
X: 84. Remove/Install Diversion -Tier Two |
|
01/02/2007 |
|
Elmwood Diversion - Tier Two |
Y: 84. Remove/Install Diversion -Tier Two |
|
09/28/2006 |
09/01/2006 |
Jacobs Roberts Creek - Tier Two |
Z: 84. Remove/Install Diversion -Tier Two |
|
09/28/2006 |
07/01/2006 |
Nelson Return Flow Cooling System |
AA: 149. Install Pipeline - Tier Two |
|
01/02/2007 |
|
Clausen Return Flow System |
AB: 149. Install Pipeline - Tier Two |
|
01/02/2007 |
|
Project Designs for 2006 Construction Projects |
AC: 175. Produce Design and/or Specifications - WSWCD |
|
01/31/2007 |
10/05/2006 |
Installed Fish Passage Structure - Culvert #4 |
AD: 184. Butte Creek Culvert Replacement |
|
08/31/2006 |
10/05/2006 |
COPY: Installed Fish Passage Structure - Culvert #6 |
AE: 184. Butte Creek Culvert Replacement |
|
08/31/2006 |
09/01/2006 |
Installed Fish Passage Structure - Culvert #7 |
AF: 184. Butte Creek Culvert Replacement |
|
08/31/2006 |
10/05/2006 |
Installed Fish Passage Structure - Culvert #8 |
AG: 184. Butte Creek Culvert Realingnment - step-wier installation |
|
08/31/2006 |
09/01/2006 |