Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 26950: 1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT ENHANCEMENT
Project Number:
Title:
Umatilla Anadromous Fish Habitat-Umatilla Tribe
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Umatilla 100.00%
Contract Number:
26950
Contract Title:
1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT ENHANCEMENT
Contract Continuation:
Previous: Next:
22529: 1987-100-01 UMATILLA BASIN ANADROMOUS FISH HABITAT ENHANCEMENT
  • 32047: 1987-100-01 EXP UMATILLA ANADROMOUS FISH HABITAT ENHANCEMENT
Contract Status:
History
Contract Description:
Significant effort and funds have been directed at the restoration of anadromous fish in the Umatilla River Basin. This habitat enhancement project is one element in the comprehensive Umatilla Program which also includes artificial production, adult and juvenile passage improvements (ladders, screens, and trap and haul), in-stream flow enhancement, and monitoring and evaluation. Emphasis on watershed-wide habitat is needed for protection and enhancement of natural production capabilities in the basin.  

Historical and current land management practices continue to impact water quality and limit fisheries production capabilities in the Umatilla River Basin. These impacts include:

- agricultural pollution (sedimentation and chemical run-off) from poor cropland practices
- overgrazing of riparian and upland areas
- irrigation withdrawals
- logging
- channelization and constriction of stream channels
- development in floodplain areas

This project represents a continuation of existing efforts to improve natural production of existing summer steelhead and re-introduced chinook and coho salmon in the Umatilla River Basin. This project will continue to provide an integrated and comprehensive information base. Historical and current land use practices in the watershed will continue to be assessed. Recent completion of the Umatilla Subbasin/Willow Subbasin Summary and the Umatilla Subbasin Watershed Assessment will assist the project in identifying and updating habitat needs in the basin. The project will continue to complement existing fish passage and artificial production programs in the basin. On-going habitat restoration and protection efforts on private lands will be integrated with proposed enhancement projects to better justify expenditure of funds and time. Remedial measures will continue to be implemented to reduce or eliminate detrimental land management activities where possible. Continued operations and maintenance of existing enhancement projects will be included under this integrated approach. Watershed areas, containing contiguous blocks of quality anadromous salmon habitat, will be identified and recommended as priority for purchase or acquisition of management rights (including perpetual riparian easements, water rights, timber rights, grazing rights, etc.). Acquisition and improved resource management in such areas will ensure permanent protection of limited critical habitat.  

Restoration of anadromous fisheries resources in the Umatilla River Basin has been a coordinated effort between Tribal, local, state, and federal agencies and the agricultural community. Examples include the Umatilla Basin Project, the Umatilla River Subbasin Salmon and Steelhead Production Plan, the Umatilla Basin Anadromous Fish Habitat Enhancement Project and development of the Umatilla Hatchery and associated artificial production plans. This coordination has continued and expanded through development of scoping groups made up of local landowners, sportsman clubs and resource agency personnel. These groups have been instrumental in identifying issues and assisting in development of creative solutions to land use problems in the basin. Public coordination efforts will continue, and Bonneville Power Administration (BPA) funds along with cost-share monies from additional sources will be pursued to implement necessary watershed improvements on private lands.

Project personnel shall request cooperation from the local Natural Resource Conservation Service (NRCS), Umatilla County Farm Service Agency (FSA) and Umatilla County Soil and Water Conservation District (SWCD) personnel to determine projects eligible under agriculture incentive programs that may be supplemented or extended with BPA funds. Project personnel will help landowners identify such projects. This approach shall include development of a reporting system to provide and receive regular updates from the NRCS, FSA and SWCD, state and Tribal offices, regarding participating landowners and their project locations. CTUIR shall participate as appropriate in the coordination, implementation, continuation and extension of agreements that provide specific benefits to Tribal anadromous salmonid programs.


The project will continue to enhance habitat in those portions of the Umatilla River Basin which most improve natural production of existing summer steelhead and re-introduced chinook and coho salmon.  Other areas may be considered if opportunities arise in high priority stream reaches as identified in the Umatilla Subbasin/Willow Creek Subbasin Summary. Additional maintenance enhancements will be implemented within the existing mid Mission Creek and mid Wildhorse Creek project areas. Other project areas shall continue to be assessed and maintenance will occur as necessary.
Account Type(s):
Expense
Contract Start Date:
02/01/2006
Contract End Date:
01/31/2007
Current Contract Value:
$333,204
Expenditures:
$333,204

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Dawn Boorse Bonneville Power Administration No Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Julie Burke Umatilla Confederated Tribes (CTUIR) Yes Administrative Contact julieburke@ctuir.org (541) 429-7292
Billy Goodrich Umatilla Confederated Tribes (CTUIR) Yes Technical Contact billygoodrich@ctuir.org (541) 966-2383
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Gary James Umatilla Confederated Tribes (CTUIR) No Supervisor garyjames@ctuir.org (541) 429-7285
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Bob Lewis Umatilla Confederated Tribes (CTUIR) Yes Technical Contact bobhlewis@hotmail.com (541) 938-6119
Jonathan McCloud Bonneville Power Administration Yes COR jmmccloud@bpa.gov (503) 230-3110
Paul Rabb Umatilla Confederated Tribes (CTUIR) No Administrative Contact paulrabb@ctuir.org (541) 429-7165


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental clearance documents received and approved by BPA environmental compliance personnel A: 165. Prepare NEPA checklist and Biological Assessment (BA) & NMFS consultation 12/28/2006
Coordination with other agencies and organizations B: 118. Coordination with other agencies and organizations 01/31/2007 01/31/2007
Plans and proposals reviewed within 60 days of receipt. C: 122. Review plans and proposals 01/31/2007 01/30/2007
JONATHAN WILL UPDATE D: 157. Collect Water/Air/Temperature/Suspended Solids/Turbidity, and Benthic Invertebrate Data 12/01/2006 01/31/2007
Analyzed/interpreted data E: 162. Analyze/interpret Temperature, SS, & Invertebrate Data 01/31/2007 05/10/2006
Conservation easements F: 172. Acquire conservation easements for improvements on Wildhorse and Birch Creeks 09/29/2006 09/29/2006
Managed improvement projects G: 119. Manage Birch Cr., Meacham Cr., & Wildhorse Cr. habitat improvement projects 01/31/2007 01/30/2007
Designs/specifications H: 175. Preparation of engineering designs/specifications - Birch Cr. projects 01/31/2007 01/31/2007
Engineering Design/Specs. I: 175. Preparation of project design and specs. - Meacham Cr. projects 11/23/2006 01/31/2007
Management Plans J: 174. Preparation of a project mgt. plan - McKay Cr. projects 06/15/2006 05/10/2006
Management plan K: 174. Preparation of project management plans - Birch Cr. 11/15/2006
3 management plans L: 174. Preparation of project mgt. plans - Meacham Cr. projects 10/16/2006 10/16/2006
Cultural Preservation Clearance M: 165. Cultural Preservation Clearance 08/15/2006
USACE/SLD permits N: 165. USACE/SLD dredge/fill permits for Meacham Cr. projects 09/15/2006
Dredge/fill permits O: 165. USACE/SLD dredge/fill permits and ODWR permits for Birch Cr. projects 11/01/2006
Wells/pumps P: 34. Dig wells and install pump/troughs for alternatives to surface water use 12/20/2006
Water wells Q: 82. Dig wells and install pumps for alternatives to surface water use 11/20/2006
LWD installation R: 29. Install large woody debris (LWD) in Meacham Cr. 10/16/2006 10/16/2006
Barbed wire fence S: 40. Install fence on Baker property, E. Birch Cr. 09/29/2006
Fish ladder T: 184. Improve fish passage conditions at the Hoeft diversion dam 12/29/2006
Barrier alleviation U: 184. Modify barrier impediments in Meacham Cr. 09/29/2006
Box culvert passage improvement V: 184. Improve fish passage conditions at the Cunningham Sheep box culvert 12/15/2006
Vegetative Planting W: 47. Plant riparian and flood plain vegetation 01/31/2007
Survival of trees and shrubs at a minimum of 70%. X: 22. Maintain vegetation planted previously on CTUIR easements 01/31/2007 01/31/2007
Treated weeds Y: 53. Control noxious weeds 12/11/2006 01/31/2007
Repaired fencing/gates Z: 186. Repair damaged fencing/gates 06/01/2006 06/01/2006
Unimpaired instream passage structures AA: 186. Conduct O&M activities on instream improvement structures 01/31/2007 01/31/2007
Participate with other entities concerning fish and wildlife habitat AB: 99. Participation with other entities in advisory & educational activities 01/31/2007 01/31/2007
Modified diversion dam AC: 85. Modify Hoeft existing diversion dam 12/29/2006
Removed diversion dam AD: 85. Remove Broun diversion Dam 01/31/2007
Removed diversion dam AE: 85. Remove Peterson/Whitney Diversion Dam 09/29/2006
2006 Annual Report AF: 132. Draft & Finalize the 2006 Annual Report 01/31/2007 01/31/2007
Funding Package - Submit draft to COTR AG: 119. Manage and Administer the Project 11/01/2006 01/31/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Salmonids
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 2 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 3 instances of WE 85 Remove/Breach Fish Passage Barrier
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 162 Analyze/Interpret Data
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 174 Produce Plan
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Prepare NEPA checklist and Biological Assessment (BA) & NMFS consultation
B 118 Coordination with other agencies and organizations
C 122 Review plans and proposals
D 157 Collect Water/Air/Temperature/Suspended Solids/Turbidity, and Benthic Invertebrate Data
E 162 Analyze/interpret Temperature, SS, & Invertebrate Data
F 172 Acquire conservation easements for improvements on Wildhorse and Birch Creeks
G 119 Manage Birch Cr., Meacham Cr., & Wildhorse Cr. habitat improvement projects
H 175 Preparation of engineering designs/specifications - Birch Cr. projects
I 175 Preparation of project design and specs. - Meacham Cr. projects
J 174 Preparation of a project mgt. plan - McKay Cr. projects
K 174 Preparation of project management plans - Birch Cr.
L 174 Preparation of project mgt. plans - Meacham Cr. projects
M 165 Cultural Preservation Clearance
N 165 USACE/SLD dredge/fill permits for Meacham Cr. projects
O 165 USACE/SLD dredge/fill permits and ODWR permits for Birch Cr. projects
P 34 Dig wells and install pump/troughs for alternatives to surface water use
Q 82 Dig wells and install pumps for alternatives to surface water use
R 29 Install large woody debris (LWD) in Meacham Cr.
S 40 Install fence on Baker property, E. Birch Cr.
T 184 Improve fish passage conditions at the Hoeft diversion dam
U 184 Modify barrier impediments in Meacham Cr.
V 184 Improve fish passage conditions at the Cunningham Sheep box culvert
W 47 Plant riparian and flood plain vegetation
X 22 Maintain vegetation planted previously on CTUIR easements
Y 53 Control noxious weeds
Z 186 Repair damaged fencing/gates
AA 186 Conduct O&M activities on instream improvement structures
AB 99 Participation with other entities in advisory & educational activities
AC 85 Modify Hoeft existing diversion dam
AD 85 Remove Broun diversion Dam
AE 85 Remove Peterson/Whitney Diversion Dam
AF 132 Draft & Finalize the 2006 Annual Report
AG 119 Manage and Administer the Project
AH 185 Periodic Status Reports for BPA