Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 29534: 2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
Project Number:
Title:
Asotin Creek Wildlife Mitigation
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Asotin 100.00%
Contract Number:
29534
Contract Title:
2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
Contract Continuation:
Previous: Next:
25403: 2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
  • 34928: 2006-005-00 EXP ASOTIN CREEK WILDLIFE AREA O&M
Contract Status:
Closed
Contract Description:
Asotin Creek Wildlife Area Operation and Maintenance.  Contract provides funding for operation of Schlee and Bickford acquisitions.  Past accomplishments include weed control performed in major riparian areas along with associated uplands, boundary stock fence maintenance and reconstruction, installation of informational kiosks and public parking improvements, modernization of the water supply system on the Smoothing Iron Parcel, completion of a rare plant survey, installation of gallinaceous guzzlers on both units, and maintenance of access roads and trails.  Planned enhancements include restoring riparian areas and conversion of agricultural fields into native grass habitat.  Restoration of riparian areas includes continued weed control measures, establishment of woody vegetation in riparian areas, and maintenance of boundary stock fence to prevent damage from trespass livestock.  Agricultural field restoration will be performed in conjunction with agricultural farming activities being carried out by sharecroppers.  The sharecropper on Smoothing Iron Ridge will convert non-native smooth brome fields to cultivated wheat fields for a period of time yet to be determined that will sufficiently remove residual smooth brome plants.  WDFW will work with the sharecropper to seed native grass to the fields - the idea being that raising wheat on the site for a certain period of time will provide an ideal seedbed for native grass seeding.  Since the Smoothing Iron site is a relatively arid area in late summer and fall, continued development of water sources for wildlife and use by domestic livestock will continue.  Livestock grazing used as tool to improve habitat for upland wildlife is planned for the smoothing iron unit as part of WDFW's pilot grazing program.  Water sources developed/improved as described in the SOW compliment this goal as does continued maintenance  of the improved water system at the buildings located on Smoothing Iron Ridge.
Account Type(s):
Expense
Contract Start Date:
10/01/2006
Contract End Date:
09/30/2007
Current Contract Value:
$89,676
Expenditures:
$89,676

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance A: 165. Environmental Compliance 03/28/2007 03/30/2007
Control Noxious Weeds on a minimum of 150 acres in the George and Bickford Units B: 22. Control Noxious Weeds in George, and Bickford Units 09/30/2007 07/30/2007
Control Noxious weeds on an minimum of 150 acres on Smoothing Iron Unit. C: 22. Control Noxious Weeds in Smoothing Iron Unit 09/30/2007 06/30/2007
20 miles of stock fence D: 186. Maintain Boundary Stock Fences on Smoothing Iron Unit 09/30/2007 09/30/2007
20 miles of stock fence E: 186. Maintain Boundary Stock Fences on George Creek Unit 09/30/2007 09/30/2007
20 miles of stock fence F: 186. Maintain Boundary Stock Fences on Bickford Unit 09/30/2007 09/30/2007
Building Maintenance G: 186. Maintain Smoothing Iron Buildings. 09/30/2007 09/30/2007
Building Maintenance H: 186. Maintain Hay Shed on Bickford Unit. 09/30/2007 09/30/2007
Maintain/improve water trough sites I: 186. Improve/maintain Smoothing Iron water developments 09/30/2007 09/30/2007
Agricultural Field Restoration J: 47. Agricultural Field Restoration 09/30/2007
Establish woody riparian vegetation K: 47. Establish woody vegetation in riparian areas 09/30/2007 09/30/2007
Finish Management Plan L: 174. Complete Wildlife Area Mitigation Plan 01/12/2007 01/12/2007
Citizens Advisory Group (CAG) M: 99. Conduct Citizen's advisory group meetings 09/28/2007
Annual Report FY07 Contract Period N: 132. Annual Report 09/30/2007 09/30/2007
Manage and administer Asotin Creek BPA project. O: 119. Administer Asotin Creek Project 09/30/2007 09/30/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 22 Maintain Vegetation
  • 6 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 2 instances of WE 47 Plant Vegetation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance 02/09/2007
B 22 Control Noxious Weeds in George, and Bickford Units 02/15/2007
C 22 Control Noxious Weeds in Smoothing Iron Unit 02/15/2007
D 186 Maintain Boundary Stock Fences on Smoothing Iron Unit 02/15/2007
E 186 Maintain Boundary Stock Fences on George Creek Unit 02/15/2007
F 186 Maintain Boundary Stock Fences on Bickford Unit 02/15/2007
G 186 Maintain Smoothing Iron Buildings. 02/15/2007
H 186 Maintain Hay Shed on Bickford Unit. 02/15/2007
I 186 Improve/maintain Smoothing Iron water developments 06/22/2007
J 47 Agricultural Field Restoration 06/18/2007
K 47 Establish woody vegetation in riparian areas 06/18/2007
L 174 Complete Wildlife Area Mitigation Plan 02/09/2007
M 99 Conduct Citizen's advisory group meetings 02/09/2007
N 132 Annual Report 02/09/2007
O 119 Administer Asotin Creek Project 02/09/2007
P 185 Periodic Status Reports for BPA 02/09/2007