Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 30111: 1998-021-00 EXP HOOD RIVER FISH HABITAT
Project Number:
Title:
Hood River Fish Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
30111
Contract Title:
1998-021-00 EXP HOOD RIVER FISH HABITAT
Contract Continuation:
Previous: Next:
20308: PI 1998-021-00 HOOD RIVER FISH HABITAT
  • 34866: 199802100 EXP HOOD RIVER FISH HABITAT
Contract Status:
History
Contract Description:
ADMINISTRATIVE SUMMARY
The Confederated Tribes of the Warm Springs Reservation of Oregon
Hood River Production Program
6030 Dee Highway
Parkdale, Oregon 97041
Fisheries Program Manager:  Brad Houslet (541) 553-2039
Fiscal Officer:  Lori Switzler  (541) 553-3487
Hood River Production Program Coordinator:  Chris Brun(541) 806-0293
Technical Contact:  Joe McCanna (541) 352-9326

FISCAL YEAR 2005

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, and assist in project implementation and monitoring activities.

OBJECTIVE 2.  Coordinate, implement, and revise, as needed, the Hood River Fish Habitat Protection, Restoration, and Monitoring Plan.

OBJECTIVE 3.  Design, construct, and implement East Fork Irrigation District's Central Lateral Canal upgrade and invert siphon.  Monitor and evaluate the changes in fish presence and available habitat due to project implementation.

OBJECTIVE 4.  Add large wood to the West Fork Hood River.  Monitor and evaluate changes in fish presence and available habitat related to project implementation.

OBJECTIVE 5.  Construct and maintain riparian fence to stabilize and improve the riparian zone along the East Fork Hood River tributaries.


FISCAL YEAR 2006

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, and assist in project implementation and monitoring activities.

OBJECTIVE 2.  Coordinate, implement, and revise, as needed, the Hood River Fish Habitat Protection, Restoration, and Monitoring Plan and Hood River Action Plan.

OBJECTIVE 3.  Design, construct, and implement East Fork Irrigation District's Central Lateral Canal upgrade and invert siphon, phase 2 completion.  Monitor and evaluate the changes in fish presence and habitat due to project implementation.

OBJECTIVE 4.  Monitor East Fork Hood River tributary surface waters for organophosphate pesticides and macroinvertebrates in spring and summer, before and after pesticide applications.

OBJECTIVE 5.  Provide safe fish passage to and from a NOAA Fishereis approved fish screen on Tony Creek, a tributary to the Middle Fork Hood River.

OBJECTIVE 6.  Add large wood to the West Fork Hood River.  Monitor and evaluate changes in fish presence and available habitat related to project implementation.

OBJECTIVE 7.  Construct and maintain riparian fence to stabilize and improve the riparian zone along the East Fork Hood River tributaries.


FISCAL YEAR 2007

OBJECTIVE 1.  Provide coordination of all activities, administrative oversight, and assist in project implementation and monitoring activities.

OBJECTIVE 2.  Coordinate, implement, and revise, as needed, the Hood River Fish Habitat Protection, Restoration, and Monitoring Plan and Hood River Action Plan.

OBJECTIVE 3.  Monitor and evaluate the changes in fish presence and habitat due to project implementation of the East Fork Irrigation Central Canal project (capital).

OBJECTIVE 4.  Monitor East Fork Hood River tributary surface waters for organophosphate pesticides and macroinvertebrates in spring and summer, before and after pesticide applications.

OBJECTIVE 5.  Implement fish habitat restoration and channel rehabilitation work on Robinhood Creek, a tributary to the East Fork Hood River.  Monitor and evaluate changes in fish presence and available habitat related to project implementation.
Account Type(s):
Expense
Contract Start Date:
10/01/2006
Contract End Date:
09/30/2007
Current Contract Value:
$122,680
Expenditures:
$122,680

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Sarah Branum Bonneville Power Administration Yes COR stbranum@bpa.gov (503) 230-5115
Christopher Brun Confederated Tribes of Warm Springs Yes Contract Manager cbrun@hrecn.net (541) 352-3548
Patty Couch Confederated Tribes of Warm Springs No Administrative Contact pcouch@wstribes.org (541) 553-2005
Brad Houslet Confederated Tribes of Warm Springs No Administrative Contact brad.houslet@ctwsbnr.org (541) 553-2039
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Joseph McCanna Confederated Tribes of Warm Springs Yes Technical Contact jmccanna@hrecn.net (541) 352-9326
Arthur Mitchell Confederated Tribes of Warm Springs No Administrative Contact arthur.mitchell@wstribes.org (541) 553-3219
Lori Switzler Confederated Tribes of Warm Springs No Administrative Contact lswitzler@wstribes.org (541) 553-3487
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448
Richard Yarde Bonneville Power Administration No Env. Compliance Lead rryarde@bpa.gov (503) 230-3769


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project administration requirements completed A: 119. Manage Project 09/30/2007 09/10/2007
All work complies with environmental regulations B: 165. Work with BPA on environmental compliance requirements 09/30/2007 09/28/2007
12 monthly HRPP reports sent to COTR D: 141. Provide monthly status reports to BPA COTR 09/30/2007 07/28/2007
Final Annual Report complete E: 132. Prepare an annual report 03/31/2007 04/06/2007
Hood River Watershed Action Plan up to date F: 114. Provide implementation support 09/30/2007 07/28/2007
Water quality data and summaries G: 157. Pesticide monitoring in the East Fork Hood River basin 09/01/2007 08/31/2007
Robinhood Creek work complete H: 29. Monitor construction and ensure design compliance for Robinhood Creek restoration project 09/30/2007 09/21/2007
Analysis of pre-project monitoring data I: 157. Monitor the Robinhood Creek project area before and after construction 09/30/2007 09/21/2007
Data on Neal Creek passage & habitat changes J: 157. Monitor changes to fish passage and fish habitat on Neal Creek and the EFID Neal Creek Lateral 09/30/2007 09/28/2007

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 119 Manage Project 02/09/2007
B 165 Work with BPA on environmental compliance requirements 02/09/2007
C 185 Periodic Status Reports for BPA 02/09/2007
D 141 Provide monthly status reports to BPA COTR 02/09/2007
E 132 Prepare an annual report 02/09/2007
F 114 Provide implementation support 02/09/2007
G 157 Pesticide monitoring in the East Fork Hood River basin 02/09/2007
H 29 Monitor construction and ensure design compliance for Robinhood Creek restoration project 02/09/2007
I 157 Monitor the Robinhood Creek project area before and after construction 02/09/2007
J 157 Monitor changes to fish passage and fish habitat on Neal Creek and the EFID Neal Creek Lateral 02/09/2007