Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Completed Environmental Compliance for this contract and BPA-funded projects on the ground | A: 165. Complete environmental compliance documentation | 06/30/2008 | 06/25/2008 | |
Funding Package - Submit draft to COTR | B: 119. Manage & Administer Contract | 03/31/2008 | 04/15/2008 | |
Regional Coordination in the Grande Ronde and Imnaha subbasins | C: 189. Coordination with Partners | 06/30/2008 | 06/25/2008 | |
Identify & Select Habitat Projects in the Grande Ronde and Imnaha subbasins in NE OR | D: 114. Identify & Select Habitat Projects | 06/30/2008 | 06/25/2008 | |
Implementation Designs | E: 175. Produce Project Specific Designs | 06/30/2008 | 06/25/2008 | |
Manage and administer habitat projects | F: 119. Manage & Administer On-the-Ground Projects | 12/31/2007 | 12/31/2007 | |
Project Implementation Monitoring | G: 157. Perform Implementation Monitoring | 06/30/2008 | 06/25/2008 | |
Data Analysis and Interpretation | H: 162. Interpret Data Collected During Project Implementation | 06/30/2008 | 06/25/2008 | |
Information Dissemination | I: 161. Present Results of Projects | 06/30/2008 | 06/25/2008 | |
Database Creation & Maintenance | J: 160. Maintain Necessary Records of Implemented Projects | 06/30/2008 | 06/25/2008 | |
Final report uploaded to the BPA website | K: 132. Submit Annual Report for the period 07/2007 to 06/2008 | 05/31/2008 | 06/25/2008 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Trout, Brook (Salvelinus fontinalis) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Complete environmental compliance documentation | 02/09/2007 | ||||||
B | 119 | Manage & Administer Contract | 02/09/2007 | ||||||
C | 189 | Coordination with Partners | 02/09/2007 | ||||||
D | 114 | Identify & Select Habitat Projects | 02/09/2007 | ||||||
E | 175 | Produce Project Specific Designs | 02/09/2007 | ||||||
F | 119 | Manage & Administer On-the-Ground Projects | 02/09/2007 | ||||||
G | 157 | Perform Implementation Monitoring | 02/09/2007 | ||||||
H | 162 | Interpret Data Collected During Project Implementation | 02/09/2007 | ||||||
I | 161 | Present Results of Projects | 02/09/2007 | ||||||
J | 160 | Maintain Necessary Records of Implemented Projects | 02/09/2007 | ||||||
K | 132 | Submit Annual Report for the period 07/2007 to 06/2008 | 02/09/2007 | ||||||
L | 185 | Periodic Status Reports for BPA | 02/09/2007 |