Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 35478: 1999-010-00 EXP PINE HOLLOW WATERSHED ENHANCEMENT
Project Number:
Title:
Pine Hollow and Jackknife Watershed Restoration
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Columbia Plateau John Day 100.00%
Contract Number:
35478
Contract Title:
1999-010-00 EXP PINE HOLLOW WATERSHED ENHANCEMENT
Contract Continuation:
Previous: Next:
24460: 199901000 EXP PINE HOLLOW WATERSHED ENHANCEMENT
  • 51211: 1999-010-00 EXP SHERMAN LOWER JOHN DAY WATERSHED ENHANCEMENT
Contract Status:
History
Contract Description:
Workplan:
The following work plan outlines the series of activities, including methods, products, timeline and cost, to be implemented as part of the Pine Hollow / Jackknife Watershed Project by the Sherman County Soil and Water Conservation District (SWCD) from November 1, 2007 to June 30, 2008.

Partners:
Sherman County SWCD
Pine Hollow / Jackknife Watershed Council
USDA Natural Resources Conservation Service
Oregon Dept of Fish & Wildlife, John Day Basin
Bureau of Land Management
Wasco County SWCD
PG & E Gas Transmission Northwest
Oregon Watershed Enhancement Board
Landowners
Account Type(s):
Expense
Contract Start Date:
11/01/2007
Contract End Date:
09/15/2010
Current Contract Value:
$23,705
Expenditures:
$23,705

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Submit Appropriate NEPA Information A: 165. Obtain Environmental Compliance For Upland Projects 09/15/2010 09/15/2010
1 Off-Stream Water Facility for Project # PH-18 (T4S, R18E, S. 33) B: 34. Off-Stream Water Facility - Existing Source, Project # PH-18 (T4S, R18E, S. 33) 07/31/2008 07/28/2008
1 Off-Stream Solar Water Facility for Project # PH-19 (T3S, R18E, S. 4, SW 1/4) C: 34. Off-Stream Solar Water Facility - Existing Source, Project # PH-19 (T3S, R18E, S. 4, SW 1/4) 06/30/2008 06/25/2008
1 WASCB Constructed for Project # PH-22 (T7S, R18E, S. 6, NE 1/4) F: 55. Construct WASCB - Project # PH-22 (T7S, R18E, S. 6, NE 1/4) 03/31/2010 08/12/2009
1 WASCB Constructed for Project # PH-26 (T7S, R18E, S. 18, NW 1/4) G: 55. Construct WASCB - Project # PH-26 (T7S, R18E, S. 18, NW 1/4) 03/31/2010 08/12/2009
1 Solar/Wind Hybrid Water Facility for Project # PH-29 (T4S, R17E, S. 24, NW 1/4) I: 34. Off-Stream Solar/Wind Water Facility - Existing Source, Project # PH-29 (T4S, R17E, S. 24, NW 1/4) 09/15/2010
1 WASCB Constructed for Project # PH-30 (T5S, R18E, S. 14, SW 1/4) J: 55. Construct WASCB - Project # PH-30 (T5S, R18E, S. 14, SW 1/4) 06/30/2008 06/18/2008
Project Managed M: 119. Manage & Administer Project 09/15/2010 09/15/2010
1 Off-Stream Water Facility - Develop Well for Project # PH-32 (T5S, R17E, S. 23, W 1/2) N: 34. Off-Stream Water Facility - Develop Well, Project # PH-32 (T5S, R17E, S. 23, W 1/2) 03/31/2010 07/27/2009
1 Off-Stream Solar/Wind Water Facility for Project # PH-34 (T4S, R18E, S. 30, NE 1/4) P: 34. Off-Stream Solar/Wind Water Facility - Existing Source, Project # PH-34 (T4S, R18E, S. 30, NE 1/4) 09/15/2010
1 Off-Stream Solar Water Facility for Project # PH-35 (T3S, R18E, S. 8, NE 1/4) Q: 34. Off-Stream Solar Water Facility - Existing Source, Project # PH-35 (T3S, R18E, S. 8, NE 1/4) 03/31/2010 06/29/2009
1- Off-Stream Water Facility Project # PH-37 (T6S, R18E, Sec. 20, SE 1/4) S: 34. Off-Stream Water Facility - Project # PH-37 (T6S, R18E, Sec. 20, SE 1/4) 09/15/2010
Attach Progress Report in Pisces T: 132. Submit Progress Report For The Period 11/1/07 - 9/15/10 08/31/2010 08/31/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 8 instances of WE 34 Develop Alternative Water Source
  • 8 instances of WE 55 Erosion and Sedimentation Control

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Environmental Compliance For Upland Projects 02/09/2007
B 34 Off-Stream Water Facility - Existing Source, Project # PH-18 (T4S, R18E, S. 33) 11/29/2007
C 34 Off-Stream Solar Water Facility - Existing Source, Project # PH-19 (T3S, R18E, S. 4, SW 1/4) 11/28/2007
D 55 CANCELED - Construct WASCB - Project # PH-20 (T7S, R17E, S. 12, SW 1/4)
E 55 CANCELED - Construct WASCB - Project # PH-21 (T7S, R17E, S. 12, SW 1/4)
F 55 Construct WASCB - Project # PH-22 (T7S, R18E, S. 6, NE 1/4) 11/28/2007
G 55 Construct WASCB - Project # PH-26 (T7S, R18E, S. 18, NW 1/4) 10/10/2007
H 55 CANCELED - Construct WASCB - Project # PH-27 (T7S, R18E, S. 6, SE 1/4)
I 34 Off-Stream Solar/Wind Water Facility - Existing Source, Project # PH-29 (T4S, R17E, S. 24, NW 1/4) 01/11/2008
J 55 Construct WASCB - Project # PH-30 (T5S, R18E, S. 14, SW 1/4) 01/11/2008
K 34 CANCELED - Off-Stream Spring Development, Project # PH-31 (T5S, R18E, S.23, NW 1/4)
L 185 Periodic Status Reports for BPA 02/09/2007
M 119 Manage & Administer Project 02/09/2007
N 34 Off-Stream Water Facility - Develop Well, Project # PH-32 (T5S, R17E, S. 23, W 1/2) 10/01/2008
O 55 CANCELED - Construct WASCB - Project # PH-33 (T6S, R18E, S. 28, NW 1/4) 11/01/2007
P 34 Off-Stream Solar/Wind Water Facility - Existing Source, Project # PH-34 (T4S, R18E, S. 30, NE 1/4) 10/01/2008
Q 34 Off-Stream Solar Water Facility - Existing Source, Project # PH-35 (T3S, R18E, S. 8, NE 1/4) 10/01/2008
R 55 CANCELED - Construct WASCB
S 34 Off-Stream Water Facility - Project # PH-37 (T6S, R18E, Sec. 20, SE 1/4) 10/01/2008
T 132 Submit Progress Report For The Period 11/1/07 - 9/15/10 02/09/2007