Province | Subbasin | % |
---|---|---|
Columbia Plateau | Walla Walla | 100.00% |
Previous: | Next: |
---|---|
n/a |
|
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Dawn Boorse | Bonneville Power Administration | No | Env. Compliance Lead | drboorse@bpa.gov | (503) 230-5678 |
Sarah Branum | Bonneville Power Administration | Yes | COR | stbranum@bpa.gov | (503) 230-5115 |
Wendy Harris | Walla Walla Basin Watershed Council | Yes | Contract Manager | wendy.harris@wwbwc.org | (541) 938-2170 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Lisa Marko MacLellan | Bonneville Power Administration | Yes | Interested Party | lmmarko@bpa.gov | (503) 230-4047 |
Chris Sheets | Walla Walla Basin Watershed Council | No | Administrative Contact | chris.sheets@wwbwc.org | (541) 938-2170 |
Brian Wolcott | Walla Walla Basin Watershed Council | Yes | Supervisor | brian.wolcott@wwbwc.org | (541) 938-2170 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | B: 119. Admin oversight for Cap Activities | 06/01/2010 | 07/10/2010 | |
Environmental Compliance complete | C: 165. Environmental Compliance Documentation for all cap actions | 11/17/2008 | 11/17/2008 | |
designs and specs complete | D: 175. Pipeline, Aquifer Recharge, and On-Farm Storage Design/Specs | 03/31/2009 | 03/31/2009 | |
Install 500 Feet of Irrigation Piping | E: 149. Powell-Pleasantview - Install pipeline | 07/31/2009 | 03/31/2009 | |
18,200 feet of pipeline installed | F: 149. Hy-line - Install phases 2 & 3 pipeline | 08/27/2010 | 08/31/2010 | |
Flow meters and measuring devices installed | H: 148. Flow meters to monitor farm water, turn out structures, and headgates | 08/31/2010 | 08/31/2010 | |
Morris sprinkler installed | I: 150. Convert to sprinkler for farms off LWW diversion. | 07/31/2010 | 08/31/2010 | |
Drain Fields for Recharge Expansion Installed | J: 98. Expand existing HBDIC aquifer recharge sites (Phase II) | 10/30/2009 | 12/04/2009 | |
Annual Report submitted | K: 132. Submit report for period (September 2007) to (August 2008) | 08/27/2010 | ||
Liner installed in existing bulge | L: 151. NEW Burke Bulge Liner | 08/27/2010 | 08/27/2010 | |
Pre-Acquisition Activities Completed | N: 172. NEW Pre-acquisition activities for purchase of recharge site | 08/27/2010 | ||
Drain Fields for Recharge Expansion Installed | O: 82. NEW Expand Recharge Program (Phase III) | 07/31/2010 | ||
Negotiate In-stream Water Right Transactions | S: 154. NEW In-stream Water Right Transactions | 08/06/2010 | ||
Flow measuring device installed | T: 148. NEW Little Walla Walla River Measurement Devices | 08/31/2010 | ||
Automated headgate design complete | V: 175. NEW Frog - Design System | 08/31/2010 | ||
Grove Gauge Installed | W: 148. NEW Grove School Bridge Monitoring Equipment | 08/06/2010 | 08/31/2010 | |
Water Right Transaction Complete | Z: 164. NEW Acquire Water Instream for Powell/Trumbull Project | 08/31/2010 | 08/31/2010 | |
Water Right Transaction Complete | AA: 164. NEW Acquire Water Instream for Eastside Project | 08/31/2010 | 08/31/2010 | |
Water Right Transaction Complete | AB: 164. NEW Acquire Water Instream for Milton Ditch Project | 08/31/2010 | 08/31/2010 | |
Water Right Transaction Complete | AC: 164. NEW Acquire Water Instream for Lydell/Brown Project | 08/31/2010 | 08/31/2010 | |
Environmental Compliance complete | AD: 165. NEW Environmental Compliance Documentation for CAP projects | 03/31/2010 | 06/01/2010 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
B | 119 | Admin oversight for Cap Activities | 02/09/2007 | ||||||
C | 165 | Environmental Compliance Documentation for all cap actions | 02/09/2007 | ||||||
D | 175 | Pipeline, Aquifer Recharge, and On-Farm Storage Design/Specs | 02/09/2007 | ||||||
E | 149 | Powell-Pleasantview - Install pipeline | 07/08/2008 | ||||||
F | 149 | Hy-line - Install phases 2 & 3 pipeline | 10/09/2009 | ||||||
G | 149 | Trumbull Ditch Piping - Install Pipeline | 07/08/2008 | ||||||
H | 148 | Flow meters to monitor farm water, turn out structures, and headgates | 11/16/2007 | ||||||
I | 150 | Convert to sprinkler for farms off LWW diversion. | 11/16/2007 | ||||||
J | 98 | Expand existing HBDIC aquifer recharge sites (Phase II) | 11/16/2007 | ||||||
K | 132 | Submit report for period (September 2007) to (August 2008) | 02/09/2007 | ||||||
L | 151 | NEW Burke Bulge Liner | 02/09/2007 | ||||||
M | 149 | WE CANCELLED: NEW Fruitvale - Install Pipeline | 02/09/2007 | ||||||
N | 172 | NEW Pre-acquisition activities for purchase of recharge site | 02/09/2007 | ||||||
O | 82 | NEW Expand Recharge Program (Phase III) | 04/08/2010 | ||||||
P | 151 | WE CANCELLED: NEW Reese Bulge | 04/08/2010 | ||||||
Q | 151 | WE CANCELLED: NEW Tash Bulge | 04/08/2010 | ||||||
R | 151 | WE CANCELLED: NEW Morris Bulge | 04/08/2010 | ||||||
S | 154 | NEW In-stream Water Right Transactions | 02/09/2007 | ||||||
T | 148 | NEW Little Walla Walla River Measurement Devices | 06/08/2010 | ||||||
U | 148 | WE CANCELLED: NEW Spence Ditch Measurement Devices | |||||||
V | 175 | NEW Frog - Design System | 02/09/2007 | ||||||
W | 148 | NEW Grove School Bridge Monitoring Equipment | 11/10/2009 | ||||||
X | 148 | WE CANCELLED: NEW Zell Ditch Measurement Devices | |||||||
Y | 148 | WE CANCELLED: NEW Perkins Ditch Measurement Devices | |||||||
Z | 164 | NEW Acquire Water Instream for Powell/Trumbull Project | 02/09/2007 | ||||||
AA | 164 | NEW Acquire Water Instream for Eastside Project | 02/09/2007 | ||||||
AB | 164 | NEW Acquire Water Instream for Milton Ditch Project | 02/09/2007 | ||||||
AC | 164 | NEW Acquire Water Instream for Lydell/Brown Project | 02/09/2007 | ||||||
AD | 165 | NEW Environmental Compliance Documentation for CAP projects | 02/09/2007 | ||||||
AE | 82 | WE CANCELLED: NEW Brown Bulge Retrofit to include aquifer recharge | |||||||
AF | 82 | WE CANCELLED: NEW Davis Bulge Retrofit to include aquifer recharge |