Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 49378: 2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
49378
Contract Title:
2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
Contract Continuation:
Previous: Next:
35684: 200739600 CAP RESTORE WALLA WALLA RIVER FLOW
  • 60272: 2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
Contract Status:
Closed
Contract Description:
This irrigation efficiency and groundwater recharge project will improve stream flows for the passage and rearing of summer steelhead, spring Chinook, and bull trout in a flow-impaired segment of the Walla Walla River.  The Walla Walla Subbasin Plan’s highest priority project types are those that address imminent threats to ESA listed species, such as dry or low flow stream reaches.  This project will address a Subbasin Plan priority restoration area that provides habitat and also passage to primary upstream spawning grounds. Irrigation efficiency projects will utilize the Oregon Conserved Water Program to ensure that conserved water is protected as an instream water right.  Shallow aquifer recharge using high winter and spring runoff will benefit spring branches and mainstem cold water refugia.

A three-mile segment of the Walla Walla River near Milton-Freewater, Oregon, was dewatered each summer for the last century creating the need for fish rescues.  The rescues have not been necessary the last six years after aggressive irrigation efficiency programs and new wells now maintain at least 27 cfs instream throughout the spring and 25 cfs instream throughout the summer.  However, half of these bypass flows are created by an increase in supplemental well use at unsustainable rates.  Additional irrigation conservation practices, combined with winter/spring groundwater recharge, will allow irrigators to reduce their demand on the river, reduce negative impacts to groundwater, and protect the conserved water as instream water rights.
Account Type(s):
Capital
Contract Start Date:
09/01/2010
Contract End Date:
10/31/2012
Current Contract Value:
$1,159,381
Expenditures:
$1,159,381

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Dawn Boorse Bonneville Power Administration No Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Wendy Harris Walla Walla Basin Watershed Council Yes Contract Manager wendy.harris@wwbwc.org (541) 938-2170
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Chris Sheets Walla Walla Basin Watershed Council No Administrative Contact chris.sheets@wwbwc.org (541) 938-2170
Brian Wolcott Walla Walla Basin Watershed Council Yes Supervisor brian.wolcott@wwbwc.org (541) 938-2170
Tracey Yerxa Bonneville Power Administration Yes COR tyerxa@bpa.gov (503) 230-4738


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. Admin oversight for Cap Activities 07/01/2011 09/30/2011
2-year Report submitted C: 132. Submit 2-year report for September 2008 through August 2010 10/31/2012 10/31/2012
Environmental Compliance complete D: 165. Environmental Compliance Documentation for all cap actions 01/31/2011 06/04/2011
Trumbull Recharge Project Constructed E: 98. Trumbull Recharge Site 10/31/2012 10/31/2012
Anspach Recharge Project Constructed F: 98. Anspach Recharge Project 10/31/2012 10/31/2012
On farm pond constructed on Morris property G: 151. Morris Bulge 08/19/2011 11/07/2011
Flow measuring device installed at Spence Ditch H: 148. Spence Ditch Measurement Devices 02/29/2012 03/24/2012
Flow measuring device installed at Zell Ditch I: 148. Zell Ditch Measurement Devices 10/31/2012 10/31/2012
Flow measuring device installed at Perkins Ditch J: 148. Perkins Ditch Measurement Devices 10/31/2012 10/31/2012
West Little Walla Walla North Piped K: 149. West Little Walla Walla Project - North Piping 10/31/2012 10/31/2012
West Little Walla Walla South Piped L: 149. Cancelled: West Little Walla Walla Project - South Piping 10/31/2012
West Little Walla Walla Diversions Installed M: 84. West Little Walla Walla Project - Diversion Installations 10/28/2011 10/13/2011
Young Weir Installed N: 84. Young Weir & Pond Project 01/31/2012 12/30/2011
Boyd Weir Replacement and Pond Enlargement O: 84. Boyd Replace Weir and Enlarge Pond 12/31/2011 12/30/2011
Brooks Weir Installed P: 84. Brooks Weir 08/30/2011 04/30/2011
Underwood Weir Installed Q: 84. Underwood Weir 08/30/2011 12/30/2011
Negotiate In-stream Water Right Transactions R: 154. In-stream Water Right Transactions 10/31/2012 10/31/2012
Designs for above projects complete S: 175. Produce Designs for BPA Projects 03/31/2012 03/31/2012
Pre-Acquisition Activities Completed T: 172. Pre-acquisition activities for purchase or easement of recharge site 10/31/2012
Drain Fields for Recharge Expansion Installed U: 98. Complete Hudson Bay Recharge Expansion 08/31/2011 06/30/2011
Recharge Design V: 175. Recharge Design 08/31/2012 08/31/2012
Frog Designs W: 175. Frog Design 01/31/2012 01/31/2012
Flow measuring device installed X: 148. Little Walla Walla Measuring Devices 10/31/2012 10/31/2012
Funding Package - Submit draft to COTR Y: 119. Year 2 Admin oversight for Cap Activities 08/31/2012 08/31/2012
Environmental Compliance complete Z: 165. Environmental Compliance Documentation for all cap actions 03/31/2012 03/31/2012
7730 feet of pipeline installed during this phase AA: 149. Hyline - Install Final phase of pipeline 10/31/2012 10/31/2012
Replaced, Automated and tested Frog Headgates AB: 84. Frog Diversion Headgate and Automation 10/31/2012 10/31/2012
Zell Ditch Diversion AC: 84. Zell Ditch Diversion 10/31/2012 10/31/2012
White Ditch Piping Project Designs AD: 175. Produce Final Designs for White Ditch Piping 10/31/2012 10/31/2012
1-year Report submitted AE: 132. Submit 1-year report for September 2010 through August 2011 10/31/2012 10/31/2012
Stillman Ditch Piping AF: 149. Stillman Ditch Piping 10/31/2012 10/31/2012
Finalized Smith Sill Engineered Drawings AG: 175. Smith Fish Passage Barrier Modification Engineered Designs 09/10/2012 09/10/2012
Construction Management Complete AH: 100. Project Oversight for Smith Sill on mainstem Walla Walla River 10/31/2012 10/01/2012

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 7 instances of WE 84 Remove/Install Diversion
  • 3 instances of WE 98 Other
  • 5 instances of WE 175 Produce Design
  • 4 instances of WE 148 Install Flow Measuring Device
  • 4 instances of WE 149 Install Pipeline
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 7 instances of WE 84 Remove/Install Diversion
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 3 instances of WE 98 Other
  • 5 instances of WE 175 Produce Design
  • 4 instances of WE 148 Install Flow Measuring Device
  • 4 instances of WE 149 Install Pipeline
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 1 instance of WE 100 Construction Management
Trout, Bull (S. confluentus) (Threatened)
  • 7 instances of WE 84 Remove/Install Diversion
  • 3 instances of WE 98 Other
  • 5 instances of WE 175 Produce Design
  • 4 instances of WE 148 Install Flow Measuring Device
  • 4 instances of WE 149 Install Pipeline
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/01/2010
B 119 Admin oversight for Cap Activities 09/01/2010
C 132 Submit 2-year report for September 2008 through August 2010 09/01/2010
D 165 Environmental Compliance Documentation for all cap actions 09/01/2010
E 98 Trumbull Recharge Site 04/21/2011
F 98 Anspach Recharge Project 04/19/2011
G 151 Morris Bulge 09/01/2010
H 148 Spence Ditch Measurement Devices 09/01/2010
I 148 Zell Ditch Measurement Devices 09/01/2010
J 148 Perkins Ditch Measurement Devices 09/01/2010
K 149 West Little Walla Walla Project - North Piping 04/19/2011
L 149 Cancelled: West Little Walla Walla Project - South Piping 04/19/2011
M 84 West Little Walla Walla Project - Diversion Installations 04/20/2011
N 84 Young Weir & Pond Project 04/19/2011
O 84 Boyd Replace Weir and Enlarge Pond 04/19/2011
P 84 Brooks Weir 04/19/2011
Q 84 Underwood Weir 04/19/2011
R 154 In-stream Water Right Transactions 09/01/2010
S 175 Produce Designs for BPA Projects 09/01/2010
T 172 Pre-acquisition activities for purchase or easement of recharge site 09/01/2010
U 98 Complete Hudson Bay Recharge Expansion 06/15/2011
V 175 Recharge Design 09/01/2010
W 175 Frog Design 09/01/2010
X 148 Little Walla Walla Measuring Devices 09/01/2010
Y 119 Year 2 Admin oversight for Cap Activities 09/01/2010
Z 165 Environmental Compliance Documentation for all cap actions 09/01/2010
AA 149 Hyline - Install Final phase of pipeline 09/01/2010
AB 84 Frog Diversion Headgate and Automation 04/21/2011
AC 84 Zell Ditch Diversion 09/24/2012
AD 175 Produce Final Designs for White Ditch Piping 09/01/2010
AE 132 Submit 1-year report for September 2010 through August 2011 09/01/2010
AF 149 Stillman Ditch Piping 08/01/2012
AG 175 Smith Fish Passage Barrier Modification Engineered Designs 09/01/2010
AH 100 Project Oversight for Smith Sill on mainstem Walla Walla River 09/01/2010