Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 60272: 2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
Project Number:
Title:
Walla Walla Basinwide Tributary Passage and Flow
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Walla Walla 100.00%
Contract Number:
60272
Contract Title:
2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
Contract Continuation:
Previous: Next:
49378: 2007-396-00 CAP RESTORE WALLA WALLA RIVER FLOW
  • 63647: 2007-396-00 CAP WALLA WALLA BASINWIDE TRIB PASSAGE
Contract Status:
Closed
Contract Description:
This irrigation efficiency and groundwater recharge project will improve stream flows for the passage and rearing of summer steelhead, spring Chinook, and bull trout in a flow-impaired segment of the Walla Walla River.  The Walla Walla Subbasin Plan’s highest priority project types are those that address imminent threats to ESA listed species, such as dry or low flow stream reaches.  This project will address a Subbasin Plan priority restoration area that provides habitat and also passage to primary upstream spawning grounds. Irrigation efficiency projects will utilize the Oregon Conserved Water Program to ensure that conserved water is protected as an instream water right.  Shallow aquifer recharge using high winter and spring runoff will benefit spring branches and mainstem cold water refugia.

A three-mile segment of the Walla Walla River near Milton-Freewater, Oregon, was dewatered each summer for the last century creating the need for fish rescues.  The rescues have not been necessary the last eleven years after aggressive irrigation efficiency programs and new wells now maintain at least 27 cfs instream throughout the spring and 25 cfs instream throughout the summer.  However, half of these bypass flows are created by an increase in supplemental well use at unsustainable rates.  Additional irrigation conservation practices, combined with winter/spring groundwater recharge, will allow irrigators to reduce their demand on the river, reduce negative impacts to groundwater, and protect the conserved water as instream water rights.
Account Type(s):
Capital
Contract Start Date:
11/01/2012
Contract End Date:
10/31/2013
Current Contract Value:
$634,982
Expenditures:
$634,982

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Dawn Boorse Bonneville Power Administration No Env. Compliance Lead drboorse@bpa.gov (503) 230-5678
Wendy Harris Walla Walla Basin Watershed Council Yes Contract Manager wendy.harris@wwbwc.org (541) 938-2170
Brenda Heister Bonneville Power Administration Yes Contracting Officer bsheister@bpa.gov (503) 230-3531
Chris Sheets Walla Walla Basin Watershed Council No Administrative Contact chris.sheets@wwbwc.org (541) 938-2170
Jason Sweet Bonneville Power Administration Yes F&W Approver jcsweet@bpa.gov (503) 230-3349
Brian Wolcott Walla Walla Basin Watershed Council Yes Supervisor brian.wolcott@wwbwc.org (541) 938-2170
Tracey Yerxa Bonneville Power Administration Yes COR tyerxa@bpa.gov (503) 230-4738


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. Admin oversight for Cap Activities 08/16/2013 08/16/2013
Environmental Compliance complete C: 165. Environmental Compliance Documentation for all cap actions 10/31/2013
Zell Ditch Diversion E: 84. Zell Ditch Diversion 10/31/2013 10/31/2013
Flow Meters Purchased F: 148. FWUA Flow Measurement Devices 10/31/2013 09/30/2013
Attach Progress Report in Pisces G: 132. Submit 2-year report for September 2010 through October 2012 10/31/2013
Jackson Aquifer Recharge Construction I: 98. Jackson Aquifer Recharge Construction 10/31/2013 10/31/2013
Submit drawings and/or specifications to BPA J: 175. Produce Final Designs for 2012-13 Recharge Projects 10/31/2013 10/31/2013
Trolley Lane Diversion Box Covers Fabricated and Installed K: 98. Trolley Lane Diversion Box Covers 10/31/2013 10/18/2013
Negotiate In-Stream Water Right Transactions for Little Walla Walla L: 154. In-stream Water Right Transations for LWW 10/31/2013 10/31/2013
Install Van Der Ahe weir M: 148. FWUA Install Van Der Ahe Weir 10/31/2013
Install Estoup Weir N: 148. FWUA Install Estoup Weir 10/31/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 175 Produce Design
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 98 Other
  • 1 instance of WE 175 Produce Design
  • 3 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 98 Other
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 84 Remove/Install Diversion
  • 2 instances of WE 98 Other
  • 2 instances of WE 175 Produce Design
  • 3 instances of WE 148 Install Flow Measuring Device
  • 1 instance of WE 151 Line Diversion Ditch
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 09/01/2011
B 119 Admin oversight for Cap Activities 09/01/2011
C 165 Environmental Compliance Documentation for all cap actions 09/01/2011
D 175 Produce Final Designs for 2013-14 Projects 09/01/2011
E 84 Zell Ditch Diversion 09/24/2012
F 148 FWUA Flow Measurement Devices 08/15/2013
G 132 Submit 2-year report for September 2010 through October 2012 11/01/2012
H 151 Repair Powell/Pleasantview Pipe
I 98 Jackson Aquifer Recharge Construction 08/15/2013
J 175 Produce Final Designs for 2012-13 Recharge Projects 11/01/2012
K 98 Trolley Lane Diversion Box Covers 11/01/2012
L 154 In-stream Water Right Transations for LWW 11/01/2012
M 148 FWUA Install Van Der Ahe Weir 11/01/2012
N 148 FWUA Install Estoup Weir 11/01/2012