Contract 36698: 1996-077-05 EXP NPT MEADOW CREEK WATERSHED RESTORATION
Project Number:
Title:
Meadow Creek Watershed Restoration
BPA PM:
Stage:
Closed
Area:
Province Subbasin %
Mountain Snake Clearwater 100.00%
Contract Number:
36698
Contract Title:
1996-077-05 EXP NPT MEADOW CREEK WATERSHED RESTORATION
Contract Continuation:
Previous: Next:
31887: 1996 077 05 MEADOW CREEK WATERSHED RESTORATION
  • 46104: 199607705 EXP NPT MEADOW CREEK WATERSHED RESTORATION
Contract Status:
History
Contract Description:
Contract History:
The Restore McComas Meadows/Meadow Creek Watershed (1996-077-05) has been an ongoing project of the Nez Perce Tribe Fisheries Watershed Program since 1996.  This project is being completed in cooperation with the Nez Perce National Forest (NPNF).  The ultimate goal of the project is to restore the physical and biological characteristics of the watershed to provide quality habitat for anadromous and resident fish species that support the historical, cultural and economic practices of the Nez Perce Tribe.  The Meadow Creek watershed contains proposed critical habitat for listed species steelhead trout, potential critical habitat for bull trout, and has moderate habitat potential for spring Chinook salmon.  Restoration in this watershed focuses on restoring riparian processes by addressing increased water temperatures, increased sedimentation, cattle grazing affects, fish passage issues, and noxious weed infestations.  Previously completed contract work includes 4 culvert replacements, 37 miles of road decommissioning, installation of riparian vegetation cages, over 33,500 riparian trees planted, installation and maintenance of 5 miles of fence, re-contouring of the McComas Meadow ditch, and continued monitoring and evaluation and revegetation surveys.
  
Summary of FY 2008 and 2009 Contract Work:
This project is part of the Nez Perce National Forest-Nez Perce Tribe Watershed Restoration Partnership with in kind contributions from the Nez Perce National Forest.  This year's contract work will include:

A) Technical review for road decommissioning-
Road densities in the Meadow Creek watershed are 4.6 miles per square mile, the highest road density in the South Fork Clearwater subbasin (USDA Forest Service 1998).  In FY 08 up to 20 miles of roads within Meadow Creek will be decommissioned, and in FY 09 up to 22 miles of roads within Whitman Creek and 16 miles in False Creek will be decommissioned.  Road decommissioning includes pre-treatment of existing noxious weeds, re-contouring roads back to natural topography, removing all culverts, re-sloping water crossings to natural gradient, the installation of water bars, and de-compacting landing areas and skid trails which will reduce surface erosion and sediment delivery to streams.  The Forest Service (Nez Perce National Forest) will decommission these roads under a separate BPA-NPNF contract of this project, and the Nez Perce Tribe will assist in bid package preparation, contractor selection, technical oversight, final inspection, and the associated project implementation/effectiveness monitoring and evaluation.  
                                                                                                                                                                                    
B) Riparian planting-
Re-vegetation efforts have been ongoing in McComas Meadows since 2000 and have been successful.  However, Meadow Creek and its tributaries within McComas Meadows consist of over four miles of stream length, which was practically devoid of vegetation in the 1990s.  Additional plantings are warranted to provide a healthy, functioning riparian zone that provides shade to the stream, which will reduce lethal stream temperatures.  In FY 08 we will plant an estimated 2,500 native riparian trees within the McComas Meadow area.  In FY 09 we will also plant an estimated 2,500 native riparian trees within the McComas Meadow area.  Species of trees to be planted include Drummond willow, Thinleaf alder, and Red osier dogwood.
  
C) Fence maintenance-
Five miles of fence were constructed in 1997 of wooden posts and a combination of rails and four-strand barbed wire to isolate and protect McComas Meadows.  Due to heavy snow loads, annual maintenance is required to maintain a properly functioning fence that protects riparian and stream habitat.

D) Completion of design for future road decommissioning and riparian restoration-
Designs are a cooperative effort between the NPT and the NPNF.  The Forest Service and the Tribe gather the necessary field data and establish project staking and identification in the field.  Generally the NPNF takes the lead, and the Nez Perce Tribe reviews and approves all designs before being solicited for bids on construction and restoration projects.  Road decommissioning and the associated habitat restoration will reduce surface erosion and sediment delivery to streams and increase bank stability while shading the water and reducing stream temperatures.  The Whitman Creek road decommissioning project has been previously proposed and identified for treatment.  Designs will be completed under this contract, and implementation will follow in FY 09.  The False Creek road decommissioning project has also been previously proposed and identified for treatment.  Plant surveys, cultural surveys, and designs will be completed under this contract, and implementation will follow in FY 2010.

E) Management plan for controlling McComas meadows noxious weeds and restoring native vegetation-
McComas Meadows is a 600 acre grassland meadow centrally located in the Meadow Creek drainage.  Exotic, invasive weed populations within the meadow are extensive because the critical habitat and conditions of the meadow have been altered due to past management activities including excessive grazing, haying, timber harvest, and road building.  In FY 08/09 a management plan will be developed by the NPT and NPNF to begin controlling noxious weed infestations, and to restore native vegetation within McComas Meadows.  

F) Continued monitoring and evaluation-
Project effectiveness monitoring:  A monitoring protocol for culvert replacements will track the status of habitat within and around the culvert, as well as the stream channel's reaction to the newly installed culvert.  Monitoring for culvert replacements includes ocular fish surveys above and below culverts, channel grade, in-culvert substrate, and profile measurements. A report on the success of previously and newly installed culverts will be completed.  Culvert replacement monitoring has been ongoing since 2005.  Per the protocol, culvert replacement monitoring in Meadow Creek is scheduled for the Covert Creek culvert for FY 08.

Project effectiveness monitoring:  The Nez Perce National Forest and the Nez Perce Tribe have developed a monitoring plan for decommissioned roads.  Data is used to monitor success and for suggesting improvements that could be made.  The annual monitoring plan has established numerous monitoring sites for all roads that have been obliterated and establishes a timetable for subsequent monitoring.  Specifically in Meadow Creek evaluation of approximately 37 miles of obliterated roads will be accomplished by collecting monitoring data at five different sample sites as shown in the WE location.  Data collected for Road Obliteration Monitoring and Evaluation includes the following: locate and evaluate new mass failures, record and evaluate points of surface erosion, evaluate re-vegetation coverage and succession to native plants, measure stream channel restoration and adjustment, and evaluate whether the treatment applied was appropriate for the land type.  Periodic monitoring has been done at these sites since FY 2004 per the protocol.

Status and Trend Monitoring: A monitoring protocol for selected stream habitat reaches will track the status and trend of Meadow Creek. Information will be collected on fish abundance and distribution, macro-invertebrates, flow, temperature, sediment composition, and habitat parameters to include channel morphology, valley width index, Wolman Pebble counts, cobble embeddedness, large woody debris, bank stability, and riparian condition and density.  This data will be summarized into a monitoring report, showing trends of conditions as a result of watershed restoration activities.  Five reaches on Meadow Creek are scheduled for monitoring in FY 08.  Monitoring for some of the parameters at these reaches began in FY 1997 and periodic monitoring has occurred annually since 1997.
Account Type(s):
Expense
Contract Start Date:
03/01/2008
Contract End Date:
10/31/2010
Current Contract Value:
$552,441
Expenditures:
$552,441

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration No Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Arleen Henry Nez Perce Tribe No Administrative Contact arleenh@nezperce.org (208) 621-3833
Mark Johnson Nez Perce Tribe Yes Contract Manager markj@nezperce.org (208) 621-3561
David Kaplowe Bonneville Power Administration Yes COR djkaplowe@bpa.gov (503) 230-5365
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Heidi McRoberts Nez Perce Tribe Yes Contract Manager heidim@nezperce.org (208) 621-3548
Michelle Roberts US Forest Service (USFS) No Interested Party mmroberts@fs.fed.us (208) 983-4091
Emmit Taylor, Jr. Nez Perce Tribe No Supervisor emmitt@nezperce.org (208) 621-3544
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental compliance documentation submitted to BPA A: 165. Provide environmental compliance information to BPA for projects on Forest Service Lands 08/24/2008 09/10/2008
Meadow Creek Education and Outreach complete B: 99. Meadow Creek Project Area Education and Outreach 02/28/2010 02/28/2010
Technical review completed C: 122. Provide Technical Review for the Meadow Creek Phase II Road Removal 11/30/2008 11/14/2008
Designs and cost estimates for road removal D: 175. Designs for Whitman Creek Road Decommissioning 04/15/2009 02/28/2009
Technical review completed E: 122. Provide Technical Review for the Whitman Creek Road Removal 10/31/2010 09/30/2010
Riparian re-vegetation complete F: 47. Plant riparian vegetation - McComas Meadows 02/28/2010 12/15/2009
Cages inspected and relocated G: 22. Protect hawthorn trees within McComas Meadows 10/01/2009 09/30/2009
Fence maintenance completed H: 186. Maintain Fence 12/30/2009 09/30/2009
Culvert data collected I: 157. Collect Data on Culverts that have been Replaced 11/30/2008 12/01/2008
Road data collected J: 157. Collect Data on Roads that were Removed 10/31/2010 10/31/2010
Habitat data collected K: 157. Stream Habitat Data Collection in Meadow Creek Watershed 02/28/2010 02/28/2010
Data analyzed and 2008, 2009 reports complete L: 162. Meadow Creek Data Analysis 02/28/2010 02/28/2010
Design and cost estimate complete M: 175. Designs for Farris Creek Culvert Replacement 02/28/2010 02/28/2010
Designs and cost estimates for road removal N: 175. Designs for False Creek Road Decommissioning 04/01/2009 04/01/2009
Restoration management plan completed O: 174. Management Plan for Restoring Native Vegetation and Controlling McComas Meadows Noxious Weeds 02/28/2010 02/28/2010
FY 2010 SOW package and FY 08 and FY 09 accrual estimates P: 119. Management, Coordination and Communication 12/18/2009 12/31/2009
Final FY 08 annual report attached to this contract Q: 132. Complete Annual Report for the period 3/1/08-2/28/09 02/28/2009 02/28/2009
Final FY 09 annual report attached to this contract R: 132. Complete Annual Report for the period 3/1/09-2/28/2010 10/31/2010 10/31/2010
Technical review completed T: 122. Provide Technical Review for False Creek Phase I Road Removal 11/30/2009 11/01/2009
Designs and cost estimates for road removal U: 175. Designs for False Creek Phase II Road Decommissioning 02/28/2010 02/01/2010
Technical review completed V: 122. Provide technical review Rock Creek Culvert Replacement 10/31/2009 09/15/2009
Completed inventory and initial weed treatment W: 53. Noxious Weed Survey and Treatment 12/31/2009 12/31/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 53 Remove Vegetation
  • 4 instances of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan
  • 4 instances of WE 175 Produce Design
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide environmental compliance information to BPA for projects on Forest Service Lands 02/09/2007
B 99 Meadow Creek Project Area Education and Outreach 02/09/2007
C 122 Provide Technical Review for the Meadow Creek Phase II Road Removal 02/09/2007
D 175 Designs for Whitman Creek Road Decommissioning 02/09/2007
E 122 Provide Technical Review for the Whitman Creek Road Removal 02/09/2007
F 47 Plant riparian vegetation - McComas Meadows 08/25/2008
G 22 Protect hawthorn trees within McComas Meadows 02/09/2007
H 186 Maintain Fence 02/09/2007
I 157 Collect Data on Culverts that have been Replaced 02/09/2007
J 157 Collect Data on Roads that were Removed 02/09/2007
K 157 Stream Habitat Data Collection in Meadow Creek Watershed 02/09/2007
L 162 Meadow Creek Data Analysis 02/09/2007
M 175 Designs for Farris Creek Culvert Replacement 02/09/2007
N 175 Designs for False Creek Road Decommissioning 02/09/2007
O 174 Management Plan for Restoring Native Vegetation and Controlling McComas Meadows Noxious Weeds 02/09/2007
P 119 Management, Coordination and Communication 02/09/2007
Q 132 Complete Annual Report for the period 3/1/08-2/28/09 02/09/2007
R 132 Complete Annual Report for the period 3/1/09-2/28/2010 02/09/2007
S 185 Periodic Status Reports for BPA 02/09/2007
T 122 Provide Technical Review for False Creek Phase I Road Removal 02/09/2007
U 175 Designs for False Creek Phase II Road Decommissioning 02/09/2007
V 122 Provide technical review Rock Creek Culvert Replacement 02/09/2007
W 53 Noxious Weed Survey and Treatment 03/16/2009