Province | Subbasin | % |
---|---|---|
Blue Mountain | Grande Ronde | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Complete environmental compliance process | A: 165. Produce environmental compliance documentation | 10/31/2008 | 10/31/2008 | |
Coordination with GRMW as needed - may not include all Deliverable Specs | B: 189. Coordinate with the GRMW as specified in the GRMW-BPA MOU | 09/30/2009 | 09/30/2009 | |
Complete data collection | C: 157. Collect stream flow measurements on twelve Grande Ronde Basin gauging stations | 09/30/2009 | 09/30/2009 | |
Complete provisional and final flow records | D: 162. Generate provisional and final flow records | 04/01/2009 | 04/01/2009 | |
Complete station maintenance as needed | E: 186. Repair/maintain/replace stream flow gauging station | 09/30/2009 | 09/30/2009 | |
Complete project administration | F: 119. Project administration | 09/30/2009 | 09/30/2009 | |
Attach Progress Report in Pisces | G: 132. Submit Project Completion Report for 2008 Water Year | 09/30/2009 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Produce environmental compliance documentation | 02/09/2007 | ||||||
B | 189 | Coordinate with the GRMW as specified in the GRMW-BPA MOU | 02/09/2007 | ||||||
C | 157 | Collect stream flow measurements on twelve Grande Ronde Basin gauging stations | 06/19/2009 | ||||||
D | 162 | Generate provisional and final flow records | 02/09/2007 | ||||||
E | 186 | Repair/maintain/replace stream flow gauging station | 06/19/2009 | ||||||
F | 119 | Project administration | 02/09/2007 | ||||||
G | 132 | Submit Project Completion Report for 2008 Water Year | 02/09/2007 | ||||||
H | 185 | Periodic Status Reports for BPA | 02/09/2007 |