Province | Subbasin | % |
---|---|---|
Columbia Plateau | Umatilla | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Julie Burke | Umatilla Confederated Tribes (CTUIR) | Yes | Administrative Contact | julieburke@ctuir.org | (541) 429-7292 |
Craig Contor | Umatilla Confederated Tribes (CTUIR) | Yes | Contract Manager | craigcontor@ctuir.org | (541) 429-7279 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Gary James | Umatilla Confederated Tribes (CTUIR) | No | Interested Party | garyjames@ctuir.org | (541) 429-7285 |
Timmie Mandish | Bonneville Power Administration | Yes | COR | tamandish@bpa.gov | (503) 230-3983 |
Rosemary Mazaika | Bonneville Power Administration | Yes | F&W Approver | rxmazaika@bpa.gov | (503) 230-5869 |
Gene Shippentower | Umatilla Confederated Tribes (CTUIR) | Yes | Supervisor | geneshippentower@ctuir.org | (541) 429-7287 |
Nancy Weintraub | Bonneville Power Administration | No | Env. Compliance Lead | nhweintraub@bpa.gov | (503) 230-5373 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Completed ESA Permits and Permit Annual Reports | B: 165. Submit Annual ESA Permit Reports and Permit Applications | 01/29/2010 | 01/22/2010 | |
Completed Spawning Surveys | C: 157. Spawning Surveys (Modified for MOA) | 12/31/2009 | 12/18/2009 | |
Completed Estimates of Tribal Harvest | D: 157. Harvest Monitoring | 02/28/2010 | 02/28/2010 | |
Completed Scale Interpretation and Cataloging | E: 157. Age, growth, and brood-year monitoring | 02/26/2010 | 02/05/2010 | |
Water Temperature Data | F: 157. Monitor Water Temperatures (MOA) | 12/18/2009 | 12/11/2009 | |
Trap, tag, and recapture steelhead in Meacham and Three Mile traps | G: 157. Outmigration Monitoring (MOA) | 02/28/2010 | 02/28/2010 | |
Spawning Distribution and Passage of Salmon and Steelhead | H: 157. Adult Salmon and Steelhead Passage Evaluations (MOA) | 02/26/2010 | 02/26/2010 | |
Maintain organized data sets and records for new work (MOA) | I: 160. Manage Radio Telemetry and PIT Tag Data (MOA) | 02/26/2010 | 02/26/2010 | |
Maintain and Developed Accessible Databases | J: 160. Manage and summarize data | 02/26/2010 | 02/26/2010 | |
Completed Data Analysis | K: 162. Analyze data | 02/26/2010 | 02/26/2010 | |
Completed design for PIT tag detectors at TMD and the installation and monitoring of the test frame. | L: 70. Design PIT Tag Detectors at TMD and Install Test Format (MOA) | 08/14/2009 | ||
Participate in UMMEOC and AOP | M: 189. Participate in Umatilla Management Monitoring & Evaluation Oversight Committee (UMMEOC) and Um | 02/25/2010 | 02/18/2010 | |
Submit the 2008 Progress Report to Pisces | N: 132. Submit Progress Report for the period (March 208) to (Feb 2009) | 06/12/2009 | 06/01/2009 | |
Completed SOW package and reports | O: 119. Manage Projects | 11/30/2009 | 12/14/2009 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
B | 165 | Submit Annual ESA Permit Reports and Permit Applications | 02/09/2007 | ||||||
C | 157 | Spawning Surveys (Modified for MOA) | 02/10/2009 | ||||||
D | 157 | Harvest Monitoring | 02/09/2007 | ||||||
E | 157 | Age, growth, and brood-year monitoring | 02/10/2009 | ||||||
F | 157 | Monitor Water Temperatures (MOA) | 02/10/2009 | ||||||
G | 157 | Outmigration Monitoring (MOA) | 02/10/2009 | ||||||
H | 157 | Adult Salmon and Steelhead Passage Evaluations (MOA) | 02/10/2009 | ||||||
I | 160 | Manage Radio Telemetry and PIT Tag Data (MOA) | 02/09/2007 | ||||||
J | 160 | Manage and summarize data | 02/09/2007 | ||||||
K | 162 | Analyze data | 02/09/2007 | ||||||
L | 70 | Design PIT Tag Detectors at TMD and Install Test Format (MOA) | |||||||
M | 189 | Participate in Umatilla Management Monitoring & Evaluation Oversight Committee (UMMEOC) and Um | 02/09/2007 | ||||||
N | 132 | Submit Progress Report for the period (March 208) to (Feb 2009) | 02/09/2007 | ||||||
O | 119 | Manage Projects | 02/09/2007 |