Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Obtain required permits | A: 165. Obtain required permits | 08/15/2009 | 08/15/2009 | |
Purchase feminized triploid rainbow trout | B: 187. Purchase Feminized Triploid Rainbow Trout | 09/30/2009 | 01/20/2010 | |
Conduct data search | C: 157. Conduct data search | 10/31/2009 | 10/31/2009 | |
Funding Package - Submit draft to COTR | D: 119. Manage and administer Lake Rufus Woods Supplementation and Creel Project | 05/01/2010 | 06/30/2010 | |
Statistical design and analysis | E: 162. Statistical analysis of data | 07/31/2010 | 07/27/2010 | |
Conduct fisheries creel on Lake Rufus Woods | F: 157. Conduct Fisheries Creel on Lake Rufus Woods | 07/31/2010 | 07/27/2010 | |
Mark and plant triploid rainbow trout. | G: 158. Mark and plant triploid rainbow trout | 07/31/2010 | 06/17/2010 | |
Transfer data to JSAP database. | H: 159. Transfer summary data to JSAP | 07/31/2010 | 07/27/2010 | |
Attach Progress Report in Pisces | J: 132. Submit Progress Report for the period (Aug 08) to (July 09) | 02/08/2010 | 02/08/2010 |
Primary Focal Species | Work Statement Elements |
---|---|
Trout, Rainbow (Oncorhynchus mykiss) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Obtain required permits | 02/09/2007 | ||||||
B | 187 | Purchase Feminized Triploid Rainbow Trout | 02/09/2007 | ||||||
C | 157 | Conduct data search | 02/09/2007 | ||||||
D | 119 | Manage and administer Lake Rufus Woods Supplementation and Creel Project | 02/09/2007 | ||||||
E | 162 | Statistical analysis of data | 02/09/2007 | ||||||
F | 157 | Conduct Fisheries Creel on Lake Rufus Woods | 02/09/2007 | ||||||
G | 158 | Mark and plant triploid rainbow trout | 02/09/2007 | ||||||
H | 159 | Transfer summary data to JSAP | 02/09/2007 | ||||||
I | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
J | 132 | Submit Progress Report for the period (Aug 08) to (July 09) | 02/09/2007 |