Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 44788: 199206106 EXP ALBENI FALLS WL COUER D'ALENE
Project Number:
Title:
Albeni Falls Wildlife Mitigation-Coeur D'Alene Tribe
Stage:
Implementation
Area:
Province Subbasin %
Intermountain Pend Oreille 100.00%
Contract Number:
44788
Contract Title:
199206106 EXP ALBENI FALLS WL COUER D'ALENE
Contract Continuation:
Previous: Next:
39936: 199206106 CDAT ALBENI FALLS WL
  • 49932: 1992-061-06 EXP ALBENI FALLS WL COUER D'ALENE
Contract Status:
Closed
Contract Description:
The Idaho Department of Fish and Game formed the Albeni Falls Interagency Work Group in 1985 for the purpose of determining wildlife impacts associated with the construction of the Albeni Falls hydroelectric project. Work Group members include the IDFG, the Kalispel Tribe, the Coeur D'Alene Tribe, the Kootenai Tribe of Idaho and the U. S. Army Corps of Engineers. Once the loss assessments were completed, the group worked collectively to protect, enhance and mitigate wildlife impacts in the Coeur d' Alene and Pend Oreille Subbasins. This contract provides for the enhancement, operations and maintenance, construction and implementation on mitigation properties managed by the Coeur d' Alene Tribe.  In addition, this contract provides the funding for the Tribe to conduct planning and design activities for the potential acquisition of mitigation properties.  Currently the Tribe owns and manages approximately 3,300 acres under the Albeni Falls Wildlife Mitigation Project.

Continuing activities encompass long-term operation and maintenance with targeted enhancement activities.. Stream restoration and flood plain enhancement is being conducted on the Benewah Creek mitigation acquisition as part of the Fisheries Program's enhancement project as well as wetland enhancement / creation on the Goose Haven lake mitigation acquisition.

The properties acquired to date by the Coeur d' Alene Tribe fall into two general categories. Those that are conservation type with limited enhancements necessary and those that have high potential habitat value but require active enhancement activities to realize their potential. In 2008, the objective is to re-establish functional hydrology and expand the wetland component to  Goose Haven Lake was implemented successfully.  Fiscal year 2010 will entail primarily operation and maintenance activities with the addition of another 1018 acres of upland habitat.
Account Type(s):
Expense
Contract Start Date:
10/01/2009
Contract End Date:
09/30/2010
Current Contract Value:
$414,208
Expenditures:
$414,208

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Cameron Heusser Coeur D'Alene Tribe Yes Supervisor cheusser@cdatribe-nsn.gov (208) 686-5521
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Rosemary Mazaika Bonneville Power Administration No Interested Party rxmazaika@bpa.gov (503) 230-5869
Anders Mikkelsen Coeur D'Alene Tribe Yes Contract Manager amikkelsen@cdatribe-nsn.gov (208) 686-8902
Jenna Peterson Bonneville Power Administration Yes Env. Compliance Lead jepeterson@bpa.gov (503) 230-3018
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Virgil Watts III Bonneville Power Administration Yes COR vlwatts@bpa.gov (503) 230-4625


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Compliance B: 165. NEPA checklist/Compliance 09/30/2010 09/30/2010
Regional Wildlife Program Document Review C: 122. Regional Workgroup Management Plan and Acquisition Review 09/30/2010 09/30/2010
Management Plan Development and Revision D: 174. Produce management plans 09/30/2010 09/30/2010
Maintain wetland vegetation at Goose Haven lake E: 22. Maintain Trees and Wetland vegetation planted in Goose Haven lake 09/30/2010 09/30/2010
Debris Removal From Mitigation Properties F: 27. Hepton Property Debris Removal 09/30/2010 09/30/2010
Debris Removal on Habitat Properties G: 27. Elkhorn Ranch Property Debris Removal 09/30/2010 09/30/2010
Debris Removal on Habitat Properties H: 27. St. Joe River Property Debris Removal 09/30/2010 09/30/2010
Maintain perimeter fence and gates on all properties I: 186. Maintain Fence line and Structures 09/30/2010 09/30/2010
Investigate to trespass on all mitigation sites J: 26. Investigate trespass on mitigation properties 09/30/2010 09/30/2010
Vegetation Planting on The Goose Haven Lake Property K: 47. Plant vegetation to restore native habitats within the Goose Haven Lake Property 09/30/2010 09/30/2010
Regional Wildlife Habitat Coordination & Administration L: 189. Albeni Falls Work Group, Upper Columbia United Tribes, Bonneville Power, Columbia Basin 09/30/2010 09/30/2010
Completed HEP Reports M: 87. Prepare HEP report for the Albeni Falls Mitigation Projects 09/30/2010 09/30/2010
Albeni Falls Project Management N: 119. Albeni Falls Wildlife Mitigation Program 09/30/2010 09/30/2010
Install and maintain no trespassing signs O: 188. Install and maintain no trespassing signs on all mitigation properties 09/30/2010 09/30/2010
Property Surveys completed on newly acquired lands P: 98. Record of Survey on acquired lands 09/30/2010 09/30/2010
PISCES Quarterly reports Q: 132. Submit Progress Report for the period (October 2009 ) to (September 2010) 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions R: 53. Remove noxious weeds via chemical application on Hepton Lake 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions S: 53. Remove noxious weeds via chemical application on Ellkhorn Ranch 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions T: 53. Remove noxious weeds via chemical application on Windy Bay 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions U: 53. Remove noxious weeds via chemical application on St. Joe River 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions V: 53. Remove noxious weeds via chemical application on Goose Haven lake 09/30/2010 09/30/2010
Herbicide application on mitigation acquisitions W: 53. Remove noxious weeds via chemical application on Cougar Creek 09/30/2010 09/30/2010

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 22 Maintain Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 3 instances of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 6 instances of WE 53 Remove Vegetation
  • 1 instance of WE 98 Other
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/09/2007
B 165 NEPA checklist/Compliance 02/09/2007
C 122 Regional Workgroup Management Plan and Acquisition Review 02/09/2007
D 174 Produce management plans 02/09/2007
E 22 Maintain Trees and Wetland vegetation planted in Goose Haven lake 03/12/2010
F 27 Hepton Property Debris Removal 03/25/2010
G 27 Elkhorn Ranch Property Debris Removal 03/25/2010
H 27 St. Joe River Property Debris Removal 03/25/2010
I 186 Maintain Fence line and Structures 02/09/2007
J 26 Investigate trespass on mitigation properties 02/09/2007
K 47 Plant vegetation to restore native habitats within the Goose Haven Lake Property 03/25/2010
L 189 Albeni Falls Work Group, Upper Columbia United Tribes, Bonneville Power, Columbia Basin 02/09/2007
M 87 Prepare HEP report for the Albeni Falls Mitigation Projects 02/09/2007
N 119 Albeni Falls Wildlife Mitigation Program 02/09/2007
O 188 Install and maintain no trespassing signs on all mitigation properties 03/12/2010
P 98 Record of Survey on acquired lands 10/01/2009
Q 132 Submit Progress Report for the period (October 2009 ) to (September 2010) 02/09/2007
R 53 Remove noxious weeds via chemical application on Hepton Lake 08/26/2010
S 53 Remove noxious weeds via chemical application on Ellkhorn Ranch 10/01/2009
T 53 Remove noxious weeds via chemical application on Windy Bay 08/26/2010
U 53 Remove noxious weeds via chemical application on St. Joe River 08/19/2010
V 53 Remove noxious weeds via chemical application on Goose Haven lake 08/26/2010
W 53 Remove noxious weeds via chemical application on Cougar Creek 08/26/2010