Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 45280: 199202601 EXP BIOP NORTH FORK CABIN CREEK/SHEEHY REARING HABITAT
Project Number:
Title:
Grande Ronde Model Watershed
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Blue Mountain Grande Ronde 100.00%
Contract Number:
45280
Contract Title:
199202601 EXP BIOP NORTH FORK CABIN CREEK/SHEEHY REARING HABITAT
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
North Fork Cabin Creek Culvert Replacements

Introduction and Background
The project proposes to replace three culverts with channel-spanning bridges, arches or bottomless concrete box culverts. North Fork Cabin Creek is habitat for summer steelhead, resident rainbow and other native fish. All culverts are partial to complete barriers (depending on flow) to adult steelhead passage.  All are complete barriers to juvenile steelhead and resident fish. Two of the culverts are on a county road, one is a private drive.  The North Fork Cabin Creek, at the project sites, is an intermittent stream, usually ceasing to flow in late July or early August. Flow in the headwater tributaries is perennial and provides year-long steelhead rearing and resident fish habitat.


Project Objectives:

•Provide year-round fish passage for all life stages of all native species, particularly Snake River summer steelhead
•Maintain streambed stability

Proposed Actions:

•Remove existing culverts
•Construct and remove bypass - Site 2 (middle only)
•Realign streambed to conform with stream form and function above and below the sites - Site 3 (north only)
•Install rock cross vane grade control structures as necessary to stabilize streambed (below Sites 1 & 3, above and below Site 2)
•Construct new structures (steel bridges at Sites 1 & 3, bottomless arch at Site 2)
•Erosion seed disturbed ground, reestablish hardwoods
•Grade and resurface the gravel roads

Benefits
Replacement of the three culverts in combination will open access for steelhead to approximately 5.5 miles of headwater habitat.  Larger capacity crossing structures will reduce risk of failure and introduction of sediment and road fill into the system.

Construction is proposed for the in-water work period July 1 to October 15, 2010.  The channel is expected to be dry during the construction period.  Anderson-Perry & Associates (AP) of  La Grande, Oregon have completed a site survey, preliminary designs and final designs. AP will prepare and submit DSL and COE permit applications. ESA consultation will be completed via BPA’s HIP II.  Cultural Resource survey and SHPO Section 106 compliance will be subcontracted.


Catherine Creek Sheehy Rearing Habitat

Introduction and Background
The project proposes to create winter rearing habitat for juvenile steelhead and Chinook by opening up an abandoned channel and providing  fish access from Catherine Creek .  Catherine Creek is habitat for ESA listed Snake River summer steelhead, summer Chinook and bull trout as well as resident rainbow and other native fish. The old channel was bypassed and cutoff when Catherine Creek was channelized about 40 years ago. A plug was constructed to keep water from flowing into the historic channel.  This reach of Catherine Creek is used extensively for winter rearing by juvenile steelhead and Chinook. Past channelization and dike construction has greatly diminished the quality and quantity of rearing habitat throughout this reach.

Project Objectives:

•Provide off-channel winter rearing habitat for juvenile Snake River spring Chinook and summer steelhead.

Proposed Actions:

•Remove plug blocking off the old channel.
•Install 3 rootwads to protect streambank as per designs
•Place LWD in the backwater channel
•Remove old fence, construct new livestock exclusion fence around the backwater channel.
•Erosion seed disturbed ground
•Interplant live willow stakes along backwater channel
•Install 2 off-channel livestock water troughs
•Install PVC water line to supply water troughs from end of irrigation mainline.

Benefits
Backwater channel will provide additional rearing habitat for juvenile Chinook, steelhead and resident species.  Off-channel livestock water will eliminated cattle access to the stream reducing sediment and nutrient inputs.

Implementation is proposed for the 2010 field season.  Work outside the Catherine Creek channel can occur anytime.  Connection to Catherine Creek will occur within the in-water work period July 1 to August 15, 2010.  Anderson-Perry & Associates (AP) of  La Grande, Oregon have completed a site survey, preliminary designs and final designs. AP will prepare and submit DSL and COE permit applications. Preparation of a Biological Assessment will be subcontracted. Cultural Resource survey and SHPO Section 106 compliance will be subcontracted.
Account Type(s):
Expense
Contract Start Date:
12/01/2009
Contract End Date:
12/31/2011
Current Contract Value:
$285,939
Expenditures:
$285,939

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Project permits and environmental compliance documents A: 165. Environmental compliance for N. Fk Cabin Creek Fish Passage 11/30/2010 06/30/2010
Project management and administration C: 119. Project management & Administration for Cabin Creek and Sheehy Projects 11/30/2011 10/21/2011
North Fork Cabin Creek bridge (north site) constructed D: 184. North Fork Cabin Creek Bridge Robinson Road (north site) 11/30/2010 08/31/2010
North Fork Cabin Creek arch (middle site) constructed E: 184. North Fork Cabin Creek Culvert Installation (middle site) 11/30/2011 10/21/2011
North Fork Cabin Creek bridge (south site) constructed F: 184. North Fork Cabin Creek Bridge Robinson Road (south site) 11/30/2010 09/30/2010
N Fk Cabin Creek Fish Passage Completion Report I: 132. Completion report - N Fk Cabin Creek Fish Passage 12/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
Sockeye (O. nerka) - Snake River ESU (Endangered)
  • 1 instance of WE 184 Install Fish Passage Structure
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 2 instances of WE 184 Install Fish Passage Structure
Trout, Bull (S. confluentus) (Threatened)
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental compliance for N. Fk Cabin Creek Fish Passage 02/09/2007
B 165 Environmental compliance for Catherine Creek Sheehy Rearing Habitat 12/01/2009
C 119 Project management & Administration for Cabin Creek and Sheehy Projects 12/01/2009
D 184 North Fork Cabin Creek Bridge Robinson Road (north site) 07/06/2009
E 184 North Fork Cabin Creek Culvert Installation (middle site) 12/01/2009
F 184 North Fork Cabin Creek Bridge Robinson Road (south site) 12/01/2009
G 29 Catherine Creek Sheehy Rearing Habitat
H 132 Completion report - Catherine Creek Sheehy Rearing Habitat 12/01/2009
I 132 Completion report - N Fk Cabin Creek Fish Passage 12/01/2009
J 185 Periodic Status Reports for BPA 02/09/2007