Province | Subbasin | % |
---|---|---|
Columbia Gorge | Hood | 100.00% |
Previous: | Next: |
---|---|
n/a |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Christopher Brun | Confederated Tribes of Warm Springs | Yes | Contract Manager | cbrun@hrecn.net | (541) 352-3548 |
Israel Duran | Bonneville Power Administration | Yes | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
Richard Golden Jr | Bonneville Power Administration | Yes | COR | rlgolden@bpa.gov | (503) 230-5119 |
Brad Houslet | Confederated Tribes of Warm Springs | No | Supervisor | brad.houslet@ctwsbnr.org | (541) 553-2039 |
Arthur Mitchell | Confederated Tribes of Warm Springs | No | Administrative Contact | arthur.mitchell@wstribes.org | (541) 553-3219 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Dan Warren | D J Warren and Associates, Inc. | No | Interested Party | dan.warren@djwassociates.com | (541) 929-4639 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
All required environmental and land use permits secured. | A: 165. Produce environmental compliance documentation and land use permits | 09/30/2011 | 09/30/2011 | |
Construction Management | B: 100. West Fork acclimation facility construction administration | 09/30/2013 | 09/30/2013 | |
Moving Falls fish ladder and adult fish trapping facility completed. | C: 70. Install an adult fish trapping facility in the West Fork Hood River at Moving Falls. | 06/28/2013 | 06/28/2013 | |
Dee Mill adult fish trapping facility completed. | D: 70. Install an adult fish trapping faclity in the East Fork Hood River at Dee Mill. | 04/01/2011 | 03/01/2011 | |
Moving Falls Acclimation Facility Construction Complete | E: 171. Construct Moving Falls acclimation facility. | 08/29/2014 | 08/29/2014 | |
Moving Falls grade control structures maintained. | F: 184. Maintain Moving Falls grade control structures. | 10/14/2011 | 10/17/2011 | |
Project management and coordination | G: 100. Project management and coordination | 02/28/2011 | 02/28/2011 | |
Funding Package - Submit draft to COTR | H: 119. Routine contract administration | 10/01/2013 | 09/30/2013 | |
Access agreement secured. | I: 172. Secure land use agreement with East Fork trap site landowner. | 10/11/2010 | 07/23/2010 | |
Attach Progress Report in Pisces | K: 132. Submit Progress Report for the period January 2010 through Dec. 2013. | 12/31/2014 | ||
Moving Falls acclimation facility access road and Dee Mill trap site improved. | L: 38. Improve access road to Moving Falls acclimation site and Dee Mill Trap Site | 10/29/2010 | 10/29/2010 | |
Final design complete design for HRPP West Fork Hood River facilities. | M: 175. Complete final design of new HRPP adult trapping and acclimation facilities. | 06/30/2010 | 06/30/2010 | |
Moving Falls lease agreement secured. | N: 92. Complete lease agreement with West Fork landowner. | 08/30/2010 | 08/16/2010 | |
Moving Falls fish ladder / trapping facility final engineering designs complete. | O: 175. Produce final engineering designs for Moving Falls fish ladder and adult trapping facility. | 04/29/2011 | 04/29/2011 | |
Moving Falls Acclimation Facility completed. | P: 171. Complete construction of Moving Falls Acclimation Facility | 11/28/2014 | 11/28/2014 | |
Moving Falls fish ladder construction complete. | Q: 184. Complete construction of Moving Falls fish ladder. | 10/31/2014 | ||
Moving Falls fish trapping facility completed. | R: 70. Complete constructon of Moving Falls fish trapping facility. | 10/31/2014 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Produce environmental compliance documentation and land use permits | 11/16/2009 | ||||||
B | 100 | West Fork acclimation facility construction administration | 11/16/2009 | ||||||
C | 70 | Install an adult fish trapping facility in the West Fork Hood River at Moving Falls. | 05/20/2011 | ||||||
D | 70 | Install an adult fish trapping faclity in the East Fork Hood River at Dee Mill. | 01/01/2011 | ||||||
E | 171 | Construct Moving Falls acclimation facility. | 07/26/2010 | ||||||
F | 184 | Maintain Moving Falls grade control structures. | 05/20/2011 | ||||||
G | 100 | Project management and coordination | 11/16/2009 | ||||||
H | 119 | Routine contract administration | 11/16/2009 | ||||||
I | 172 | Secure land use agreement with East Fork trap site landowner. | 11/16/2009 | ||||||
J | 185 | Periodic Status Reports for BPA | 11/16/2009 | ||||||
K | 132 | Submit Progress Report for the period January 2010 through Dec. 2013. | 11/16/2009 | ||||||
L | 38 | Improve access road to Moving Falls acclimation site and Dee Mill Trap Site | 03/09/2010 | ||||||
M | 175 | Complete final design of new HRPP adult trapping and acclimation facilities. | 12/15/2009 | ||||||
N | 92 | Complete lease agreement with West Fork landowner. | 12/15/2009 | ||||||
O | 175 | Produce final engineering designs for Moving Falls fish ladder and adult trapping facility. | 12/15/2009 | ||||||
P | 171 | Complete construction of Moving Falls Acclimation Facility | 01/01/2014 | ||||||
Q | 184 | Complete construction of Moving Falls fish ladder. | 01/02/2014 | ||||||
R | 70 | Complete constructon of Moving Falls fish trapping facility. | 01/01/2014 |