Please Note: This project is the product of one or more merges and/or splits from other projects. Historical data automatically included here are limited to the current project and previous generation (the “parent” projects) only. The Project Relationships section details the nature of the relationships between this project and the previous generation. To learn about the complete ancestry of this project, please review the Project Relationships section on the Project Summary page of each parent project.
Province | Subbasin | % |
---|---|---|
Columbia Gorge | Hood | 100.00% |
Description: Page: 9 Figure 1: Tytan 144 Kw Water Heater (Model: TY-144-480-3-RC) and 360 gallon re-circulating tank. Project(s): 1988-053-15 Document: P115089 Dimensions: 360 x 480 Description: Page: 9 Figure 2: 720” long 8” HDPE pipeline from well house to facility. Project(s): 1988-053-15 Document: P115089 Dimensions: 640 x 480 Description: Page: 10 Figure 3: 24’X24” Pump house and backup diesel generator. Project(s): 1988-053-15 Document: P115089 Dimensions: 640 x 480 Description: Page: 11 Figure 4: Aeration system inside pump house. Project(s): 1988-053-15 Document: P115089 Dimensions: 640 x 480 Description: Page: 11 Figure 5: Pump controls and alarm system inside pump house. Project(s): 1988-053-15 Document: P115089 Dimensions: 640 x 480 |
To view all expenditures for all fiscal years, click "Project Exp. by FY"
To see more detailed project budget information, please visit the "Project Budget" page
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
BPA-004823 | Bonneville Power Administration | East Fork and West Fork Easement Acquisition Assistance | Active | $0 | 10/1/2008 - 9/30/2009 |
40984 SOW | Confederated Tribes of Warm Springs | 1988-053-15 CAP PARKDALE HOOD RIVER PRODUCTION PROGRAM | Closed | $430,488 | 1/15/2009 - 1/14/2010 |
41209 SOW | Confederated Tribes of Warm Springs | 1988-053-15 CAP HRPP PARKDALE PHASE 1 EXPANSION--MOA | Closed | $295,312 | 3/1/2009 - 2/28/2010 |
45346 SOW | Confederated Tribes of Warm Springs | 198805315 CAP HOOD RIVER MASTER PLAN STEP III FINAL DESIGN/BUILD | Closed | $3,792,877 | 12/15/2009 - 12/31/2014 |
68072 SOW | Confederated Tribes of Warm Springs | 1988-053-15 CAP HRPP CAPITAL IMPROVEMENTS | Closed | $1,168,951 | 3/1/2015 - 6/30/2020 |
Number | Contractor Name | Title | Status | Total Contracted Amount | Dates |
---|---|---|---|---|---|
23380 REL 1 SOW | Fishpro, Inc. | 1988-053-15 EXP HRPP EXPANSION | Closed | $402,343 | 2/6/2006 - 5/31/2008 |
38879 SOW | Confederated Tribes of Warm Springs | 1988-053-15 EXP HRPP PARKDALE PHASE I EXPANSION | Closed | $150,101 | 8/1/2008 - 2/28/2009 |
BPA-005059 | Bonneville Power Administration | FY10 Hood River Artificial Production (Parkdale) | Active | $288 | 10/1/2009 - 9/30/2010 |
Annual Progress Reports | |
---|---|
Expected (since FY2004): | 6 |
Completed: | 2 |
On time: | 2 |
Status Reports | |
---|---|
Completed: | 58 |
On time: | 40 |
Avg Days Late: | 4 |
Count of Contract Deliverables | ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Earliest Contract | Subsequent Contracts | Title | Contractor | Earliest Start | Latest End | Latest Status | Accepted Reports | Complete | Green | Yellow | Red | Total | % Green and Complete | Canceled |
23380 REL 1 | 1988-053-15 EXP HRPP EXPANSION | Fishpro, Inc. | 02/06/2006 | 05/31/2008 | Closed | 6 | 5 | 0 | 0 | 0 | 5 | 100.00% | 0 | |
38879 | 41209 | 1988-053-15 CAP HRPP PARKDALE PHASE 1 EXPANSION--MOA | Confederated Tribes of Warm Springs | 08/01/2008 | 02/28/2010 | Closed | 7 | 15 | 0 | 0 | 1 | 16 | 93.75% | 1 |
BPA-4823 | East Fork and West Fork Easement Acquisition Assistance | Bonneville Power Administration | 10/01/2008 | 09/30/2009 | Active | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
40984 | 1988-053-15 CAP PARKDALE HOOD RIVER PRODUCTION PROGRAM | Confederated Tribes of Warm Springs | 01/15/2009 | 01/14/2010 | Closed | 4 | 7 | 0 | 0 | 3 | 10 | 70.00% | 2 | |
BPA-5059 | FY10 Hood River Artificial Production (Parkdale) | Bonneville Power Administration | 10/01/2009 | 09/30/2010 | Active | 0 | 0 | 0 | 0 | 0 | 0 | 0 | ||
45346 | 198805315 CAP HOOD RIVER MASTER PLAN STEP III FINAL DESIGN/BUILD | Confederated Tribes of Warm Springs | 12/15/2009 | 12/31/2014 | Closed | 20 | 14 | 0 | 0 | 3 | 17 | 82.35% | 0 | |
68072 | 1988-053-15 CAP HRPP CAPITAL IMPROVEMENTS | Confederated Tribes of Warm Springs | 03/01/2015 | 06/30/2020 | Closed | 21 | 16 | 0 | 0 | 1 | 17 | 94.12% | 5 | |
Project Totals | 58 | 57 | 0 | 0 | 8 | 65 | 87.69% | 8 |
Assessment Number: | 1988-053-15-NPCC-20110707 |
---|---|
Project: | 1988-053-15 - Hood River Artificial Production-Parkdale |
Review: | RME / AP Category Review |
Proposal: | RMECAT-1988-053-15 |
Proposal State: | Pending BPA Response |
Approved Date: | 6/10/2011 |
Recommendation: | Under Review |
Comments: | Implement through outcome of Step Review process per October 15, 2008 Council decision. Implementation subject to regional hatchery effects evaluation process described in programmatic recommendation #4. |
Publish Date: 09/08/2011
BPA Response: Agree
BPA agrees to implement through outcome of Step Review process. |
|
Conditions: | |
Council Condition #1 Programmatic Issue: RMECAT #4 Hatchery Effectiveness—Implementation subject to regional hatchery effects evaluation process described in programmatic recommendation #4. | |
BPA Response to Council Condition #1:
<no comment>
|
Assessment Number: | 1988-053-15-BIOP-20101105 |
---|---|
Project Number: | 1988-053-15 |
Review: | RME / AP Category Review |
Proposal Number: | RMECAT-1988-053-15 |
Completed Date: | None |
2008 FCRPS BiOp Workgroup Rating: | Supports 2008 FCRPS BiOp |
Comments: |
BiOp Workgroup Comments: No BiOp Workgroup Comments The BiOp RM&E Workgroups made the following determinations regarding the proposal's ability or need to support BiOp Research, Monitoring and Evaluation (RME) RPAs. If you have questions regarding these RPA association conclusions, please contact your BPA COTR and they will help clarify, or they will arrange further discussion with the appropriate RM&E Workgroup Leads. BiOp RPA associations for the proposed work are: () All Questionable RPA Associations () and All Deleted RPA Associations () |
Proponent Response: | |
|
Assessment Number: | 1988-053-15-NPCC-20090924 |
---|---|
Project: | 1988-053-15 - Hood River Artificial Production-Parkdale |
Review: | FY07-09 Solicitation Review |
Approved Date: | 10/23/2006 |
Recommendation: | Do Not Fund |
Comments: |
Assessment Number: | 1988-053-15-ISRP-20060831 |
---|---|
Project: | 1988-053-15 - Hood River Artificial Production-Parkdale |
Review: | FY07-09 Solicitation Review |
Completed Date: | 8/31/2006 |
Final Round ISRP Date: | None |
Final Round ISRP Rating: | Does Not Meet Scientific Review Criteria |
Final Round ISRP Comment: | |
Despite its numeric designation as an ongoing project, this seems to be new work and appropriate for the Three-Step Review process. As written, the proposal suffered greatly from a lack of clarity and definition in every aspect. The ISRP cannot recommend this project for funding at this time.
|
|
Documentation Links: |
|
Assessment Number: | 1988-053-15-INLIEU-20090521 |
---|---|
Project Number: | 1988-053-15 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 10/6/2006 |
In Lieu Rating: | Problems Exist |
Cost Share Rating: | None |
Comment: | Funding to investigate alternative trapping facilities in support in support of Hood River Production Program, which include BPA interests, as well as other non-federal dam owners (PRB, Powerdale); need cost-share from other dam owners or other remedy. |
Assessment Number: | 1988-053-15-CAPITAL-20090618 |
---|---|
Project Number: | 1988-053-15 |
Review: | FY07-09 Solicitation Review |
Completed Date: | 9/14/2007 |
Capital Rating: | Qualifies for Capital Funding |
Capital Asset Category: | Hatchery |
Comment: | Capital funding approval submitted by BPA COTR. The COTR, COTR's Manager and BPA Accountant certified that the request meets the BPA F&W capital policy and is approved for capital funding (if capital funds are available). However, if this construction ends up being temporary or does not meet the $1.0 million threshold, it will not be capitalized. |
Project Relationships: |
This project Merged From 2008-309-00 effective on 5/3/2008 Relationship Description: When the accords were signed, a new project number was assigned to the construction piece of Hood River Trapping Facility/Parkdale Fish Facility Expansion. The history of this project falls under 1988-053-15, therefore it is best for the construction piece stay within the existing project. |
---|
Name | Role | Organization |
---|---|---|
Christopher Brun (Inactive) | Project Lead | Confederated Tribes of Warm Springs |
Israel Duran | Env. Compliance Lead | Bonneville Power Administration |
John Skidmore | Supervisor | Bonneville Power Administration |
Chris Brun | Supervisor | Confederated Tribes of Warm Springs |
Leona Ike (Inactive) | Administrative Contact | Confederated Tribes of Warm Springs |
Eric Andersen (Inactive) | Project Lead | Bonneville Power Administration |
Eric Andersen (Inactive) | Project Manager | Bonneville Power Administration |