Province | Subbasin | % |
---|---|---|
Columbia Gorge | Hood | 100.00% |
Previous: | Next: |
---|---|
38879: 1988-053-15 EXP HRPP PARKDALE PHASE I EXPANSION |
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Christopher Brun | Confederated Tribes of Warm Springs | Yes | Contract Manager | cbrun@hrecn.net | (541) 352-3548 |
Mickey Carter | Bonneville Power Administration | No | Env. Compliance Lead | macarter@bpa.gov | (503) 230-5885 |
Richard Golden Jr | Bonneville Power Administration | Yes | COR | rlgolden@bpa.gov | (503) 230-5119 |
Brad Houslet | Confederated Tribes of Warm Springs | No | Supervisor | brad.houslet@ctwsbnr.org | (541) 553-2039 |
Rosemary Mazaika | Bonneville Power Administration | Yes | F&W Approver | rxmazaika@bpa.gov | (503) 230-5869 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Routine administration of project | 01/05/2010 | 09/30/2009 | |
Acquire all EC and permits | B: 165. Provide all EC and permits to BPA | 03/01/2009 | 03/01/2009 | |
Well house construction and associated housed equipment and wiring complete | C: 171. Construct well house. | 08/28/2009 | 08/28/2009 | |
Pipeline installed | D: 171. Install pipeline. | 06/26/2009 | 06/26/2009 | |
Two discharge headers and one standpipe installed at Parkdale Fish Facility. | E: 171. Install discharge headers. | 07/31/2009 | 07/31/2009 | |
SCADA alarm monitor installed. | G: 61. Install alarm monitor in facility residence | 07/31/2009 | 07/31/2009 | |
Monthly electrical loads determined. | H: 61. Determine additional power requirements for well pumps and water heater. | 09/30/2009 | 09/30/2009 | |
Attach Progress Report in Pisces | J: 132. Submit Progress Report for the period Aug 2008 thru Feb 2009 | 10/30/2009 | ||
Ensure Parkdale Fish Facility Phase I upgrades meet design specifications and building codes. | K: 171. Inspect construction of Phase I upgrades. | 09/01/2009 | 09/01/2009 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Routine administration of project | 02/09/2007 | ||||||
B | 165 | Provide all EC and permits to BPA | 02/09/2007 | ||||||
C | 171 | Construct well house. | 12/17/2008 | ||||||
D | 171 | Install pipeline. | 12/05/2008 | ||||||
E | 171 | Install discharge headers. | 12/17/2008 | ||||||
F | 61 | Provide emergency power to facility residence. | 12/17/2008 | ||||||
G | 61 | Install alarm monitor in facility residence | 12/17/2008 | ||||||
H | 61 | Determine additional power requirements for well pumps and water heater. | 08/05/2000 | ||||||
I | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
J | 132 | Submit Progress Report for the period Aug 2008 thru Feb 2009 | 02/09/2007 | ||||||
K | 171 | Inspect construction of Phase I upgrades. | 02/09/2007 |