Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 68072: 1988-053-15 CAP HRPP CAPITAL IMPROVEMENTS
Project Number:
Title:
Hood River Artificial Production-Parkdale
Stage:
Complete
Area:
Province Subbasin %
Columbia Gorge Hood 100.00%
Contract Number:
68072
Contract Title:
1988-053-15 CAP HRPP CAPITAL IMPROVEMENTS
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
Funds from this project will be used to repair and up-grade Hood River Production Program facilities.

Two components of the Moving Falls Fish Facility (MFFF) are not functioning as designed. The four 80' X 8' fiberglass raceways are warping and cracking. The MFFF fish ladder entrance auxiliary water supply (AWS) is not routing sediment as designed.  To remedy these problems project funds will be used to replace the raceways and install a slide gate in the AWS.

The SCADA alarm system at Parkdale Fish Hatchery is dated and does not provide reliable protection at the MFFF. Technical support for the existing system is only provided by one vendor located in Spokane resulting in delay in necessary repairs.  The alarm system will be retrofitted or replaced with current technology that can be maintained remotely.

PFH hatch house requires additional infrastructure to reduce egg tray densities. Two - four new stack incubators (containing a total of16 trays) need to be purchased and installed.

The early rearing facility at PFH is housed under a temporary awning with above ground piping. A  30' x 40' steel building  will be constructed, plumbed and wired on hatchery grounds to house the rearing vessels.

To segregate hatchery from wild winter steelhead consistent with current guidelines the HRPP will design a permanent adult  trapping facility to replace the existing temporary resistance board weir.  

Specific tasks in this contract include:
Moving Falls Fish Rearing Facility:
Replace fiberglass raceways with concrete.
Install predator fencing around facility.
Inspect water intake for blockage.


Moving Fall Fish Ladder:
Fabricate and install a slide gate in the AWS to flush sediment.

Parkdale Fish Hatchery:
Upgrade or replace existing alarm system.
Install two - four vertical stack incubators (16 trays) and associated plumbing in the hatch house.
Relocate early reariing infrastructure inside a steel building.


Work with ODFW to design a Neal Creek Adult Fish Trap Design to replace the existing temporary trap.

Secure long term access agreement landowner of MFFF

June 2018:  Complete Master Plan upadate and improve MFFF access road
Account Type(s):
Capital
Contract Start Date:
03/01/2015
Contract End Date:
06/30/2020
Current Contract Value:
$1,168,951
Expenditures:
$1,168,951

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All required environmental and land use permits secured. B: 165. Environmental Compliance 03/27/2015 03/27/2015
Manage Contract C: 119. Contract Management 09/30/2018 11/22/2017
Construct four concrete raceways at the MFFF. D: 171. Install concrete raceways. 09/29/2017 09/15/2017
Install predator fencing. E: 171. Construct predator fencing around Moving Falls Fish Facility (MFFF). 01/31/2017 01/31/2017
MFFF water intake inspected. F: 171. Inspect MFFF water intake for blockage. 10/15/2015 08/06/2015
MFFF ladder AWS slide gate installed. G: 171. Install slide gate in MFFF auxillary water supply (AWS). 12/18/2015 09/30/2015
Sixteen trays (in two to four stacks) installed in PFH hatch house. H: 171. Reduce Egg Tray Densities in Parkdale Fish Hatchery Hatch House 07/31/2017 06/30/2017
PFH alarm system upgraded. I: 171. Upgrade HRPP alarm system. 09/29/2018 12/22/2017
Report summarizing contract accomplishments L: 132. Submit Progress Reports for the period March 2015 - September 2017 and October 2017 - September 2018 06/30/2020
PFH early rearing tanks enclosed M: 171. Enclose Parkdale Fish Hatchery early rearing tanks 12/15/2017 12/14/2017
Complete the Certification of the Moving Falls Facility Water Right Q: 154. Complete water right certification for MFFF 12/31/2017 12/21/2017
Complete risk assessment and determine next phase. R: 175. PFH Berm Phase I: Prepare designs and specifications for Parkdale Berm 09/30/2018 09/28/2018
PFH Phase II berm work completed. S: 61. PFH Berm Phase II: Implement preferred alternative from Phase I risk assessment. 09/30/2019 08/31/2017
Properly Functioning Intake Structure at Moving Falls T: 61. Maintain/repair water intake structure at the Moving Falls Fish Facility 12/31/2018 06/13/2018
HRPP Master Plan updated. U: 196. HRPP Master Plan Update 09/30/2019 09/30/2019
MFFF access road improved. V: 171. Moving Falls Access Road Improvement 06/26/2020 06/19/2020
Two grey water pumps replaced. W: 61. Replace grey water lift station at PFH 06/30/2020 12/20/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (Oncorhynchus tshawytscha) - All Populations
  • 1 instance of WE 196 Council Step Process
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened)
  • 3 instances of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 7 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened)
  • 1 instance of WE 175 Produce Design
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 196 Council Step Process
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened)
  • 3 instances of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 3 instances of WE 175 Produce Design
  • 1 instance of WE 154 Develop and Negotiate Water Right Transaction
  • 3 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2015
B 165 Environmental Compliance 03/01/2015
C 119 Contract Management 03/01/2015
D 171 Install concrete raceways. 03/02/2016
E 171 Construct predator fencing around Moving Falls Fish Facility (MFFF). 03/02/2015
F 171 Inspect MFFF water intake for blockage. 03/01/2015
G 171 Install slide gate in MFFF auxillary water supply (AWS). 03/02/2015
H 171 Reduce Egg Tray Densities in Parkdale Fish Hatchery Hatch House 03/02/2015
I 171 Upgrade HRPP alarm system. 03/01/2015
J 175 Dee Mill adult fish trap planning. 03/01/2015
K 171 Neal Creek steelhead acclimation infrastructure development. 03/02/2015
L 132 Submit Progress Reports for the period March 2015 - September 2017 and October 2017 - September 2018 03/01/2015
M 171 Enclose Parkdale Fish Hatchery early rearing tanks 05/22/2017
N 175 Plan adult fish trapping facility in Neal Creek. 03/01/2015
O 171 Construction of the Neal Creek adult fish trap
P 172 Purchase MFFF land from Weyerhaeuser 03/01/2015
Q 154 Complete water right certification for MFFF 03/01/2015
R 175 PFH Berm Phase I: Prepare designs and specifications for Parkdale Berm 09/15/2018
S 61 PFH Berm Phase II: Implement preferred alternative from Phase I risk assessment. 10/15/2018
T 61 Maintain/repair water intake structure at the Moving Falls Fish Facility 03/01/2015
U 196 HRPP Master Plan Update
V 171 Moving Falls Access Road Improvement 09/30/2019
W 61 Replace grey water lift station at PFH 01/16/2020