Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental compliance documentation submitted to BPA | A: 165. Submit environmental compliance documentation to BPA & Lower Newsome Roads NEPA | 11/30/2011 | ||
Stream reaches 5 & 4 tailings removed and re-graded | B: 52. Newsome Creek Floodplain Restoration, Reach 5 & 4 | 11/30/2011 | 10/04/2011 | |
Stream reach 5 channel reconstruction and restoration | C: 30. Newsome Creek Channel Restoration, Reach 5 & 4 | 11/30/2011 | 10/04/2011 | |
Stream reaches 5 & 4 structure installation | D: 29. Newsome Creek Structure Installation, Reach 5 & 4 | 11/30/2011 | 10/04/2011 | |
Plant propagation for Newsome Creek stream restoration | E: 47. Plant Propagation Newsome Stream Restoration | 11/30/2011 | ||
Will not be completed under this contract | F: 47. Plant Stream Reach 5 | 07/28/2011 | ||
Lower Newsome Phase I road decommissioning/improvement designs complete | G: 175. Lower Newsome Phase I Road Decommissioning/Improvement Design | 11/30/2011 | 11/28/2011 | |
Will not be completed under this contract | H: 33. Lower Newsome Phase I Road Decommissioning/Improvement | 07/28/2011 | ||
Decommissioned roads data collected | I: 157. Removed roads data collection | 11/30/2011 | 09/15/2011 | |
Stream habitat data collected | J: 157. Stream Habitat Data Collection | 11/30/2011 | 10/18/2011 | |
Data analyzed and reports completed | K: 162. Condition/Health of Newsome Creek | 11/30/2011 | 11/28/2011 | |
FY 2012 SOW package and FY 2010 & 2011 accrual estimates | L: 119. Management, Coordination and Communication | 09/23/2011 | 09/23/2011 | |
Final FY 09 annual report attached to this contract | M: 132. Submit Annual Report for the period 12/1/08 - 11/30/09 | 01/29/2010 | 01/29/2010 | |
Final FY 2010 annual report attached to this contract | N: 132. Submit Annual Report for the period 12/1/09 - 11/30/2010 | 01/29/2011 | 01/29/2011 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Snake River Spring/Summer (not listed) |
|
Steelhead (O. mykiss) - Snake River DPS (Threatened) |
|
Cutthroat Trout, Westslope (O. c. lewisi) |
|
Trout, Bull (S. confluentus) (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Submit environmental compliance documentation to BPA & Lower Newsome Roads NEPA | 02/09/2007 | ||||||
B | 52 | Newsome Creek Floodplain Restoration, Reach 5 & 4 | |||||||
C | 30 | Newsome Creek Channel Restoration, Reach 5 & 4 | |||||||
D | 29 | Newsome Creek Structure Installation, Reach 5 & 4 | |||||||
E | 47 | Plant Propagation Newsome Stream Restoration | |||||||
F | 47 | Plant Stream Reach 5 | |||||||
G | 175 | Lower Newsome Phase I Road Decommissioning/Improvement Design | 12/01/2009 | ||||||
H | 33 | Lower Newsome Phase I Road Decommissioning/Improvement | |||||||
I | 157 | Removed roads data collection | |||||||
J | 157 | Stream Habitat Data Collection | |||||||
K | 162 | Condition/Health of Newsome Creek | 02/09/2007 | ||||||
L | 119 | Management, Coordination and Communication | 02/09/2007 | ||||||
M | 132 | Submit Annual Report for the period 12/1/08 - 11/30/09 | 02/09/2007 | ||||||
N | 132 | Submit Annual Report for the period 12/1/09 - 11/30/2010 | 12/01/2009 | ||||||
O | 185 | Periodic Status Reports for BPA | 02/09/2007 |