Upload SOW, budget, property inventory for upcoming contract period to Pisces. |
A: 119. Manage and Administer Project |
|
11/01/2010 |
11/01/2010 |
Receipt of environmental compliance clearance from BPA |
B: 165. Produce Environmental Compliance Documentation |
|
09/30/2010 |
01/31/2011 |
List of final projects |
E: 114. CTUIR Umatilla Subbasin Restoration Coordination |
|
01/31/2011 |
01/31/2011 |
Provide technical input and summaries to enhance or protect natural resources in the subbasin. |
F: 122. Review and provide technical input on issues and topics that affect the areas natural resource |
|
01/31/2011 |
01/31/2011 |
Coordinate watershed association activities |
G: 191. Umatilla River Watershed coordination duties |
|
01/31/2011 |
01/31/2011 |
Complete outreach and education activities |
H: 99. Public Outreach and Education |
|
01/31/2011 |
01/31/2011 |
Produce methods for monitoring project effectiveness |
I: 156. Incorporate developed strategic and scientifically accepted monitoring methods for application |
|
01/31/2011 |
01/31/2011 |
Complete data collection and summarized findings |
J: 157. Monitoring and Evaluation CTUIR Umatilla Anadromous Fish Habitat Project |
|
01/31/2011 |
01/31/2011 |
Maximize survival of planted trees and shrubs in enhancement project areas |
K: 22. Maintain trees and shrubs, and grass seeding in Umatilla River Basin habitat enhancement areas |
|
01/31/2011 |
01/31/2011 |
Complete scheduled tree and shrub plantings in project areas |
L: 47. Supplement riparian areas of existing and new projects with additional vegetation |
|
01/31/2011 |
01/31/2011 |
Treat 512 acres (109 riparian & 403 upland) in enhancement areas |
M: 53. Control of noxious weeds in project areas by physical and chemical means |
|
01/31/2011 |
01/31/2011 |
Maintain proper operation of instream habitat structures |
N: 186. Inspect and maintain function of instream improvement structures |
|
01/31/2011 |
01/31/2011 |
Maintenance of land or structures associated with conservation easements |
O: 186. Maintenance of habitat features associated with project conservation easements |
|
01/31/2011 |
01/31/2011 |
Complete channel reconstruction or enhancement on 1.3 miles of stream |
P: 29. Meacham Creek floodplain restoration and in-stream enhancement, river miles 6.0 to 7.3 |
|
01/31/2011 |
|
Complete levee removal floodplain enhancements to Meacham Creek |
Q: 180. Enhance floodplain connectivity and function via levee setback on Meacham Creek, river miles 6.0-7.3 |
|
01/31/2011 |
|
10.0 miles of fence constructed on Meacham Creek |
R: 40. Install riparian fence enclosure in Meacham Creek, river miles 2.0-9.0 |
|
01/31/2011 |
|
Complete implementation of the channel reconstruction on 1.5 miles of stream |
S: 29. Lower Umatilla River bank stabilization and habitat restoration |
|
09/30/2010 |
|
Maintain 355 acres (61 riparian, 294 upland) in project area |
T: 22. Enhance native vegetation growth in the B&G Resources Property, Umatilla River (RM 41-44) |
|
11/30/2010 |
11/30/2010 |
Complete Instream Habitat and Bank Stability Structures |
U: 29. Birch Creek bank stabilization and habitat restoration, river mile 2.8 |
|
11/30/2010 |
11/10/2010 |
Incorporate final plan into the project annual report |
V: 174. Incorporate Umatilla River and Willow Creek watershed habitat assessment plan findings into project |
|
01/31/2011 |
01/31/2011 |
Produce draft plan for a repeatable riparian and floodplain vegetation monitoring strategy |
W: 174. Meacham Creek vegetation survey and repeatable monitoring strategy |
|
01/31/2011 |
01/31/2011 |
Modify irrigation dam for fish passage |
X: 84. Tier 2 Work Element: Peterson Dam Modification Project on Birch Creek, river mile 2.5 |
|
08/15/2010 |
|
Initiate project coordination and identify priority status and implementation need. |
Y: 175. Tier 2 Work Element: Westland/Ramos Habitat Restoration Project Plan |
|
01/31/2011 |
01/31/2011 |