Province | Subbasin | % |
---|---|---|
Basinwide | - | 100.00% |
Previous: | Next: |
---|---|
40289: 2001-003-00 EXP INSTALL/EVAL OF ESTABLISHED PIT TAG TECHNOLOGIES |
|
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Cecilia Brown | Bonneville Power Administration | Yes | COR | ckbrown@bpa.gov | (503) 230-3462 |
Douglas Dey | National Oceanic and Atmospheric Administration | No | Supervisor | doug.dey@noaa.gov | (206) 860-3237 |
Sandra Downing | National Oceanic and Atmospheric Administration | Yes | Contract Manager | sandy.downing@noaa.gov | (206) 860-5604 |
Israel Duran | Bonneville Power Administration | No | Env. Compliance Lead | induran@bpa.gov | (503) 230-3967 |
Paul Krueger | Bonneville Power Administration | Yes | F&W Approver | pqkrueger@bpa.gov | (503) 230-5723 |
Mary Nolting | National Oceanic and Atmospheric Administration | No | Administrative Contact | mary.nolting@noaa.gov | (206) 860-3232 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Nancy Weintraub | Bonneville Power Administration | No | Interested Party | nhweintraub@bpa.gov | (503) 230-5373 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Funding Package - Submit draft to COTR | A: 119. Administration tasks for this project | 07/01/2010 | 08/23/2010 | |
Environmental compliance documentation | B: 165. NEPA, ESA, & Section 106 NHPA review of Work elements that require EC | 04/30/2010 | 12/01/2009 | |
Data from the evaluation of the network of interrogation systems for adult salmonids | C: 162. Evaluate performance of the entire network of adult interrogation systems | 11/30/2010 | ||
Data from the evaluation of the prototype transceiver and analysis on the number of antennas | D: 157. Evaluation of a new transceiver model for replacing the current series of transceivers | 11/30/2010 | ||
Document outlining the tests that will be used to evaluate the different PIT tag models. | E: 156. Developing the protocol for evaluating new PIT-tag models | 04/30/2010 | 04/13/2010 | |
Data collected from the evaluation of the different PIT tag models | F: 157. Conducting lab and field tests on different PIT-tag models | 11/30/2010 | ||
Analysis of the data collected from the tests used to evaluate new PIT-tag models | G: 162. Analyze the results from the tests used to evaluate the different PIT-tag models | 11/30/2010 | ||
Section in PSMFC progress report | H: 156. Assist in development of new separation-by-code software | 08/31/2010 | 08/31/2010 | |
Attach Progress Report in Pisces | I: 132. Submit Progress Report for the period (Dec 2008) to (Nov 2009) | 09/15/2010 | ||
Attach Progress Report in Pisces | J: 132. Submit Progress Report for the period (Dec 2007) to (Nov 2008) | 04/30/2010 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (Oncorhynchus tshawytscha) - All Populations |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Sockeye (Oncorhynchus nerka) - All Populations |
|
Steelhead (Oncorhynchus mykiss) - All Populations |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 119 | Administration tasks for this project | 02/09/2007 | ||||||
B | 165 | NEPA, ESA, & Section 106 NHPA review of Work elements that require EC | 12/01/2009 | ||||||
C | 162 | Evaluate performance of the entire network of adult interrogation systems | 02/09/2007 | ||||||
D | 157 | Evaluation of a new transceiver model for replacing the current series of transceivers | 12/01/2009 | ||||||
E | 156 | Developing the protocol for evaluating new PIT-tag models | 12/01/2009 | ||||||
F | 157 | Conducting lab and field tests on different PIT-tag models | 12/01/2009 | ||||||
G | 162 | Analyze the results from the tests used to evaluate the different PIT-tag models | 12/01/2009 | ||||||
H | 156 | Assist in development of new separation-by-code software | 02/09/2007 | ||||||
I | 132 | Submit Progress Report for the period (Dec 2008) to (Nov 2009) | 02/09/2007 | ||||||
J | 132 | Submit Progress Report for the period (Dec 2007) to (Nov 2008) | 12/01/2009 | ||||||
K | 185 | Periodic Status Reports for BPA | 02/09/2007 |