Province | Subbasin | % |
---|---|---|
Columbia Plateau | Crab | 100.00% |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Douglas Corkran | Bonneville Power Administration | Yes | Env. Compliance Lead | dfcorkran@bpa.gov | (503) 230-7646 |
Sandra Fife | Bonneville Power Administration | Yes | COR | safife@bpa.gov | (503) 230-3678 |
Greg Fitzgerald | Washington Department of Fish and Wildlife (WDFW) | Yes | Contract Manager | gregory.fitzgerald@dfw.wa.gov | (509) 765-6641 |
Brenda Heister | Bonneville Power Administration | Yes | Contracting Officer | bsheister@bpa.gov | (503) 230-3531 |
Janice Jackson | Washington Department of Fish and Wildlife (WDFW) | No | Administrative Contact | janice.jackson@dfw.wa.gov | (360) 902-2444 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Matt Monda | Washington Department of Fish and Wildlife (WDFW) | No | Supervisor | mondamjm@dfw.wa.gov |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Environmental Compliance | A: 165. Environmental compliance documentation | 02/01/2010 | 02/01/2010 | |
Water Use Documentation | B: 181. Coordinate with BOR and Quincy Irrigation District | 09/30/2010 | 09/30/2010 | |
Armor dikes at the TD-1 site | C: 186. Inspect, repair, physical enhancements and dikes at TD-1 site | 01/31/2011 | 01/31/2011 | |
Armor dikes at the TD-2 site | D: 186. Inspect and repair dikes at TD-2 site | 01/31/2011 | 01/31/2011 | |
Seed disturbed soil at TD-1 | E: 186. Seed disturbed soil at TD-1 site | 01/31/2011 | 01/31/2011 | |
Seed disturbed soil at TD-2 | F: 186. Seed disturbed soil at TD-2 site | 01/31/2011 | 01/26/2011 | |
TD-1 cells tilled | G: 22. Till cells at TD-1 | 07/31/2010 | 06/24/2010 | |
Seed 50 acres of moist soil vegetation at TD-1 project site | H: 47. Moist soil seeding in TD-1 | 08/15/2010 | 07/13/2010 | |
Monitor and maintain moist soil vegetation stand at TD-1 project site | I: 22. Monitor and maintain desirable vegetation | 09/30/2010 | 09/30/2010 | |
Control of undesirable/invasive vegetation at TD-1 | J: 53. Control undesirable vegetation at TD-1 | 01/31/2011 | 01/31/2011 | |
Control of undesirable/invasive vegetation at TD-2 project site | K: 53. Control undesirable vegetation at TD-2 | 01/31/2011 | 01/31/2011 | |
Water in wetland cells at TD-1 | L: 186. Operate water control structures at TD-1 | 01/31/2011 | 01/31/2011 | |
BPA required administrative duties | M: 119. BPA Administrative requirements | 01/31/2011 | 01/31/2011 | |
Wildlife Area Administrative duties | N: 119. WDFW Administrative Requirements | 01/31/2011 | 01/31/2011 | |
Attach Progress Report in Pisces | P: 132. Submit Progress Report for the period | 01/31/2011 | 01/31/2011 | |
Numbers and species of waterfowl using TD1 and TD2 waters through the fall and winter | Q: 157. Fall and winter waterfowl counts | 01/31/2011 | 01/07/2011 | |
Numbers and species of waterfowl pairs using TD2 waters in the spring. | R: 157. Spring waterfowl pair counts | 05/31/2010 | 05/17/2010 |
Primary Focal Species | Work Statement Elements |
---|---|
Wildlife |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | Environmental compliance documentation | 02/09/2007 | ||||||
B | 181 | Coordinate with BOR and Quincy Irrigation District | 02/09/2007 | ||||||
C | 186 | Inspect, repair, physical enhancements and dikes at TD-1 site | 02/09/2007 | ||||||
D | 186 | Inspect and repair dikes at TD-2 site | 02/09/2007 | ||||||
E | 186 | Seed disturbed soil at TD-1 site | 02/09/2007 | ||||||
F | 186 | Seed disturbed soil at TD-2 site | 02/09/2007 | ||||||
G | 22 | Till cells at TD-1 | 02/09/2007 | ||||||
H | 47 | Moist soil seeding in TD-1 | 02/09/2007 | ||||||
I | 22 | Monitor and maintain desirable vegetation | 02/09/2007 | ||||||
J | 53 | Control undesirable vegetation at TD-1 | 02/09/2007 | ||||||
K | 53 | Control undesirable vegetation at TD-2 | 02/09/2007 | ||||||
L | 186 | Operate water control structures at TD-1 | 02/09/2007 | ||||||
M | 119 | BPA Administrative requirements | 02/09/2007 | ||||||
N | 119 | WDFW Administrative Requirements | 02/09/2007 | ||||||
O | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
P | 132 | Submit Progress Report for the period | 02/09/2007 | ||||||
Q | 157 | Fall and winter waterfowl counts | 02/01/2010 | ||||||
R | 157 | Spring waterfowl pair counts | 02/01/2010 |