Contract 40094: 200600300 EXP DESERT WILDLIFE AREA O&M
Project Number:
Title:
Desert Wildlife Mitigation
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Crab 100.00%
Contract Number:
40094
Contract Title:
200600300 EXP DESERT WILDLIFE AREA O&M
Contract Continuation:
Previous: Next:
34927: 2006-003-00 PL DESERT WILDLIFE AREA O&M
  • 46876: 200600300 EXP DESERT WILDLIFE AREA O&M
Contract Status:
Closed
Contract Description:
Operate and maintain two wetland enhancement projects on the Desert Wildlife Area that have been funded, in part, by the BPA.  This contract will provide funding to operate and maintain the enhanced wetlands for one year to insure that they remain functional.  
The TD-1 project is near completion; and when operated this fall will fill 7 wetland basins by diverting surface water from the Frenchman Hills wasteway into wetland basins.  Enhancements at the TD-1 Project include: installation of 11 water control structures, construction of ditches and dikes for water management, sculpting wetland basins to optimal depth for wetland obligate birds,  armoring 400 ft of dikes to protect against beaver and burrowing mammals, seeding disturbed soil resulting from construction activities, and tilling wetland cells to promote desirable moist soil vegetation.  
Operation and maintenance of TD-1 will include: coordination with BOR and Quincy Irrigation District, inspecting /repairing enhancements, re-seeding areas that failed to establish desirable vegetation in 2008, controlling undesirable vegetation and noxious weeds, operating water control structures, producing required BPA reports, and administering the contract.  
Enhancements at the TD-2 Project include: enhancement of 19 late-succession stage wetlands by excavation of organic material, construction of dikes to isolate enhanced wetlands from the Winchester Wasteway, allowing for control of unwanted fish populations in the project ponds, armoring over 1,200 feet of isolation dikes to protect against beaver damage and burrowing mammals, and seeding disturbed soils resulting from construction activities.
Operation and maintenance of TD-2 will include: inspecting and repairing enhancements, controlling undesirable vegetation and noxious weeds,  producing required BPA reports, and administering the contract.
Management of all project ponds will attempt to maximize habitat quality for waterfowl, shorebirds, and other wetland obligate wildlife species.
Account Type(s):
Expense
Contract Start Date:
10/01/2008
Contract End Date:
01/31/2010
Current Contract Value:
$50,645
Expenditures:
$50,645

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Water Use Documentation A: 181. Coordinate with BOR and Quincy Irrigation District 09/30/2009 09/30/2009
Environmental Compliance B: 165. Environmental compliance documentation 10/01/2008 10/01/2008
Armor dikes at the TD-1 site C: 186. Inspect, repair, physical enhancements and dikes at TD-1 site 09/30/2009 09/30/2009
Armor dikes at the TD-2 site D: 186. Inspect and repair dikes at TD-2 site 09/30/2009 09/30/2009
Seed disturbed soil at TD-1 E: 186. Seed disturbed soil at TD-1 site 03/31/2009 12/10/2008
Seed disturbed soil at TD-2 F: 186. Seed disturbed soil at TD-2 site 03/15/2009 03/16/2009
TD-1 cells tilled G: 22. Till cells at TD-1 06/30/2009 07/22/2009
Seed 50 acres of moist soil vegetation at TD-1 project site H: 47. Moist soil seeding in TD-1 07/15/2009 07/28/2009
Monitor and maintain moist soil vegetation stand at TD-1 project site I: 22. Monitor and maintain desirable vegetation 09/30/2009 09/22/2009
Control of undesirable/invasive vegetation at TD-1 J: 53. Control undesirable vegetation at TD-1 09/30/2009 09/22/2009
Control of undesirable/invasive vegetation at TD-2 project site K: 53. Control undesirable vegetation at TD-2 09/30/2009 09/22/2009
Water in wetland cells at TD-1 L: 186. Operate water control structures at TD-1 06/01/2009 04/15/2009
Recontour basin drainages at TD-1 as needed M: 181. Ensure wetland cells drain completely at TD-1 09/15/2009
BPA required administrative duties N: 119. BPA Administrative requirements 01/31/2010 01/31/2010
Wildlife Area Administrative duties O: 119. WDFW Administrative Requirements 10/31/2009 11/24/2009
Attach Progress Report in Pisces P: 132. Submit Progress Report for the period October 2008 through September 2009 09/30/2009 09/30/2009

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 2 instances of WE 22 Maintain Vegetation
  • 5 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 2 instances of WE 53 Remove Vegetation
  • 2 instances of WE 181 Create, Restore, and/or Enhance Wetland

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 181 Coordinate with BOR and Quincy Irrigation District 02/09/2007
B 165 Environmental compliance documentation 02/09/2007
C 186 Inspect, repair, physical enhancements and dikes at TD-1 site 02/09/2007
D 186 Inspect and repair dikes at TD-2 site 02/09/2007
E 186 Seed disturbed soil at TD-1 site 02/09/2007
F 186 Seed disturbed soil at TD-2 site 02/09/2007
G 22 Till cells at TD-1 02/09/2007
H 47 Moist soil seeding in TD-1 02/09/2007
I 22 Monitor and maintain desirable vegetation 02/09/2007
J 53 Control undesirable vegetation at TD-1 02/09/2007
K 53 Control undesirable vegetation at TD-2 02/09/2007
L 186 Operate water control structures at TD-1 02/09/2007
M 181 Ensure wetland cells drain completely at TD-1 02/09/2007
N 119 BPA Administrative requirements 02/09/2007
O 119 WDFW Administrative Requirements 02/09/2007
P 132 Submit Progress Report for the period October 2008 through September 2009 02/09/2007
Q 185 Periodic Status Reports for BPA 02/09/2007