Contract 47379: 2008-602-00 EXP LEMHI RIVER RESTORATION PLANNING
Project Number:
Title:
Upper Salmon Basin Habitat Restoration
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Mountain Snake Salmon 100.00%
Contract Number:
47379
Contract Title:
2008-602-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Continuation:
Previous: Next:
n/a
  • 53200: 2010-072-00 EXP LEMHI RIVER RESTORATION PLANNING
Contract Status:
History
Contract Description:
The Upper Lemhi River Restoration Planning contract provides the Idaho Office of Species Conservation (OSC) with funding to cover subcontracted expenses associated with on the ground implementation of salmon and steelhead recovery projects in the Lemhi watershed.  Habitat projects will be implemented for 2008-602-00 Upper Lemhi River - Restoration and 2008-606-00 Lower Lemhi Habitat - Restoration.  

In 2008, Idaho's Governor directed that all funding and contracting for Idaho's Accord projects was to go through the OSC.  OSC manages individual projects as needed to ensure adequate oversight and provide that all state agencies and their partners work in a coordinated fashion.  OSC will provide contract oversight.  Implementation work will be completed by a subcontractor, Lemhi Soil and Water Conservation District (District).  

Deliverables under the contract include project imp... lementation support.  The subcontractor will also assist BPA's Environmental Compliance Lead to ensure that environmental compliance requirements are met during habitat project implementation.   
Account Type(s):
Expense
Contract Start Date:
06/01/2010
Contract End Date:
05/31/2011
Current Contract Value:
$33,345
Expenditures:
$33,345

* Expenditures data includes accruals and are based on data through 31-Mar-2025.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
50 km
50 mi
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements
Loading...
Sort Order
WSEV ID
WE ID
Work Element Name
Title
Description
WSE Effective Budget
% of Total WSE Effective Budget
WSE Start
WSE End
         

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Assist BPA's Environmental Compliance Lead to meet necessary environmental compliance requirements. A: 165. Environmental Compliance: Upper Lemhi Restoration & Lower Lemhi Habitat Restoration 05/31/2011 05/31/2011
Funding Package - Submit draft to COTR B: 119. Manage and Administer Lemhi River Restoration Planning contract 03/15/2011 03/23/2011
Provide project implementation support. C: 119. Manage and Administer Habitat Projects: Provide Project Implementation Support 05/31/2011 05/31/2011
Participate in local planning meetings as needed D: 191. Participate in local planning meetings as needed 05/31/2011 05/31/2011
Attach Progress Report in Pisces F: 132. Submit Progress Report for the period (Jun 2010) to (May 2011) 05/01/2011 05/31/2011

Viewing of Implementation Metrics
Loading...
Sort Order
WE ID
Work Element Name
Title
Description
Metric ID
Metric
End Fiscal Year
Planned
Actual
Contractor Comments
All Measures
Annual Progress Report Measures
Populations
Viewing of Environmental Metrics Customize
Loading...
WSE ID
WSE Start
WSE End
WE ID
Title
WSE Progress
Study Plan
Protocol
Category
Subcategory
Focus 1
Focus 2
Specific Metric Title

Primary Focal Species Work Statement Elements

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Environmental Compliance: Upper Lemhi Restoration & Lower Lemhi Habitat Restoration 06/01/2010
B 119 Manage and Administer Lemhi River Restoration Planning contract 06/01/2010
C 119 Manage and Administer Habitat Projects: Provide Project Implementation Support 06/01/2010
D 191 Participate in local planning meetings as needed 06/01/2010
E 185 Periodic Status Reports for BPA 06/01/2010
F 132 Submit Progress Report for the period (Jun 2010) to (May 2011) 06/01/2010