Provide EC documentation |
A: 165. Provide EC documentation |
|
06/30/2012 |
06/30/2012 |
Funding Package - Submit draft to COTR |
B: 119. Manage and Administer Project |
|
07/20/2012 |
07/24/2012 |
Eagle Valley riparian fence |
C: 40. Eagle Valley Ranch fence |
|
09/30/2011 |
04/15/2011 |
Little Springs Creek Channel Restoration |
D: 30. Little Springs Creek Channel Restoration |
|
07/31/2011 |
11/01/2010 |
Attach Progress Report in Pisces |
E: 132. Submit Progress Report for the period (Sept 2010) to (Aug 2011) |
|
12/15/2011 |
12/21/2011 |
Realigning or creating new channel segment in Bohannon Creek |
G: 30. Realign and/or Create new channel in Bohannon Creek |
|
08/14/2012 |
|
Revegetate riparian areas |
H: 47. Replant disturbed area and new channels with native Riparian vegetation |
|
08/14/2012 |
|
Diversion consolidation and removal. |
I: 84. Diversion removal and consolidation and construction of new diversion |
|
08/14/2012 |
|
Bohannon Creek Diversion Pipeline |
J: 149. New Bohannon Creek diversion pipe. |
|
08/14/2012 |
08/14/2012 |
Bohannon Creek fish passage structure |
K: 184. Fish Passage at new Bohannon Creek Diversion |
|
08/14/2012 |
|
Installed, operational sprinkler irrigation system |
L: 150. Lemhi Little Springs Creek: Install Pivot Irrigation System, Including Pump |
|
09/30/2011 |
09/30/2011 |
Landowner to remove three diversions |
M: 84. Lemhi Little Springs Creek: Remove Diversions |
|
09/30/2011 |
08/31/2011 |
Install pipeline, including excavation, backfill and boring under Highway 28 and Little Springs Crk |
N: 149. Lemhi Little Springs Creek: Install Pipeline |
|
05/31/2011 |
05/31/2011 |
Reseed as needed. |
O: 47. Lemhi Little Springs Creek: Reseed as needed |
|
05/31/2011 |
05/31/2011 |
Install new culvert including excavation and backfill |
P: 184. Lemhi Little Springs Creek: install Ranch Road culvert |
|
05/27/2011 |
05/31/2011 |
Remove existing culvert |
Q: 85. Archie Lane Culvert Replacement: Remove culvert |
|
11/30/2011 |
10/05/2011 |
Install pre-fabricated steel bridge |
R: 184. Archie Lane Culvert Replacement: install steel bridge |
|
11/30/2011 |
10/12/2011 |
Remove culvert |
S: 85. Parmenter Lane Culvert Replacement: remove culvert |
|
09/30/2011 |
09/15/2011 |
Install pre-fabricated steel bridge |
T: 184. Parmenter Lane Culvert Replacement: install bridge |
|
10/07/2011 |
09/30/2011 |
Install Lemhi Little Springs Creek Riparian Fence |
U: 40. Lemhi Little Springs Creek: Install Snyder Fence |
|
12/23/2011 |
12/16/2011 |
Wimpey Creek #2 Diversion Replacement Project |
V: 84. Wimpey Creek #2: Diversion Replacement |
|
11/04/2011 |
11/11/2011 |
Install Riparian Fence |
W: 40. Wimpey Creek #2: Install Fence |
|
10/25/2011 |
11/11/2011 |
Plant Vegetation |
X: 47. Wimpey Creek #2: Plant Vegetation |
|
10/14/2011 |
11/11/2011 |
Upper Lemhi River Restoration |
Y: 30. Realign and create new channel for the Upper Lemhi River |
|
12/31/2011 |
05/23/2011 |
Upper Lemhi New Channel riparian fence |
Z: 40. Install fence along new and realigned Upper Lemhi River channel |
|
12/31/2011 |
12/31/2011 |
revegetate riparian areas, streambanks, and other disturbed or constructed areas. |
AA: 47. revegetate newly contructed/realigned Upper Lemhi River Channel and disturbed areas |
|
01/16/2012 |
12/30/2011 |
Attach Progress Report in Pisces |
AB: 132. Submit Progress Report for the period (8/15/2011) to (8/14/2012) |
|
08/14/2012 |
|
Bridge to be ordered and purchased. |
AC: 184. Canyon Creek: Purchase Bridge |
|
08/14/2012 |
08/13/2012 |
Filters Installed and operational |
AD: 150. Beyeler Sprinkler Modification: Filters |
|
08/14/2012 |
|