Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 49582: 2003-023-00 CAP CHIEF JOSEPH CONSTRUCTION ELECTRICAL COST
Project Number:
Title:
Chief Joseph Hatchery Program
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Okanogan 100.00%
Contract Number:
49582
Contract Title:
2003-023-00 CAP CHIEF JOSEPH CONSTRUCTION ELECTRICAL COST
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
This contract is to pay fees to Nespelem Valley Coop to bring electrical services from a tap to four separate locations:  1) Tap to Residences and RV Site 2) Tap to Main Hatchery Building 3) Tap to Relief Tunnel 4) Tap to Wells

April 2011 Contract change request is to add funds for upgrading Nespelem Valley Electric Co-op substation in order to serve the hatchery load.
Account Type(s):
Capital
Contract Start Date:
09/01/2010
Contract End Date:
11/30/2011
Current Contract Value:
$587,852
Expenditures:
$587,852

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Provide Funds to Nespelem Valley Coop B: 171. Electrical Tap Costs 08/31/2011 08/31/2011
Submit accruals to BPA as requested C: 119. Submit Accruals to BPA as requested 08/31/2011 08/31/2011
Provide Substation Upgrade to Service Chief Joseph Hatchery D: 171. NVEC Substation Upgrade 11/30/2011 11/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU
  • 2 instances of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 08/01/2010
B 171 Electrical Tap Costs 04/07/2011
C 119 Submit Accruals to BPA as requested 09/01/2010
D 171 NVEC Substation Upgrade 09/01/2010