Province | Subbasin | % |
---|---|---|
Columbia Gorge | Hood | 100.00% |
Previous: | Next: |
---|---|
39362: 1998-021-00 CAP HOOD RIVER FISH HABITAT |
* Expenditures data includes accruals and are based on data through 31-Dec-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Christopher Brun | Confederated Tribes of Warm Springs | Yes | Contract Manager | cbrun@hrecn.net | (541) 352-3548 |
Richard Golden Jr | Bonneville Power Administration | Yes | COR | rlgolden@bpa.gov | (503) 230-5119 |
Brad Houslet | Confederated Tribes of Warm Springs | No | Supervisor | brad.houslet@ctwsbnr.org | (541) 553-2039 |
Joseph McCanna | Confederated Tribes of Warm Springs | Yes | Technical Contact | jmccanna@hrecn.net | (541) 352-9326 |
Arthur Mitchell | Confederated Tribes of Warm Springs | No | Administrative Contact | arthur.mitchell@wstribes.org | (541) 553-3219 |
John Skidmore | Bonneville Power Administration | Yes | F&W Approver | jtskidmore@bpa.gov | (503) 230-5494 |
Kurt Unger | Bonneville Power Administration | Yes | Env. Compliance Lead | klunger@bpa.gov | (503) 230-5885 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Administer contract | B: 119. Routine contract administration. | 12/31/2013 | 12/31/2013 | |
Project administration for the EFID Headworks Improvement Project is complete. | C: 119. Manage EFID Headworks Improvement Project | 12/27/2013 | 12/27/2013 | |
Project administration for the DID Canal Piping Project is complete. | D: 119. Manage DID Canal Piping Project | 09/30/2013 | 09/06/2013 | |
All work complies with environmental regulations | E: 165. Work with BPA on environmental compliance requirements | 05/31/2013 | 05/31/2013 | |
DID Ditch Piping Project Final Design | F: 175. Complete final engineering design for DID ditch piping project. | 08/30/2011 | 12/16/2011 | |
Complete piping of DID open irrigation ditch. | G: 149. Pipe DID irrigation ditch. | 06/28/2013 | 06/28/2013 | |
EFID Headworks construction complete. | H: 84. Construct EFID headworks | 11/29/2013 | 10/25/2013 | |
Final Completion Report for DID Ditch Piping and EFID Headworks Improvement Projects. | I: 132. Project Completion Report for 3/1/11 - 12/31/13 | 12/31/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 02/09/2007 | ||||||
B | 119 | Routine contract administration. | 03/01/2011 | ||||||
C | 119 | Manage EFID Headworks Improvement Project | 02/09/2007 | ||||||
D | 119 | Manage DID Canal Piping Project | 03/01/2011 | ||||||
E | 165 | Work with BPA on environmental compliance requirements | 02/09/2007 | ||||||
F | 175 | Complete final engineering design for DID ditch piping project. | 03/01/2011 | ||||||
G | 149 | Pipe DID irrigation ditch. | 06/11/2012 | ||||||
H | 84 | Construct EFID headworks | 08/01/2013 | ||||||
I | 132 | Project Completion Report for 3/1/11 - 12/31/13 | 03/01/2011 |