Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 52386: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Project Number:
Title:
Yakama Reservation Watershed Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
52386
Contract Title:
1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Continuation:
Previous: Next:
44614: 1996-035-01 EXP YAKAMA RESERVATION WATERSHEDS PROJECT
  • 57335: 1996-035-01 EXP YAKAMA RESERVATION WATERSHED PROJECT
Contract Status:
Closed
Contract Description:
The YRWP works to restore natural function to the Satus, Toppenish and Ahtanum Watersheds. Our restoration and monitoring efforts take a comprehensive approach to the restoration of habitat for fisheries resources including steelhead and bull trout.
Account Type(s):
Expense
Contract Start Date:
03/01/2011
Contract End Date:
02/29/2012
Current Contract Value:
$1,606,313
Expenditures:
$1,606,313

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Shannon Adams Yakama Confederated Tribes Yes Contract Manager adas@yakamafish-nsn.gov (509) 945-0754
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Kelly Clayton Yakama Confederated Tribes Yes Technical Contact clak@yakamafish-nsn.gov (509) 945-7195
Ryan DeKnikker Yakama Confederated Tribes Yes Technical Contact dekr@yakamafish-nsn.gov (509) 945-5389
Edward Gresh Bonneville Power Administration Yes Env. Compliance Lead esgresh@bpa.gov (503) 230-5756
Tana Hoptowit Yakama Confederated Tribes Yes Interested Party hopt@yakamafish-nsn.gov (509) 865-5121x6318
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jay Marcotte Bonneville Power Administration Yes COR jgmarcotte@bpa.gov (503) 230-3943
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Steve Parker Yakama Confederated Tribes No Supervisor pars@yakamafish-nsn.gov (509) 865-6262x6342
Tim Resseguie Yakama Confederated Tribes Yes Technical Contact rest@yakamafish-nsn.gov (509) 945-7409
Brandon Rogers Yakama Confederated Tribes Yes Interested Party rogb@yakamafish-nsn.gov (509) 949-4109
Paul Ward Yakama Confederated Tribes No Supervisor warp@yakamafish-nsn.gov (509) 949-4129


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
projects managed B: 119. Manage Restoration Projects 01/31/2012 01/31/2012
List of Selected Projects (and contingency projects) to be implemented in 2011 C: 114. Select habitat improvement actions for 2011 and identify possible projects for 2012 02/29/2012 12/29/2011
Project databases that are maintained and up to date. D: 160. Update Project Database 02/29/2012 02/29/2012
Disseminated data E: 161. Create informal summary reports and maps 02/29/2012 02/29/2012
5 outreach sessions completed F: 99. Conduct field and classroom education at local schools 02/29/2012 06/06/2011
Technical review and input provided to various policy and planning efforts G: 122. Input to various Tribal planning and policy efforts 02/29/2012 04/29/2011
Completed environmental documentation H: 165. Environmental Compliance 02/29/2012 02/29/2012
Completed FY 10 Annual Report submitted to BPA I: 132. Produce Project Annual Report for FY 10 (3/1/2010 - 2/28/2011) 02/29/2012 02/29/2012
2 rotary screw traps deployed and recovered J: 70. Deploy and Recover 5ft Rotary Screw Traps 02/29/2012 02/29/2012
15 miles of completed snorkel surveys K: 157. Snorkel Surveys 10/31/2011 09/30/2011
Wapato Irrigation Project diversions managed for minimum instream flow. L: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek 09/30/2011 09/30/2011
water diversion managed at Olney lateral to provide minimum streamflow M: 186. Assist with operation of Olney Lateral 02/29/2012 02/29/2012
Functioning fences, wells, stock tanks, and habitat improvements N: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs 02/29/2012 02/29/2012
Data collected and ready to be entered into the Project's databases. O: 157. Collect Field Data 02/29/2012 02/29/2012
complete 1 mile of surveys P: 157. Timber, Fish and Wildlife (TFW) surveys 09/30/2011 08/30/2011
Completed sediment inventories and database Q: 157. Conduct Sediment Inventories 02/29/2012 02/29/2012
2 wells converted to stock wells R: 34. Convert existing wells to stock wells 02/29/2012 02/29/2012
Replace 3 passage barrier culverts with culverts capable of passage S: 184. Panther Creek Culvert Replacement Project 10/31/2011 10/31/2011
An engineered plan and plan for construction T: 175. LaSalle Ahtanum Creek project design 07/31/2011 05/01/2011
Complete engineered design plans for two on Reservation fish screens on Simcoe Creek U: 175. Design 2 on-Reservation Fish Screens on Simcoe Creek 02/29/2012 02/29/2012
Stabilize LaSalle Ahtanum Creek Bank V: 29. LaSalle Ahtanum Creek Bank Stabilization 09/30/2011 09/30/2011
One Completed Reach Assessment. W: 115. Produce a Reach Assessment in the Middle Reach of Toppenish Creek 02/29/2012 02/29/2012
Install buck and pole fence on Camas Patch Road Closure X: 40. Install Fence On Camas Patch 07/29/2011 06/29/2011
Camas Patch Road Relocation Y: 33. Camas Patch Road Relocation 09/30/2011 07/30/2011
Two backwater channels and a swale AA: 30. CCR23987 LaSalle Ahtanum Creek Backwater Channels 09/30/2011 09/30/2011
Floodplain Revegetation AB: 47. CCR23987 LaSalle Ahtanum Creek Floodplain Vegetation 10/28/2011 11/30/2011

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 3 instances of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 30 Realign, Connect, and/or Create Channel
  • 1 instance of WE 33 Decommission Road/Relocate Road
  • 1 instance of WE 34 Develop Alternative Water Source
  • 1 instance of WE 40 Install Fence
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 84 Remove/Install Diversion
  • 1 instance of WE 184 Install Fish Passage Structure
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 2 instances of WE 175 Produce Design
  • 1 instance of WE 70 Install Fish Monitoring Equipment
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 03/01/2011
B 119 Manage Restoration Projects 03/01/2011
C 114 Select habitat improvement actions for 2011 and identify possible projects for 2012 03/01/2011
D 160 Update Project Database 03/01/2011
E 161 Create informal summary reports and maps 03/01/2011
F 99 Conduct field and classroom education at local schools 03/01/2011
G 122 Input to various Tribal planning and policy efforts 03/01/2011
H 165 Environmental Compliance 03/01/2011
I 132 Produce Project Annual Report for FY 10 (3/1/2010 - 2/28/2011) 03/01/2011
J 70 Deploy and Recover 5ft Rotary Screw Traps 03/01/2011
K 157 Snorkel Surveys 03/01/2011
L 186 Manage Operation of Upper and Lower WIP canals on Ahtanum Creek 05/05/2011
M 186 Assist with operation of Olney Lateral 05/05/2011
N 186 Maintain livestock wells/stock tanks/livestock fences/improved springs 05/05/2011
O 157 Collect Field Data 03/01/2011
P 157 Timber, Fish and Wildlife (TFW) surveys 05/05/2011
Q 157 Conduct Sediment Inventories 05/05/2011
R 34 Convert existing wells to stock wells 05/05/2011
S 184 Panther Creek Culvert Replacement Project 08/01/2011
T 175 LaSalle Ahtanum Creek project design 03/01/2011
U 175 Design 2 on-Reservation Fish Screens on Simcoe Creek 03/01/2011
V 29 LaSalle Ahtanum Creek Bank Stabilization 09/19/2011
W 115 Produce a Reach Assessment in the Middle Reach of Toppenish Creek 03/01/2011
X 40 Install Fence On Camas Patch 05/05/2011
Y 33 Camas Patch Road Relocation 05/05/2011
Z 84 CCR23987 Durham Dam Removal Construction 08/04/2011
AA 30 CCR23987 LaSalle Ahtanum Creek Backwater Channels 09/19/2011
AB 47 CCR23987 LaSalle Ahtanum Creek Floodplain Vegetation 09/19/2011