FY13 SOW and LIB submitted |
B: 119. Manage Restoration Projects |
|
02/28/2013 |
01/30/2013 |
List of Selected Projects (and contingency projects) to be implemented in 2013 |
C: 114. Select habitat improvement actions and identify possible projects for 2013 |
|
09/30/2012 |
09/30/2012 |
Project databases that are maintained and up to date. |
D: 160. Update Project Database |
|
02/28/2013 |
02/28/2013 |
Disseminated data |
E: 161. Create informal summary reports and maps |
|
12/31/2012 |
12/31/2012 |
5 outreach sessions completed |
F: 99. Conduct field and classroom education at local schools |
|
11/30/2012 |
12/31/2012 |
Technical review and input provided to various policy and planning efforts |
G: 122. Input to various Tribal planning and policy efforts |
|
02/28/2013 |
02/28/2013 |
Completed environmental documentation |
H: 165. Environmental Compliance |
|
11/08/2012 |
11/07/2012 |
Completed 2011 Annual Report submitted to BPA |
I: 132. Produce Project Annual Report for FY 11 (3/1/2011 - 2/28/2012) |
|
02/01/2013 |
02/28/2013 |
2 rotary screw traps deployed and recovered |
J: 70. Deploy and Recover 5ft Rotary Screw Traps |
|
10/31/2012 |
10/31/2012 |
Outmigration estimate and other data from screw traps |
K: 157. Operate rotary screw traps |
|
02/28/2013 |
02/28/2013 |
Complete three pass surveys in Satus and Ahtanum Creeks |
L: 157. Conduct spawner surveys |
|
06/15/2012 |
05/31/2012 |
15 miles of completed snorkel surveys |
M: 157. Conduct snorkel surveys |
|
10/31/2012 |
09/30/2012 |
Complete 1500 meters of surveys |
N: 157. Conduct habitat surveys |
|
10/31/2012 |
09/30/2012 |
Water temperature record |
O: 157. Collect water temperature data |
|
01/31/2013 |
12/31/2012 |
Weekly manual discharge measurements |
P: 157. Collect discharge measurements |
|
02/28/2013 |
02/28/2013 |
Electrofishing surveys |
Q: 157. Conduct electrofishing surveys |
|
10/31/2012 |
09/30/2012 |
Monitor water level in monitoring wells |
R: 157. Collect data from monitoring wells |
|
02/28/2013 |
02/28/2013 |
Wapato Irrigation Project diversions managed for minimum instream flow. |
S: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek |
|
02/28/2013 |
02/28/2013 |
water diversion managed at Olney lateral to provide minimum streamflow |
T: 186. Assist with operation of Olney Lateral |
|
02/28/2013 |
02/28/2013 |
Functioning fences, wells, stock tanks, and habitat improvements |
U: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs |
|
02/28/2013 |
02/28/2013 |
Install Barb Wire Fence |
W: 40. Install Barb Wire Fence on Camas Patch Meadow |
|
07/01/2012 |
06/30/2012 |
Install Buck & Pole Fence |
X: 40. Install Buck & Pole Fence at Camas Patch Meadow |
|
09/30/2012 |
09/30/2012 |
Remove Diversion |
Y: 84. Durham Dam Removal Construction |
|
09/30/2012 |
08/30/2012 |
Install Fish Screen |
Z: 69. CCR27642 CHANGES - SF Simcoe Creek Feeder Ditch Fish Screen |
|
12/31/2012 |
10/08/2012 |
Remove Culvert |
AA: 85. CCR27642 CHANGES - NF Simcoe Creek Culvert Removal |
|
09/30/2012 |
07/09/2012 |
Produce/Design engineering plans |
AD: 175. CCR27642 CHANGES - Simcoe Creek Bank Stabilization Project |
|
02/28/2013 |
02/28/2013 |
outmigration estimates and timing information |
AE: 162. Analyze smolt outmigration data |
|
02/28/2013 |
02/28/2013 |
index of spawner abundance and spawning distribution |
AF: 162. Analyze spawner survey data |
|
02/28/2013 |
02/28/2013 |
Water temperature record and descriptive statistics |
AG: 162. Analyze water temperature data |
|
02/28/2013 |
02/28/2013 |
Habitat metrics and indicators |
AH: 162. Analyze habitat survey data |
|
02/28/2013 |
02/28/2013 |
Spatial Fish Density |
AI: 162. Analyze snorkel survey data |
|
12/01/2012 |
12/01/2012 |
Camas Patch Meadow Assessment |
AJ: 174. CCR27642 NEW - Camas Patch Meadow Assessment |
|
02/28/2013 |
02/28/2013 |
technical review recommendations provided |
AK: 122. CCR27642 NEW - Project engineering support |
|
02/28/2013 |
02/28/2013 |