projects managed |
B: 119. Manage Restoration Projects |
|
01/31/2012 |
01/31/2012 |
List of Selected Projects (and contingency projects) to be implemented in 2011 |
C: 114. Select habitat improvement actions for 2011 and identify possible projects for 2012 |
|
02/29/2012 |
12/29/2011 |
Project databases that are maintained and up to date. |
D: 160. Update Project Database |
|
02/29/2012 |
02/29/2012 |
Disseminated data |
E: 161. Create informal summary reports and maps |
|
02/29/2012 |
02/29/2012 |
5 outreach sessions completed |
F: 99. Conduct field and classroom education at local schools |
|
02/29/2012 |
06/06/2011 |
Technical review and input provided to various policy and planning efforts |
G: 122. Input to various Tribal planning and policy efforts |
|
02/29/2012 |
04/29/2011 |
Completed environmental documentation |
H: 165. Environmental Compliance |
|
02/29/2012 |
02/29/2012 |
Completed FY 10 Annual Report submitted to BPA |
I: 132. Produce Project Annual Report for FY 10 (3/1/2010 - 2/28/2011) |
|
02/29/2012 |
02/29/2012 |
2 rotary screw traps deployed and recovered |
J: 70. Deploy and Recover 5ft Rotary Screw Traps |
|
02/29/2012 |
02/29/2012 |
15 miles of completed snorkel surveys |
K: 157. Snorkel Surveys |
|
10/31/2011 |
09/30/2011 |
Wapato Irrigation Project diversions managed for minimum instream flow. |
L: 186. Manage Operation of Upper and Lower WIP canals on Ahtanum Creek |
|
09/30/2011 |
09/30/2011 |
water diversion managed at Olney lateral to provide minimum streamflow |
M: 186. Assist with operation of Olney Lateral |
|
02/29/2012 |
02/29/2012 |
Functioning fences, wells, stock tanks, and habitat improvements |
N: 186. Maintain livestock wells/stock tanks/livestock fences/improved springs |
|
02/29/2012 |
02/29/2012 |
Data collected and ready to be entered into the Project's databases. |
O: 157. Collect Field Data |
|
02/29/2012 |
02/29/2012 |
complete 1 mile of surveys |
P: 157. Timber, Fish and Wildlife (TFW) surveys |
|
09/30/2011 |
08/30/2011 |
Completed sediment inventories and database |
Q: 157. Conduct Sediment Inventories |
|
02/29/2012 |
02/29/2012 |
2 wells converted to stock wells |
R: 34. Convert existing wells to stock wells |
|
02/29/2012 |
02/29/2012 |
Replace 3 passage barrier culverts with culverts capable of passage |
S: 184. Panther Creek Culvert Replacement Project |
|
10/31/2011 |
10/31/2011 |
An engineered plan and plan for construction |
T: 175. LaSalle Ahtanum Creek project design |
|
07/31/2011 |
05/01/2011 |
Complete engineered design plans for two on Reservation fish screens on Simcoe Creek |
U: 175. Design 2 on-Reservation Fish Screens on Simcoe Creek |
|
02/29/2012 |
02/29/2012 |
Stabilize LaSalle Ahtanum Creek Bank |
V: 29. LaSalle Ahtanum Creek Bank Stabilization |
|
09/30/2011 |
09/30/2011 |
One Completed Reach Assessment. |
W: 115. Produce a Reach Assessment in the Middle Reach of Toppenish Creek |
|
02/29/2012 |
02/29/2012 |
Install buck and pole fence on Camas Patch Road Closure |
X: 40. Install Fence On Camas Patch |
|
07/29/2011 |
06/29/2011 |
Camas Patch Road Relocation |
Y: 33. Camas Patch Road Relocation |
|
09/30/2011 |
07/30/2011 |
Two backwater channels and a swale |
AA: 30. CCR23987 LaSalle Ahtanum Creek Backwater Channels |
|
09/30/2011 |
09/30/2011 |
Floodplain Revegetation |
AB: 47. CCR23987 LaSalle Ahtanum Creek Floodplain Vegetation |
|
10/28/2011 |
11/30/2011 |