Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 53350: 2003-017-00 EXP ISEMP BIOMARK PART II SALMON R PIT TAG INSTALL
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
53350
Contract Title:
2003-017-00 EXP ISEMP BIOMARK PART II SALMON R PIT TAG INSTALL
Contract Continuation:
Previous: Next:
48304: 2003-017-00 EXP ISEMP BIO MARK SALMON R PIT TAG INSTALL
Contract Status:
Closed
Contract Description:
CCR 29147 is a no cost contract modification required due to delays in acquiring access/right of way  permit from the BLM, and appropriate scenic and wildlife river permit(s) from the state for the Wallowa River array, WE I.   This is only a change is schedule.   Installation may occur as early as February 2013 if permits can be secured.  If permits cannot be secured prior to this date, then in-water installation of the array will have to wait until river flows drop in early August with planned installation completed by the end of August, or early September.  The proposed new end date for this CCR is September 20, 3013, ensuring adequate time to test and accept the array by the end of the contract..  

CCR 28667 is a no cost contract modification for the purpose of clarifying the actions described in CCR 26276. Briefly, CCR 26276 identified a site in the upper Grande Ronde River and a site in the Wallowa River for placement of a single-span PIT tag array (one at each site). These two upstream sites were selected to replace the tandem PIT tag array originally proposed for the lower Grande Ronde River. CCR 28667 clarifies the prior CCR by breaking Work Element F into two Work Elements; one describing the PIT tag array installation in the upper Grande Ronde (Work Element F), and Work Element I describing the installation of a PIT tag array in the Wallowa River. Additionally, language is included to document the obsolescence of Work Element H; which originally proposed installation of a tandem PIT tag array in the Lower Grande Ronde River.

CCR 26276 is a no cost contract modification that includes the following elements:
1. Inclusion of a new Work Element (H) that identifies alternative PIT tag array locations in the upper Grande Ronde River and Wallowa River. Briefly, the originally proposed PIT tag array sites on the lower mainstem Grande Ronde River described in Work Element F may ultimately prove infeasible with existing PIT tag array technology. The FCRPS BiOp workgroup is considering the tradeoffs between the sites described in Work Elements H and F. Once a final set of locations has been selected by the workgroup, either Work Element H or F will be deleted.
2. The original contract included errors in two stream names that have been fixed.
3. The contract end date has been extended from 5/25/2012 to 01/31/2013 in order to facilitate permitting and enable additional opportunities for installation of PIT tag arrays in the Grande Ronde and upper Salmon River.

Notes Accompanying CR-199943:

Under the fast track proposal process, Biomark was identified to conduct site selection, design, construction, and installation activities for eight new passive integrated transponder (PIT) tag arrays. This work has been divided into two performance periods; the initial contract issued in June 2010 in the amount of $1,070,964.00 and a second performance period in the amount of $806,930.00 that was initially planned to be awarded in September of 2011. Biomark has completed the work associated with the initial performance period ahead of schedule. This Contract (CR-199943) is to enable Biomark to continue tasks needed under the project utilizing FY 2011 funds. C-199943 enables Biomark to continue to meet the originally proposed project deliverables ahead of schedule.


Background:
Since its inception in FY2003, Project #2003-017-00 (the Integrated Status and Effectiveness Monitoring Program; ISEMP) has been developing two novel monitoring and evaluation programs: (i) subbasin-scale pilot status and trend monitoring efforts for anadromous salmonids and their habitat in the Wenatchee/Entiat, John Day and South Fork Salmon River basins, and (ii) effectiveness monitoring for suites of habitat restoration projects in selected watersheds within the three target subbasins. This work - critical for implementing the 2000 NMFS FCRPS Biological Opinion (RPA Actions 180, 181, and 183) (BiOp) and UPAs from the 2004 BiOp - builds on current status and trend monitoring programs within each of these basins. Several regional and local organizations are funding and implementing these programs. In short, this project has integrated existing and new monitoring and evaluation activities in three pilot subbasins to help ensure that provisions of the BiOp are satisfied. This contract is one of several contracts that will implement this project. The final report for this contract will contain data that will 1) be submitted to NOAA Fisheries (also a contractor under this project) for use in a project level integrated Annual Report and 2) be submitted to BPA as a contract final report according to the terms of this contract.  

The Salmon portion of the ISEMP project began in 2005 with the completion of a study design (http://www.nwfsc.noaa.gov/research/divisions/cbd/mathbio/isemp/docs_salmon.cfm#2005), which received a positive review by the Independent Scientific Review Panel in 2006 (ISRP 2006-1; http://www.nwfsc.noaa.gov/research/divisions/cbd/mathbio/isemp/docs_salmon.cfm#2005). Implementation of the ISEMP project in the Salmon subbasin was funded in FY2008, and commenced on-the-ground actions in FY2009. This contract funds Biomark to construct and install extended length instream PIT tag array systems in the lower Imnaha River, Joseph Creek, lower Grande Ronde River, and mainstem upper Salmon River.  These arrays include construction and installation of arrays identified under the FAST TRACK RM&E review process based on decisions by ISEMP's overall project manager Chris Jordan in coordination with Chris Beasley, ISEMP's Salmon River  project manager.

[Note:  Jody White and Chris Beasley will serve in their respective roles (see contact) and are fully funded under contract 45428.]
Account Type(s):
Expense
Contract Start Date:
05/26/2011
Contract End Date:
09/20/2013
Current Contract Value:
$806,930
Expenditures:
$806,930

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Steve Anglea Biomark, LLC. Yes Technical Contact steve.anglea@biomark.com (208) 275-0011x6766
Christopher Beasley Quantitative Consultants Inc Yes Supervisor chris@qcinc.org (360) 620-2883
Brian Beckley Biomark, LLC. Yes Contract Manager brian.beckley@biomark.com (208) 275-0011
David Byrnes Bonneville Power Administration Yes COR dmbyrnes@bpa.gov (503) 230-3171
Rossana Callejas Bonneville Power Administration No Interested Party rxcallejas@bpa.gov (503) 230-7558
Israel Duran Bonneville Power Administration Yes Env. Compliance Lead induran@bpa.gov (503) 230-3967
Audrey Hopkins Biomark, LLC. Yes Technical Contact audrey.hopkins@biomark.com (208) 955-6763
Chris Jordan National Oceanic and Atmospheric Administration Yes Interested Party chris.jordan@noaa.gov (541) 754-4629
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Pamela Nelle Terraqua, Inc. Yes Interested Party pamela@terraqua.biz (509) 885-8143
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605
Jody White Quantitative Consultants Inc Yes Technical Contact jody@qcinc.org (208) 860-5269


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Document and report environmental compliance findings. A: 165. Provide documentation to BPA Environmental Compliance lead. 12/30/2011 12/30/2011
Funding Package - Submit draft to COTR C: 119. Submit funding package to COTR. 09/30/2011 09/30/2011
Install tandem PIT tag array South Fork Clearwater River. D: 70. Install tandem PIT tag array South Fork Clearwater River 05/01/2012 09/30/2011
Install tandem PIT tag array Upper Salmon River E: 70. Install tandem PIT tag array Upper Salmon River 01/31/2013 09/28/2012
Install tandem PIT tag array Upper Grande Ronde River. F: 70. Install tandem PIT tag array Upper Grande Ronde River 01/31/2013 10/30/2012
Attach Progress Report in Pisces G: 132. Submit Progress Report for the period (Sep 2010) to (Sep 2011) 01/31/2013 01/07/2013
Install tandem PIT tag array in Lower Grande Ronde River H: 70. Install tandem PIT tag array in Lower Grande Ronde River 01/31/2013 08/20/2013
Install single span PIT tag array in the Wallowa River I: 70. Install single span PIT tag array in the Wallowa River 09/17/2013 08/20/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened)
  • 1 instance of WE 70 Install Fish Monitoring Equipment
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 5 instances of WE 70 Install Fish Monitoring Equipment

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Provide documentation to BPA Environmental Compliance lead. 06/01/2011
B 185 Periodic Status Reports for BPA 06/01/2011
C 119 Submit funding package to COTR. 06/01/2011
D 70 Install tandem PIT tag array South Fork Clearwater River 07/08/2011
E 70 Install tandem PIT tag array Upper Salmon River 07/08/2011
F 70 Install tandem PIT tag array Upper Grande Ronde River 07/08/2011
G 132 Submit Progress Report for the period (Sep 2010) to (Sep 2011) 06/01/2011
H 70 Install tandem PIT tag array in Lower Grande Ronde River 05/26/2011
I 70 Install single span PIT tag array in the Wallowa River 07/15/2013