Contract 56662 REL 179: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCEMENT
Project Number:
Title:
Yakama Southern Territories Habitat Project (STHP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Klickitat 100.00%
Contract Number:
56662 REL 179
Contract Title:
1997-056-00 EXP KLICKITAT WATERSHED ENHANCEMENT
Contract Continuation:
Previous: Next:
56662 REL 154: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCEMENT
Contract Status:
Closed
Contract Description:
INTRODUCTION

The Klickitat Watershed Enhancement Project (KWEP) works to restore, enhance, and protect watershed function within the Klickitat subbasin.  Project work emphasizes restoration and protection in watersheds and reaches that support native salmonid stocks, particularly steelhead (Oncorhynchus mykiss; listed as "Threatened" within the Mid-Columbia Evolutionarily Significant Unit), spring Chinook (O. tshawytscha) salmon, and bull trout (Salvelinus confluentus; Endangered Species Act "Threatened").  Restoration activities focus on restoring stream processes by removing or mitigating watershed perturbance, improving habitat conditions, and water quality.  Watershed and habitat improvements also benefit fall Chinook (O. tshawytscha), coho (O. kisutch) salmon, resident rainbow trout, and cutthroat trout (O. clarki) and enhance habitat for terrestrial and amphibian wildlife species.  Protection activities compliment restoration efforts within the subbasin by securing refugia and preventing degradation.  90% of the off-reservation project area is in private ownership thus cooperation with state, federal, tribal, and private entities is essential.  KWEP addresses goals and objectives presented in the Klickitat Subbasin Plan, Klickitat Lead Entity Strategic Plan, and the Northwest Power Planning Council's Fish and Wildlife Program.  

PROJECT GOALS

The overall goal of KWEP is to restore watershed health to aid recovery of salmonid stocks in the Klickitat subbasin.  There are three sub-goals:

•  Assess watershed and habitat conditions to prioritize sites for restoration activities.  This involves data collection, compilation, and review of existing as well as historic habitat and watershed conditions.  Identification and filling of data gaps is also a component of KWEP.
•  Protect, restore, and enhance priority watersheds and reaches to increase riparian, wetland, and stream habitat quality.  In-situ and watershed-scale restoration activities mitigate or resolve conflicting historic, present, and/or future land-uses.  Protect areas of existing high-quality habitat condition and prevent further deterioration of degraded habitats.  Restore areas of degraded stream channel and/or habitat condition.
•  Monitor watershed conditions to assess trends and effectiveness of restoration activities.  Monitoring is a critical component to evaluating project success and guiding adaptive practices.  Site-specific and basin-wide spatial scales are addressed.  KWEP augments the Klickitat Monitoring & Evaluation Project (BPA project #1995-06-335)  by assisting data collection and providing Quality Assurance /Quality Control (QA/QC) and analysis of channel morphology, streamflow, temperature, habitat, and channel substrate data.
Account Type(s):
Expense
Contract Start Date:
04/01/2019
Contract End Date:
03/31/2020
Current Contract Value:
$576,028
Expenditures:
$576,028

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Jamie Cleveland Bonneville Power Administration Yes COR jacleveland@bpa.gov (503) 230-3160
Desmond Gelman Bonneville Power Administration No CO Assistant dxgelman@bpa.gov (503) 230-4960
Adrianne Grimm Yakama Confederated Tribes No Interested Party gria@yakamafish-nsn.gov (509) 281-1935
Deanna Lamebull Yakama Confederated Tribes No Administrative Contact Deanna_Lamebull@Yakama.com (509) 865-5121x6348
David Lindley Yakama Confederated Tribes Yes Contract Manager dlindley@ykfp.org (509) 369-3565
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Claire McClory Bonneville Power Administration Yes Env. Compliance Lead cdmcclory@bpa.gov (503) 230-5922
Bill Sharp Yakama Confederated Tribes Yes Supervisor Bill_Sharp@yakama.com (509) 865-5121x6355
Adrienne Wilson Yakama Confederated Tribes Yes Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Prepare Necessary Documentation for Various Environmental Compliance Needs A: 165. Prepare Necessary Documentation for Various Environmental Compliance Needs 03/31/2020 03/26/2020
Promote the establishment/expansion of wetland/riparian vegetation, provide high flow refugia and increase habitat quality of O. mykiss. B: 29. White Creek 191 Meadows Enhancement - Instream Habitat and Inset Floodplain 12/15/2019 10/31/2019
Revegetate roughly 5 acres at White Creek 191 Project Site C: 47. Revegetate White Creek 191 Meadow Site 11/29/2019 11/15/2019
Install Livestock Exclusion Fence - White Creek 191 Meadow D: 40. Install Livestock Exclusion Fence - White Creek 191 Meadow 11/29/2019 10/31/2019
Complete Final Design: Swale Creek - x-ings, side-channel and/or floodplain reconnection E: 175. Finalize Design - Swale Creek x-ings, SC Channel and Floodplain Reconnection 03/31/2020 03/31/2020
Develop or update (out-year) prioritized Habitat Project list: upload to Pisces F: 114. Select, Prioritize, and Begin to Develop Projects for Implementation Over the Next 2-3 Years 03/31/2020 03/26/2020
Revegetate roughly 5 acres at Tepee Creek Phase 3 Project Site G: 47. Supplemental Planting at Tepee Creek Phase 3 Site 11/29/2019 06/14/2019
Manage Native Nursery at Klickitat Field Office H: 47. Manage Native Nursery 03/31/2020 03/26/2020
Invasive Weed Control I: 199. Invasive Plant Control 10/15/2019 08/16/2019
Monitoring of Past Projects J: 157. Habitat Enhancement Project Monitoring 03/31/2020 03/31/2020
Project Monitoring Data Analysis K: 162. Summarize/Analyze Habitat Enhancement Monitoring Data 03/31/2020 03/31/2020
Streamflow Monitoring Data for 9 Sites L: 157. Streamflow Monitoring 03/31/2020 03/31/2020
Streamflow Data Analysis M: 162. Summarize/Analyze Streamflow Monitoring Data 03/31/2020 03/31/2020
Summary of Continuous Stage Information and Coordination of Fisheries Assessment N: 157. Klickitat/Columbia River Confluence Assessment 03/31/2020 03/31/2020
Habitat Assessment O: 157. Habitat Assessment 03/31/2020 03/31/2020
Physical Habitat Data Analysis P: 162. Analyze Physical Habitat Data 03/31/2020 03/31/2020
Attend Technical Meetings Q: 122. Assist Planning Activities - Technical Review 03/31/2020 03/31/2020
Outreach to Professional Societies and Presentation of KWEP Implemented Project R: 99. Project Outreach 03/31/2020 03/31/2020
Completed Annual Report T: 132. Submit Progress Report for the Period 1/1/2019 to 12/31/2019 03/31/2020
Completed Annual Report U: 132. Submit Progress Report for the Period 1/1/2018 to 12/31/2018 05/09/2019 04/01/2019
BPA - Preparation of SOW Package, Submission of Accrual Estimate, and Accurate Invoices V: 119. BPA and SRFB Project Management and Administration 03/31/2020 03/31/2020
YKFP Watershed Coordination W: 191. Coordination of YKFP Restoration 03/31/2020 03/31/2020

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 1 instance of WE 175 Produce Design
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 3 instances of WE 162 Analyze/Interpret Data
Trout, Rainbow (Oncorhynchus mykiss)
  • 1 instance of WE 40 Install Fence

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Prepare Necessary Documentation for Various Environmental Compliance Needs 04/01/2019
B 29 White Creek 191 Meadows Enhancement - Instream Habitat and Inset Floodplain 08/28/2019
C 47 Revegetate White Creek 191 Meadow Site 08/28/2019
D 40 Install Livestock Exclusion Fence - White Creek 191 Meadow 08/28/2019
E 175 Finalize Design - Swale Creek x-ings, SC Channel and Floodplain Reconnection
F 114 Select, Prioritize, and Begin to Develop Projects for Implementation Over the Next 2-3 Years 04/01/2019
G 47 Supplemental Planting at Tepee Creek Phase 3 Site 04/01/2019
H 47 Manage Native Nursery 04/01/2019
I 199 Invasive Plant Control 04/01/2019
J 157 Habitat Enhancement Project Monitoring
K 162 Summarize/Analyze Habitat Enhancement Monitoring Data 04/01/2019
L 157 Streamflow Monitoring
M 162 Summarize/Analyze Streamflow Monitoring Data 04/01/2019
N 157 Klickitat/Columbia River Confluence Assessment 04/01/2019
O 157 Habitat Assessment 04/01/2019
P 162 Analyze Physical Habitat Data 04/01/2019
Q 122 Assist Planning Activities - Technical Review 04/01/2019
R 99 Project Outreach 04/01/2019
S 185 Periodic Status Reports for BPA 04/01/2019
T 132 Submit Progress Report for the Period 1/1/2019 to 12/31/2019 04/01/2019
U 132 Submit Progress Report for the Period 1/1/2018 to 12/31/2018 04/01/2019
V 119 BPA and SRFB Project Management and Administration 04/01/2019
W 191 Coordination of YKFP Restoration