Maintain and improvement existing/used hatchery O&M infrastructure |
A: 61. O&M for maintenance of facilities |
|
01/31/2024 |
|
Eyed egg incubation & transportation for MCCRP program |
B: 66. Transport BY23 Coho eyed-eggs from incubation facilities to rearing facilities |
|
01/31/2024 |
|
Coho broodstock collections-Methow and Wenatchee programs |
C: 66. Trap 2023 Coho broodstock at Dryden, Tumwater, Wells Dam (east and west ladders), Methow FH, Winthrop NFH, and Leavenworth NFH (backup site only) |
|
12/15/2023 |
12/11/2023 |
Trinity Pilot Project and preparation for contracting/construction |
D: 115. Trinity Site Development for spring Chinook & coho |
|
06/01/2023 |
06/08/2023 |
Effective implementation management and timely contract administration |
E: 119. Manage and Administer 2023-2024 Project for Mid Columbia Coho Restoration & Upper Columbia Spring Chinook and Steelhead known as Upper Columbia Production Projects |
|
01/31/2024 |
|
Completed Annual Report |
F: 132. Finalize annual reporting of the CY22 period (2/1/22 through 1/31/23) |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
G: 157. Analyze genetic tissue samples for PBT analysis of parental groups |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
H: 157. Collect/Generate Field and Lab Data to determine 2023 emergence timing, growth and distribution |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
I: 157. Extract CWT from 2023 brood coho snouts collected at spawning and on spawning ground surveys |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
J: 157. Collect biological data from 2023 coho brood at spawning |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
K: 157. Conduct spawning ground surveys for the 2023 return year in the Methow Basin |
|
01/31/2024 |
|
Produce accessible, error-checked datasets |
L: 157. Conduct spawning ground surveys for the 2023 return year in the Wenatchee Basin |
|
01/31/2024 |
|
Goat Wall release study PIT tagged fish |
M: 158. PIT tag up to 12,000 BY22 Spring Chinook in the Methow basin for 2023 releases |
|
11/30/2023 |
11/15/2023 |
Methow and Wenatchee acclimated PIT tagged juveniles |
N: 158. Mark/Tag Animals - PIT-tag up to 80,000 BY22 coho pre-smolts |
|
01/31/2024 |
|
CWT & PBT marking of MCCRP |
O: 158. Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,700,000 BY22 coho pre-smolts |
|
11/30/2023 |
12/18/2023 |
Coho database management for MCCRP |
P: 160. Enter data into and maintain local databases |
|
01/31/2024 |
|
Deliverable: An accessible, error-checked data set with metadata |
Q: 162. Analyze and interpret M&E data from 2023 |
|
01/31/2024 |
|
Produce Environmental Compliance documents |
R: 165. Revise/Update Environmental Compliance Documentation for all applicable work on Coho Reintroduction and UCSCSA final site list compliance for acclimation |
|
01/31/2024 |
|
Produce Hatchery Ops Plan |
S: 174. Hatchery Operations and Facility Plans |
|
01/31/2024 |
|
Produce/Update Plan |
T: 174. Update Upper Columbia Spring Chinook & Steelhead Acclimation (UCSCSA) Plan as sites become identified as part of the implementation schedule |
|
01/31/2024 |
|
Coho spawning at Winthrop NFH |
U: 176. Spawn 2023 brood coho at Winthrop NFH |
|
12/30/2023 |
12/28/2023 |
Wenatchee program spawning @ LNFH |
V: 176. Spawn 2023 brood coho at Leavenworth NFH |
|
12/25/2023 |
12/21/2023 |
Spring Chinook acclimation at Goat Wall |
W: 176. Acclimate BY21 Spring Chinook at Goat Wall Pond |
|
05/30/2023 |
05/30/2023 |
Coho acclimation at Twisp Weir pond |
X: 176. Acclimation/Release Coho BY2021: Methow: Twisp Weir |
|
05/01/2023 |
05/01/2023 |
Coho acclimation at Chewuch AP |
Y: 176. Acclimation/Release Coho BY2021: Methow: Chewuch Acclimation Facility |
|
05/05/2023 |
05/05/2023 |
Coho acclimation at Mid Valley Pond |
Z: 176. Acclimation/Release Coho BY2021: Methow: Mid Valley Ponds |
|
06/01/2023 |
06/01/2023 |
Coho acclimation at Early Winters Ponds |
AA: 176. Acclimation/Release Coho BY2021: Methow: Early Winters |
|
06/01/2023 |
06/01/2023 |
Coho acclimation at Lower Twisp Ponds |
AB: 176. Acclimation/Release Coho BY2021: Methow: Lower Twisp Ponds |
|
05/15/2023 |
05/15/2023 |
Coho acclimation at Eightmile Ranch Pond |
AC: 176. Acclimation/Release Coho BY2021: Methow: Eightmile Ranch |
|
06/15/2023 |
06/15/2023 |
Coho acclimation at Leavenworth NFH |
AD: 176. Release Coho BY2021: Wenatchee: Leavenworth NFH |
|
04/25/2023 |
04/25/2023 |
Coulter Pond acclimated coho releases-Wenatchee River Basin |
AE: 176. Acclimation/Release Coho BY2021: Wenatchee: Coulter pond |
|
06/30/2023 |
06/30/2023 |
Butcher Creek acclimation of coho smolts |
AF: 176. Acclimation/Release Coho BY2021: Wenatchee: Butcher pond |
|
06/30/2023 |
06/30/2023 |
Acclimate and volitional release coho at Rohlfing's Pond |
AG: 176. Acclimation/Release Coho BY2021: Wenatchee: Rohlfing's pond |
|
06/30/2023 |
06/30/2023 |
Acclimate/volitional release of Beaver Creek Acclimation Pond-Wenatchee River Basin |
AH: 176. Acclimation/Release Coho BY2021: Wenatchee: Beaver Creek pond |
|
06/30/2023 |
06/30/2023 |
Watershed Coordination on project implementation |
AJ: 191. Coordination of Plan with Regional Stakeholders |
|
01/31/2024 |
|