Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 302: 1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
Project Number:
Title:
Upper Columbia Production
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Methow 40.00%
Wenatchee 60.00%
Contract Number:
56662 REL 302
Contract Title:
1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
Contract Continuation:
Previous: Next:
56662 REL 274: 1996-040-00 EXP UC COHO O&M, M&E & UC SCS/STH ACCLIMATION
  • CR-374041: 1996-040-00 EXP UC COHO O&M, M&E, UC SCS/STH ACCLIMATION
Contract Status:
Issued
Contract Description:
FY24 marks the 4th year of Upper Columbia project mergers into 1996-040-00 (Mid-Columbia Reintroduction Feasibility Study), 2008-458-00 (Steelhead Kelt Reconditioning) and 2009-001-00 (Upper Columbia Spring Chinook and Steelhead Acclimation. This action creates administrative efficiencies within the Yakama Nation FRM, streamlining reporting, assets and funds for similar Basin actions to meet anadromous reintroduction objective goals.

This contract period from Feb. 1, 2024 through Jan. 31, 2025 would continue programmatic objectives for the coho reintroduction program. Duties to include primary O&M activities such as acclimation, adult collections and spawning and early egg incubation in both the Methow and Wenatchee basins will continue. Other actions are included as well (e.g.- carcass out planting, etc.) but are part of these overarching program goals and objectives. The Methow program will enter into its first year of Natural Production Phases (NPP 1) transitioning towards natural production; a decrease by 30% of the production down to 700,000 will be released from targeted tributaries (i.e.-Chewuch R., Twisp R., and Upper Methow R.).  The Wenatchee program continues to work through the Broodstock Development Phase Two (BDPII) of the program and will look to repeat project-specific studies to try and determine if a contingency can be implemented if adults are unable to ascend Tumwater Canyon at the rate required to meet BDPII objectives.

O&M activities to include: fish rearing/acclimation, broodstock collection, spawning, incubation, transportation of eyed eggs to LCR facilities, facility oversight/operations, annual non-technical production reporting (both in WEN and MET but also to include rearing summaries through USFWS subcontracting).  

M&E activities include survival measures and data collection for status and trend analyses of the coho program; both within year and for long-term comparisons. Coho abundance and egg-to-immigrant survival (through the use of smolt traps) for naturally produced juveniles on both Nason Creek as well as the lower Wenatchee River trap (operated by WDFW) allows for us to calculate smolt-to-adult rates for natural origin returns.  Hatchery in-pond acclimation survival as well as out-migrant run timing is critical in determining that volitional releases are the most appropriate means for releases of coho in both Methow and Wenatchee basins.   On the adult returns, escapement methods to be calculated will involve spawning ground surveys to determine spawning timing, distribution and H vs. N origin compositions.

M&E Activities covered under this contract would relate to tagging/marking of juveniles in the form of:
- CWT'ing/Body Tagging/PBT analysis/PIT tagging (the first 3 would provide information in determining SARs and the last one would be for in-pond and Columbia corridor survivals as juveniles)
- Data analysis for adult distribution, run composition, spawning densities and locations, MvsF ratios, run timing, fecundity, etc.  (activities to contribute to this would occur on spawning ground surveys and at spawning).
- Juvenile run timing, out-migration survival and abundance (via the rotary screw trap on Nason Cr. as well as the WDFW operated Cashmere screw tap)
- Program will include Cost-Sharing with Chelan and Grant County PUD  

The Spring Chinook and Steelhead acclimation distribution in the upper Methow where adult management is in place and being implemented to restrict/reduce hatchery influence and more importantly reduce the effects of a single source release location, which YN identified in the UCSCSA original plan. Currently, restrictions to the numbers being released in the upper Methow are due to the uncertainties of whether these decreases in productivity form the egg-to-emigrant life stage is due to super saturation in the reaches near Methow SFH and Winthrop NFH, hatchery contributions that are driving down reproductive success or a combination of both. The 2023 releases will include Chewuch AF and Goat Wall, used for acclimation of spring Chinook.  Steelhead in the Methow are being planned for release either from Early Winters, Mid-Valley-Pond and/or Gold Creek Ponds.  

This merged acclimation project proposes to further develop acclimation for upper Columbia steelhead and spring Chinook by developing new semi-natural ponds similar to what has been uniquely successful in the Mid-Columbia Coho Restoration Project. This would involve utilizing the existing PUD/Federal mitigation production in the region that is currently doing either direct stream plants or single point, large releases and expand/refine those releases by adding additional acclimation releases in known habitat reaches within the Wenatchee and Methow watersheds. This strategy will enhance the goals of recovery for these 2 listed stocks as discussed below.   Steelhead releases planned at the Powerline Pond site on upper Nason Creek is being planned for 2023.  
Account Type(s):
Expense
Contract Start Date:
02/01/2024
Contract End Date:
01/31/2025
Current Contract Value:
$2,517,572
Expenditures:
$1,506,405

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Rick Alford Yakama Confederated Tribes Yes Technical Contact alfr@yakamafish-nsn.gov (509) 996-9857
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
David Blodgett III Yakama Confederated Tribes No Supervisor blod@yakamafish-nsn.gov
Jeffrey Caisman Yakama Confederated Tribes Yes Technical Contact caij@yakamafish-nsn.gov (847) 219-6386
Mary Haight Bonneville Power Administration Yes Backup COR mthaight@bpa.gov (503) 230-3112
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Contract Manager kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Eric McOmie Bonneville Power Administration Yes COR ermcomie@bpa.gov (503) 230-4964
Keely Murdoch Yakama Confederated Tribes Yes Interested Party murk@yakamafish-nsn.gov (509) 548-2206
Jessica Power Bonneville Power Administration No CO Assistant jdpower@bpa.gov (503) 230-4023
Thomas Scribner Yakama Confederated Tribes Yes Supervisor scrt@yakamafish-nsn.gov (503) 331-9850
Shawn Skinner Bonneville Power Administration Yes Env. Compliance Lead srskinner@bpa.gov (503) 230-3727
Shanita Sohappy Yakama Confederated Tribes No Administrative Contact sohsh@yakamafish-nsn.gov (509) 865-5121
Gregory Wolfe Yakama Confederated Tribes Yes Contract Manager wolg@yakamafish-nsn.gov (509) 881-0674
Karen Wolfe Bonneville Power Administration Yes Contracting Officer ktwolfe@bpa.gov (503) 230-3448


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Maintain fish production and rearing facilities B: 61. O&M for maintenance of facilities 01/31/2025
Transport eyed eggs from the Wentachee and Methow basins to lower Columbia River facilities for rearing to pre-smolt stage C: 66. Transport BY24 Coho eyed-eggs from incubation facilities to rearing facilities 01/31/2025
Broodstock adults for the Methow and Wenatchee programs D: 66. Trap 2024 Coho broodstock at Dryden, Tumwater, Wells Dam (east and west ladders), Methow FH, Winthrop NFH, and Leavenworth NFH (backup site only) 12/15/2024
Trinity Pilot Project and preparation for contracting/construction E: 115. Trinity Site Development for spring Chinook & coho 06/01/2024 06/01/2024
Effective implementation management and timely contract administration F: 119. Manage and Administer 2024-2025 Project for Mid Columbia Coho Restoration & Upper Columbia Spring Chinook and Steelhead known as Upper Columbia Production Projects 01/31/2025
Completed Annual Report G: 132. Finalize annual reporting of the CY24 period (2/1/24 through 1/31/25) 01/15/2025
Produce accessible, error-checked datasets H: 157. Analyze genetic tissue samples for PBT analysis of parental groups 01/31/2025 03/01/2024
Produce accessible, error-checked datasets I: 157. Collect/Generate Field and Lab Data to determine 2024 emergence timing, growth and distribution 01/31/2025
Produce accessible, error-checked datasets J: 157. Extract CWT from 2024 brood coho snouts collected at spawning and on spawning ground surveys 01/31/2025
Produce accessible, error-checked datasets K: 157. Collect biological data from 2024 coho brood at spawning 01/31/2025
Produce accessible, error-checked datasets L: 157. Conduct spawning ground surveys for the 2024 return year in the Methow Basin 01/31/2025
Produce accessible, error-checked datasets M: 157. Conduct spawning ground surveys for the 2024 return year in the Wenatchee Basin 01/31/2025
PIT tag 10,000 summer steelhead N: 158. PIT tag up to 10,000 BY23 steelhead parr in the Methow Basin for 2025 releases 11/30/2024
Methow and Wenatchee acclimated PIT tagged juveniles O: 158. Mark/Tag Animals - PIT-tag up to 80,000 BY23 coho pre-smolts 01/31/2025
CWT & PBT marking of MCCRP P: 158. Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,700,000 BY24 coho pre-smolts 11/30/2024
Coho database management for MCCRP Q: 160. Enter data into and maintain local databases 01/31/2025
Deliverable: An accessible, error-checked data set with metadata R: 162. Analyze and interpret M&E data from 2024 01/31/2025
Produce Environmental Compliance documents S: 165. Revise/Update Environmental Compliance Documentation for all applicable work on Coho Reintroduction and UCSCSA final site list compliance for acclimation 01/31/2025
Produce an Annual Hatchery Operation Plan T: 174. Hatchery Operations and Facility Plans 01/31/2025
Produce an Annual Hatchery Operations Plan. U: 174. Update Upper Columbia Spring Chinook & Steelhead Acclimation (UCSCSA) Plan as sites become identified as part of the implementation schedule 01/31/2025
Spawn approximately 750 coho brood adults for 2026 program releases in the Methow Basin V: 176. Spawn 2024 brood coho at Winthrop NFH 12/30/2024
Spawn Coho at Leavenworth National Hatchery W: 176. Spawn 2024 brood coho at Leavenworth NFH 12/25/2024
Coho acclimation at Goat Wall Pond X: 176. Acclimate/Release Coho BY2022: Methow: Goat Wall Pond 05/30/2024 05/29/2024
Coho acclimation at Twisp Weir Pond Y: 176. Acclimation/Release Coho BY2022: Methow: Twisp Weir 05/01/2024 05/01/2024
Coho acclimation at Chewuch AP Z: 176. Acclimation/Release Coho BY2022: Methow: Chewuch Acclimation Facility 05/05/2024 05/01/2024
Coho acclimation at Mid-Valley Pond AA: 176. Acclimation/Release Coho BY2022: Methow: Mid Valley Ponds 06/01/2024 06/01/2024
Coho and steelhead Acclimation at Early Winters Ponds AB: 176. Acclimation/Release Coho and Winthrop NFH steelhead BY2022: Methow: Early Winters 06/01/2024 05/01/2024
Coho acclimation at Lower Twisp Ponds AC: 176. Acclimation/Release Coho BY2022: Methow: Lower Twisp Ponds 05/15/2024 05/15/2024
Coho acclimation at 8-Mile Pond AD: 176. Acclimation/Release Coho BY2022: Methow: Eightmile Ranch 06/15/2024 06/15/2024
Coho Acclimation at Leavenworth National Hatchery AE: 176. Release Coho BY2022: Wenatchee: Leavenworth NFH 04/25/2024 04/25/2024
Acclimate coho at Coulter Pond AF: 176. Acclimation/Release Coho BY2022: Wenatchee: Coulter pond 06/30/2024 06/30/2024
Acclimate coho at Butcher Pond AG: 176. Acclimation/Release Coho BY2022: Wenatchee: Butcher pond 06/30/2024 06/30/2024
Acclimate and release coho from Rohlfing Pond AH: 176. Acclimation/Release Coho BY2022: Wenatchee: Rohlfing's pond 06/30/2024 06/30/2024
Acclimate and release coho from Beaver Pond AI: 176. Acclimation/Release Coho BY2022: Wenatchee: Beaver Creek Pond 06/30/2024 06/30/2024
Acclimate and volitionally release coho at Powerline Pond AJ: 176. Acclimation/Release Coho BY2022: Wenatchee; Powerline Pond 06/30/2024 06/30/2024
Coordinate with regional stakeholders AK: 191. Coordination of Plan with Regional Stakeholders 01/31/2025
Produce an Annual Operations Plan AL: 174. Produce an Annual Operations Plan 01/31/2025

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 174 Produce Plan
Coho (O. kisutch) - Unspecified Population
  • 15 instances of WE 176 Produce Hatchery Fish
  • 2 instances of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 61 Maintain Artificial Production Facility/Infrastructure
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 2 instances of WE 174 Produce Plan
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 2 instances of WE 158 Mark/Tag Animals
  • 1 instance of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 158 Mark/Tag Animals

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA
B 61 O&M for maintenance of facilities 10/25/2023
C 66 Transport BY24 Coho eyed-eggs from incubation facilities to rearing facilities 10/25/2023
D 66 Trap 2024 Coho broodstock at Dryden, Tumwater, Wells Dam (east and west ladders), Methow FH, Winthrop NFH, and Leavenworth NFH (backup site only) 10/25/2023
E 115 Trinity Site Development for spring Chinook & coho 10/25/2023
F 119 Manage and Administer 2024-2025 Project for Mid Columbia Coho Restoration & Upper Columbia Spring Chinook and Steelhead known as Upper Columbia Production Projects
G 132 Finalize annual reporting of the CY24 period (2/1/24 through 1/31/25)
H 157 Analyze genetic tissue samples for PBT analysis of parental groups 10/25/2023
I 157 Collect/Generate Field and Lab Data to determine 2024 emergence timing, growth and distribution 10/25/2023
J 157 Extract CWT from 2024 brood coho snouts collected at spawning and on spawning ground surveys 10/25/2023
K 157 Collect biological data from 2024 coho brood at spawning 10/25/2023
L 157 Conduct spawning ground surveys for the 2024 return year in the Methow Basin 10/25/2023
M 157 Conduct spawning ground surveys for the 2024 return year in the Wenatchee Basin 10/25/2023
N 158 PIT tag up to 10,000 BY23 steelhead parr in the Methow Basin for 2025 releases 10/25/2023
O 158 Mark/Tag Animals - PIT-tag up to 80,000 BY23 coho pre-smolts 10/25/2023
P 158 Mark/Tag Animals - Subcontract CWT and/or PBT of approximately 1,700,000 BY24 coho pre-smolts 10/25/2023
Q 160 Enter data into and maintain local databases
R 162 Analyze and interpret M&E data from 2024
S 165 Revise/Update Environmental Compliance Documentation for all applicable work on Coho Reintroduction and UCSCSA final site list compliance for acclimation
T 174 Hatchery Operations and Facility Plans 10/25/2023
U 174 Update Upper Columbia Spring Chinook & Steelhead Acclimation (UCSCSA) Plan as sites become identified as part of the implementation schedule 10/25/2023
V 176 Spawn 2024 brood coho at Winthrop NFH 10/25/2023
W 176 Spawn 2024 brood coho at Leavenworth NFH 10/25/2023
X 176 Acclimate/Release Coho BY2022: Methow: Goat Wall Pond 10/25/2023
Y 176 Acclimation/Release Coho BY2022: Methow: Twisp Weir 10/25/2023
Z 176 Acclimation/Release Coho BY2022: Methow: Chewuch Acclimation Facility 10/25/2023
AA 176 Acclimation/Release Coho BY2022: Methow: Mid Valley Ponds 10/25/2023
AB 176 Acclimation/Release Coho and Winthrop NFH steelhead BY2022: Methow: Early Winters 10/25/2023
AC 176 Acclimation/Release Coho BY2022: Methow: Lower Twisp Ponds 10/25/2023
AD 176 Acclimation/Release Coho BY2022: Methow: Eightmile Ranch 10/25/2023
AE 176 Release Coho BY2022: Wenatchee: Leavenworth NFH 10/25/2023
AF 176 Acclimation/Release Coho BY2022: Wenatchee: Coulter pond 10/25/2023
AG 176 Acclimation/Release Coho BY2022: Wenatchee: Butcher pond 10/25/2023
AH 176 Acclimation/Release Coho BY2022: Wenatchee: Rohlfing's pond 10/25/2023
AI 176 Acclimation/Release Coho BY2022: Wenatchee: Beaver Creek Pond 10/25/2023
AJ 176 Acclimation/Release Coho BY2022: Wenatchee; Powerline Pond 10/25/2023
AK 191 Coordination of Plan with Regional Stakeholders
AL 174 Produce an Annual Operations Plan 10/25/2023