Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 56662 REL 44: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCE
Project Number:
Title:
Yakama Southern Territories Habitat Project (STHP)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Gorge Klickitat 100.00%
Contract Number:
56662 REL 44
Contract Title:
1997-056-00 EXP KLICKITAT WATERSHED ENHANCE
Contract Continuation:
Previous: Next:
56662 REL 23: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCE
Contract Status:
Closed
Contract Description:
INTRODUCTION

The Klickitat Watershed Enhancement Project (KWEP) works to restore, enhance, and protect watershed function within the Klickitat subbasin. Project work emphasizes restoration and protection in watersheds and reaches that support native salmonid stocks, particularly steelhead (Oncorhynchus mykiss; listed as "Threatened" within the Mid-Columbia Evolutionarily Significant Unit), spring Chinook (O. tshawytscha) salmon, and bull trout (Salvelinus confluentus; Endangered Species Act "Threatened").  Restoration activities are aimed at restoring stream processes by removing or mitigating watershed perturbances and improving habitat conditions and water quality.  Watershed and habitat improvements also benefit fall Chinook (O. tshawytscha) and coho (O. kisutch) salmon, resident rainbow trout, and cutthroat trout (O. clarki) and enhance habitat for many terrestrial and amphibian wildlife species.  Protection activities compliment restoration efforts within the subbasin by securing refugia and preventing degradation.  Since 90% of the off-reservation project area is in private ownership, maximum effectiveness is accomplished via cooperation with state, federal, tribal, and private entities. KWEP addresses goals and objectives presented in the Klickitat Subbasin Plan, Klickitat Lead Entity Strategic Plan, and the 1994 Northwest Power Planing Council's Fish and Wildlife Program.  


PROJECT GOALS

The overall goal of KWEP is to restore watershed health to aid recovery of salmonid stocks in the Klickitat subbasin.  There are three sub-goals:

•  Assess watershed and habitat conditions to prioritize sites for restoration activities.   This involves data collection, compilation, and review of existing as well as historic habitat and watershed conditions.  Identification and filling of data gaps is also a component of KWEP.
•  Protect, restore, and enhance priority watersheds and reaches to increase riparian, wetland, and stream habitat quality.  In-situ and watershed-scale restoration activities mitigate or resolve conflicting historic, present, and/or future land-uses.  Protect areas of existing high-quality habitat condition and prevent further deterioration of degraded habitats.  Restore areas of degraded stream channel and/or habitat condition.
•  Monitor watershed conditions to assess trends and effectiveness of restoration activities.  Monitoring is a critical component to evaluating project success and guiding adaptive practices.  Site-specific and basin-wide spatial scales are addressed.  KWEP augments the Klickitat Monitoring & Evaluation Project (BPA project #1995-06-335)  by assisting data collection and providing Quality Assurance /Quality Control (QA/QC) and analysis of channel morphology, streamflow, temperature, habitat, and channel substrate data.


RELATED PROJECTS

Habitat Assessment and Monitoring - Augment monitoring and assessment of physical watershed characteristics in the Klickitat subbasin.  Supplement data and analysis of the Klickitat M&E project by assisting with collection, QA/QC, and analysis.  Conduct effectiveness monitoring at past KWEP-related project sites.  
Assist data collection and management of channel morphology, streamflow, temperature, habitat, and channel substrate data.
Account Type(s):
Expense
Contract Start Date:
04/01/2014
Contract End Date:
03/31/2015
Current Contract Value:
$571,009
Expenditures:
$571,009

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

BPA CO:
BPA COR:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Will Conley Yakama Confederated Tribes Yes Supervisor will@ykfp.org (509) 369-3183
Mary Haight Bonneville Power Administration Yes COR mthaight@bpa.gov (503) 230-3112
Deanna Lamebull Yakama Confederated Tribes No Administrative Contact Deanna_Lamebull@Yakama.com (509) 865-5121x6348
David Lindley Yakama Confederated Tribes Yes Contract Manager dlindley@ykfp.org (509) 369-3565
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Jennifer Lord Bonneville Power Administration No Env. Compliance Lead jklord@bpa.gov (503) 230-5192
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Bill Sharp Yakama Confederated Tribes Yes Supervisor Bill_Sharp@yakama.com (509) 865-5121x6355
Adrienne Wilson Yakama Confederated Tribes Yes Administrative Contact Adrienne_Wilson@Yakama.com (509) 865-5121x6306


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Prepare necessary documentation for various environmental compliance needs B: 165. Prepare necessary documentation for various environmental compliance needs 03/31/2015 03/31/2015
Design and Specifications for Klickitat River Floodplain Project (Haul Road) Haul Phase 5 C: 175. Design and Specifications for Klickitat River Floodplain Project (Haul Road) Phase 5 07/31/2014 07/15/2014
Construction Management Haul Road Phase 5 D: 100. Construction Oversight for Klickitat River Floodplain Project (Haul Road) - Phase 5 11/30/2014 11/07/2014
Specifications and Bid Documents for Upper Klickitat (Phase 4) E: 175. Specifications for Upper Klickitat Project (Phase 4) 08/15/2014 08/14/2014
Construction Management Upper Klickitat Project (Phase 4) F: 100. Construction Oversight for Upper Klickitat Project (Phase 4) 11/28/2014 11/20/2014
Placement of LWD in mainstem Klickitat River G: 29. Upper Klickitat Phase 4 - LWD Additions to convert plan-bed to pool-riffle morphology 11/28/2014 11/20/2014
Install Livestock Exclusion Fence - Tepee Creek Phase 2 H: 40. Install Livestock Exclusion Fence - Tepee Creek Phase 2 07/31/2014 06/18/2014
Produce 30% design and specifications for Tepee Creek Phase 3 I: 175. Design and specifications for Tepee Creek Phase 3 03/31/2015 03/31/2015
Manage Native Nursery at Klickitat Field Office J: 47. Manage Native Nursery 03/31/2015 03/31/2015
Revegetate 2.0+ acres K: 47. Revegetate Klickitat River Floodplain Restoration (Haul Road) Phase 5 project site 03/31/2015 03/31/2015
Revegetate 1 acres L: 47. Revegetate Upper Klickitat River Phase 4 site 12/15/2014 11/20/2014
Invasive Weed Control M: 199. Invasive Plant Control 10/31/2014 10/31/2014
Monitoring of Past Projects N: 157. Habitat Enhancement Project Monitoring 03/31/2015 03/31/2015
Streamflow monitoring data for 9 sites O: 157. Streamflow monitoring 03/31/2015 03/24/2015
Summary of continuous stage information P: 157. Collect water surface elevation data - Klickitat/Columbia River Confluence 03/31/2015 03/31/2015
Final Report - Klickitat River Delta Habitat Assessment Q: 162. Produce Final Report - Klickitat River Delta Habitat Assessment 03/31/2015 03/31/2015
Turbidity, temperature and stage data for Big Muddy Creek and Klickitat River sites R: 157. Measure turbidity timing and duration associated with Big Muddy Creek 03/31/2015 03/31/2015
Habitat Assessment S: 157. Habitat Assessment 03/31/2015 03/31/2015
Conduct Food Web Study on Tepee and White Creeks (Effectiveness Monitoring) T: 157. Conduct Food Web Study on Tepee and White Creeks 02/28/2015 06/13/2014
Physical Habitat Data Analysis U: 162. Summarize monitoring data 03/31/2015 03/31/2015
Attend Technical Meetings V: 122. Assist Planning Activities - Technical Review 03/31/2015 03/31/2015
Disseminate Results of a KWEP implemented restoration project W: 161. Disseminate Klickitat habitat and project information 03/31/2015 03/31/2015
Database Management and Development (multiple databases) X: 160. Database Management and Development 03/31/2015 03/31/2015
Outreach to Professional Societies Y: 99. Project Outreach 03/31/2015 03/31/2015
Conduct one appraisal Z: 172. Acquire and review appraisal for one parcel 03/31/2015 03/31/2015
BPA - preparation of SOW package, submission of accrual estimate, and accurate invoices. AA: 119. BPA and SRFB Project Management and Administration 03/31/2015 03/31/2015
Annual report for 2010-11 attached in Pisces AB: 132. Submit Progress Report for the period 1/1/2010 to 12/31/2011 04/07/2014 04/01/2014
Annual report for 2012 attached in Pisces AC: 132. Submit Annual Report for the period 1/1/2012 to 12/31/2012 02/20/2015 03/30/2015
Attach Progress Report in Pisces AE: 132. Submit Progress Report for the period 1/1/2014 to 12/31/2014 03/15/2015

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 100 Construction Management
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 199 Remove Vegetation
  • 1 instance of WE 29 Increase Aquatic and/or Floodplain Complexity
  • 1 instance of WE 40 Install Fence
  • 3 instances of WE 47 Plant Vegetation
  • 1 instance of WE 172 Conduct Pre-Acquisition Activities
  • 1 instance of WE 122 Provide Technical Review and Recommendation
  • 3 instances of WE 175 Produce Design
  • 6 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data
  • 2 instances of WE 100 Construction Management

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 04/01/2014
B 165 Prepare necessary documentation for various environmental compliance needs 04/01/2014
C 175 Design and Specifications for Klickitat River Floodplain Project (Haul Road) Phase 5 11/14/2013
D 100 Construction Oversight for Klickitat River Floodplain Project (Haul Road) - Phase 5 11/14/2013
E 175 Specifications for Upper Klickitat Project (Phase 4) 11/14/2013
F 100 Construction Oversight for Upper Klickitat Project (Phase 4) 11/15/2013
G 29 Upper Klickitat Phase 4 - LWD Additions to convert plan-bed to pool-riffle morphology 04/01/2014
H 40 Install Livestock Exclusion Fence - Tepee Creek Phase 2 04/01/2014
I 175 Design and specifications for Tepee Creek Phase 3 11/15/2013
J 47 Manage Native Nursery 11/15/2013
K 47 Revegetate Klickitat River Floodplain Restoration (Haul Road) Phase 5 project site 04/01/2014
L 47 Revegetate Upper Klickitat River Phase 4 site 04/01/2014
M 199 Invasive Plant Control 04/01/2014
N 157 Habitat Enhancement Project Monitoring 11/15/2013
O 157 Streamflow monitoring 11/15/2013
P 157 Collect water surface elevation data - Klickitat/Columbia River Confluence 11/15/2013
Q 162 Produce Final Report - Klickitat River Delta Habitat Assessment 04/01/2014
R 157 Measure turbidity timing and duration associated with Big Muddy Creek 11/15/2013
S 157 Habitat Assessment 04/01/2014
T 157 Conduct Food Web Study on Tepee and White Creeks 04/01/2014
U 162 Summarize monitoring data 04/01/2014
V 122 Assist Planning Activities - Technical Review 04/01/2014
W 161 Disseminate Klickitat habitat and project information 04/01/2014
X 160 Database Management and Development 04/01/2014
Y 99 Project Outreach 04/01/2014
Z 172 Acquire and review appraisal for one parcel 04/01/2014
AA 119 BPA and SRFB Project Management and Administration 04/01/2014
AB 132 Submit Progress Report for the period 1/1/2010 to 12/31/2011 04/01/2014
AC 132 Submit Annual Report for the period 1/1/2012 to 12/31/2012 04/01/2014
AD 132 Submit Annual Report for the period 1/1/2013 to 12/31/2013 04/01/2014
AE 132 Submit Progress Report for the period 1/1/2014 to 12/31/2014 04/01/2014