Province | Subbasin | % |
---|---|---|
Columbia Gorge | Klickitat | 100.00% |
Previous: | Next: |
---|---|
52388: 1997-056-00 EXP KLICKITAT WATERSHED ENHANCE |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Will Conley | Yakama Confederated Tribes | Yes | Supervisor | will@ykfp.org | (509) 369-3183 |
Mary Haight | Bonneville Power Administration | Yes | COR | mthaight@bpa.gov | (503) 230-3112 |
Deanna Lamebull | Yakama Confederated Tribes | No | Administrative Contact | Deanna_Lamebull@Yakama.com | (509) 865-5121x6348 |
David Lindley | Yakama Confederated Tribes | Yes | Contract Manager | dlindley@ykfp.org | (509) 369-3565 |
Peter Lofy | Bonneville Power Administration | Yes | F&W Approver | ptlofy@bpa.gov | (503) 230-4193 |
Jennifer Lord | Bonneville Power Administration | No | Env. Compliance Lead | jklord@bpa.gov | (503) 230-5192 |
Khanida Mote | Bonneville Power Administration | Yes | Contracting Officer | kpmote@bpa.gov | (503) 230-4599 |
Bill Sharp | Yakama Confederated Tribes | Yes | Supervisor | Bill_Sharp@yakama.com | (509) 865-5121x6355 |
Adrienne Wilson | Yakama Confederated Tribes | Yes | Administrative Contact | Adrienne_Wilson@Yakama.com | (509) 865-5121x6306 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Prepare necessary documentation for various environmental compliance needs | B: 165. Prepare necessary documentation for various environmental compliance needs | 09/30/2013 | 07/03/2013 | |
Design and Specifications for Klickitat River Floodplain Project (Haul Road) Haul Phase 4 | C: 175. Design and Specifications for Klickitat River Floodplain Project (Haul Road) Phase 4 | 08/31/2013 | 08/31/2013 | |
Construction oversight and EC for the Klickitat River Floodplain Project (Haul Road) Phase 4 | D: 100. Contruction Oversight for Klickitat River Floodplain Project (Haul Road) - Phase 4 | 11/15/2013 | 12/09/2013 | |
Construction Oversight for Upper Klickitat (Phase 3) | E: 100. Construction Oversight for Upper Klickitat Phase 3 | 09/30/2013 | 07/09/2013 | |
Upper Klickitat Phase 3 - Side channel reconnection | F: 30. Upper Klickitat Phase 3 - side channel reconnection | 09/30/2013 | 07/09/2013 | |
Construction oversight for Tepee Creek Meadows - Phase 2 | G: 100. Construction Oversight for Tepee Creek Meadows Project - Phase 2 | 11/15/2013 | 11/04/2013 | |
Reconnection of historic channel, reconfiguration of existing channel, and log jam construction | H: 29. Tepee Creek Meadow Project (Phase 2) - Floodplain Reconnection | 11/15/2013 | 11/06/2013 | |
Design and Specifications for Upper Klickitat (Phase 4) | I: 175. Design and Specifications for Upper Klickitat Project (Phase 4) | 12/15/2013 | 12/15/2013 | |
Construction oversight for Upper Klickitat (Phase 4) | J: 100. Construction Oversight for Upper Klickitat Project (Phase 4) | 03/31/2014 | ||
Manage Native Nursery | K: 47. Manage Native Nursery | 03/31/2014 | 12/09/2013 | |
Revegetate 4.0 acres | L: 47. Revegetate Klickitat River Floodplain Restoration (Haul Road) Phase 4 project site | 03/31/2014 | 03/28/2014 | |
Revegetate 15 acres | M: 47. Revegetate Tepee Creek Phase 2 project site | 11/15/2013 | 11/05/2013 | |
Revegetate 7 acres | N: 47. Revegetate Upper Klickitat River Phase 3 and 4 sites | 03/31/2014 | 03/28/2014 | |
Invasive Weed Control | O: 197. Invasive plant control | 08/31/2013 | 09/19/2013 | |
Effectiveness monitoring data | P: 157. Habitat Enhancement Project Monitoring | 12/01/2013 | 11/05/2013 | |
Streamflow monitoring data for 5 sites | Q: 157. Streamflow monitoring | 03/31/2014 | 03/28/2014 | |
Summary of continuous stage information | R: 157. Collect water surface elevation data - Klickitat/Columbia River Confluence | 03/31/2014 | 03/28/2014 | |
Turbidity, temperature and stage data for Big Muddy Creek and Klickitat River sites | S: 157. Measure turbidity timing and duration associated with Big Muddy Creek | 03/31/2014 | 03/28/2014 | |
Habitat Assessment | T: 157. Habitat Assessment | 03/31/2014 | 03/28/2014 | |
Conduct Food Web Study on Tepee and White Creeks (Effectiveness Monitoring) | U: 162. Conduct Food Web Study on Tepee and White Creeks (Effectiveness Monitoring) | 03/31/2014 | 03/28/2014 | |
Physical Habitat Data Analysis | V: 162. Summarize monitoring data | 03/31/2014 | 03/28/2014 | |
Attend Technical Meetings | W: 122. Assist Planning Activities - Technical Review | 03/31/2014 | 03/28/2014 | |
Disseminate Results of a KWEP implemented restoration project | X: 161. Disseminate Klickitat habitat and project information | 03/31/2014 | 03/28/2014 | |
Database Management and Development (multiple databases) | Y: 160. Database Management and Development | 03/31/2014 | 03/28/2014 | |
Outreach to Professional Societies | Z: 99. Project Outreach | 03/31/2014 | 03/28/2014 | |
Conduct one appraisal | AA: 172. Acquire and review appraisal for one parcel | 03/31/2014 | 03/28/2014 | |
BPA - preparation of SOW package, submission of accrual estimate, and accurate invoices. SRFB - adm | AB: 119. BPA and SRFB Project Management and Administration | 03/31/2014 | 03/28/2014 | |
Attach 2010 Progress Report in Pisces | AC: 132. Submit Progress Report for the period (1/1/2010) to (12/31/10) | 03/31/2014 | 03/24/2014 | |
Annual report for 2012 attached in Pisces | AE: 132. Submit Annual Report for the period 1/1/2012 to 12/31/2012 | 03/31/2014 | ||
Collect topographic data via LiDAR for a section of Klickitat River valley bottom | AF: 157. Old WE "U" - Collect topo data for approx. 20 miles of Klickitat River valley bottom | 03/31/2014 | 05/31/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 04/01/2013 | ||||||
B | 165 | Prepare necessary documentation for various environmental compliance needs | 04/01/2013 | ||||||
C | 175 | Design and Specifications for Klickitat River Floodplain Project (Haul Road) Phase 4 | 04/01/2013 | ||||||
D | 100 | Contruction Oversight for Klickitat River Floodplain Project (Haul Road) - Phase 4 | 09/04/2013 | ||||||
E | 100 | Construction Oversight for Upper Klickitat Phase 3 | 09/04/2013 | ||||||
F | 30 | Upper Klickitat Phase 3 - side channel reconnection | 07/02/2013 | ||||||
G | 100 | Construction Oversight for Tepee Creek Meadows Project - Phase 2 | 09/04/2013 | ||||||
H | 29 | Tepee Creek Meadow Project (Phase 2) - Floodplain Reconnection | 07/02/2013 | ||||||
I | 175 | Design and Specifications for Upper Klickitat Project (Phase 4) | 04/01/2013 | ||||||
J | 100 | Construction Oversight for Upper Klickitat Project (Phase 4) | 04/01/2013 | ||||||
K | 47 | Manage Native Nursery | 04/09/2013 | ||||||
L | 47 | Revegetate Klickitat River Floodplain Restoration (Haul Road) Phase 4 project site | 07/02/2013 | ||||||
M | 47 | Revegetate Tepee Creek Phase 2 project site | 07/02/2013 | ||||||
N | 47 | Revegetate Upper Klickitat River Phase 3 and 4 sites | 07/02/2013 | ||||||
O | 197 | Invasive plant control | 07/02/2013 | ||||||
P | 157 | Habitat Enhancement Project Monitoring | 04/01/2013 | ||||||
Q | 157 | Streamflow monitoring | 04/10/2013 | ||||||
R | 157 | Collect water surface elevation data - Klickitat/Columbia River Confluence | 04/10/2013 | ||||||
S | 157 | Measure turbidity timing and duration associated with Big Muddy Creek | 04/10/2013 | ||||||
T | 157 | Habitat Assessment | 07/02/2013 | ||||||
U | 162 | Conduct Food Web Study on Tepee and White Creeks (Effectiveness Monitoring) | 04/01/2013 | ||||||
V | 162 | Summarize monitoring data | 04/01/2013 | ||||||
W | 122 | Assist Planning Activities - Technical Review | 04/01/2013 | ||||||
X | 161 | Disseminate Klickitat habitat and project information | 04/01/2013 | ||||||
Y | 160 | Database Management and Development | 04/01/2013 | ||||||
Z | 99 | Project Outreach | 04/01/2013 | ||||||
AA | 172 | Acquire and review appraisal for one parcel | 04/01/2013 | ||||||
AB | 119 | BPA and SRFB Project Management and Administration | 04/01/2013 | ||||||
AC | 132 | Submit Progress Report for the period (1/1/2010) to (12/31/10) | 04/01/2013 | ||||||
AD | 132 | Submit Progress Report for the period 1/1/2011 to 12/31/2011 | 04/01/2013 | ||||||
AE | 132 | Submit Annual Report for the period 1/1/2012 to 12/31/2012 | 04/01/2013 | ||||||
AF | 157 | Old WE "U" - Collect topo data for approx. 20 miles of Klickitat River valley bottom | 04/01/2013 |