Province | Subbasin | % |
---|---|---|
Columbia Gorge | Klickitat | 100.00% |
Previous: | Next: |
---|---|
56662 REL 59: 1997-013-35 EXP YKFP KLICKITAT RIVER OPERATIONS AND MAINTENANCE |
|
* Expenditures data includes accruals and are based on data through 31-Oct-2024.
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
Administrative tasks | B: 119. Contract Management & Administration | 03/31/2016 | 03/31/2016 | |
EC Compliance | C: 165. Participate in ESA/NEPA Compliance for Klickitat O&M Project | 03/31/2016 | 03/31/2016 | |
YKFP Klickitat Field Office Maintenance | D: 186. Maintain YKFP Klickitat Field Office | 03/31/2016 | 03/31/2016 | |
O&M project staff support of YKFP activities in the Klickitat Subbasin | E: 186. O&M support of K-MD&H, K-WEP, K-M&E | 03/31/2016 | 03/31/2016 | |
Lyle Fishway & Research Facility O&M | F: 186. Lyle Fishway & Research Facility O&M | 03/31/2016 | 03/31/2016 | |
Castile Falls Fishway Enumeration Facility O&M | G: 186. Castile Falls Enumeration Facility O&M | 03/31/2016 | 03/31/2016 | |
Lyle Fishway & Research Facility - Vegetation Management | H: 47. Lyle Falls Fishway & Research Facility Vegetation Management | 03/31/2016 | 03/31/2016 | |
Design system to load broodstock to transport vehicles | J: 175. Design system for moving broodstock to transport vehicle | 03/31/2016 | 03/24/2016 | |
Complete cooling water system upgrades | K: 171. Identify and implement an alternative generator cooling water system | 03/31/2016 | 03/31/2016 | |
Complete Upgrades at the Castile Falls Fishway and Enumeration Facility | L: 171. Facility Upgrades at Castile | 03/31/2016 | 03/31/2016 | |
Complete upgrades to the PLC, at the Castile Falls Fishway and Enumeration Facility. | M: 171. PLC Upgrades at Castile | 03/31/2016 | 03/31/2016 | |
All administrative tasks fulfilled with timely quality products | N: 119. Year 2: Contract Management & Administration | 03/31/2017 | 03/31/2017 | |
EC Compliance | O: 165. Year 2: Participate in ESA/NEPA Compliance for Klickitat O&M Project | 03/31/2017 | 03/31/2017 | |
YKFP Klickitat Field Office Maintenance | P: 186. Year 2: Maintain YKFP Klickitat Field Office | 03/31/2017 | 03/31/2017 | |
O&M project staff support of YKFP activities in the Klickitat Subbasin | Q: 186. Year 2: O&M support of K-MD&H, K-WEP, K-M&E | 03/31/2017 | 03/31/2017 | |
Lyle Fishway & Research Facility O&M | R: 186. Year 2: Lyle Fishway & Research Facility O&M | 03/31/2017 | 03/31/2017 | |
Castile Falls Fishway Enumeration Facility O&M | S: 186. Year 2: Castile Falls Enumeration Facility O&M | 03/31/2017 | 03/31/2017 | |
Lyle Fishway & Research Facility - Vegetation Management | T: 198. Year 2: Lyle Falls Fishway & Research Facility Vegetation Management | 03/31/2017 | 03/31/2017 | |
Completed Annual Report | U: 132. Year 2: Lyle Falls and Castile Falls Construction Final Project Report | 03/01/2017 | ||
Complete, test and operate cooling water system upgrades | W: 171. Year 2: Identify and implement an alternative generator cooling water system | 03/31/2017 | 03/25/2016 | |
Complete Upgrades at the Castile Falls Fishway and Enumeration Facility | X: 171. Year 2: Facility Upgrades at Castile | 03/31/2017 | 03/31/2017 | |
Complete upgrades to the PLC, at the Castile Falls Fishway and Enumeration Facility. | Y: 171. Year 2: PLC Upgrades at Castile | 03/31/2017 | 03/31/2016 | |
Completed 2014-2016 Annual Report and Associated Plans | Z: 132. Year 2: Annual Reports Apr2014-Mar2016 | 02/17/2017 | 03/17/2017 | |
Construction Management Complete | AA: 100. Year 2: Lyle Falls Maintenance Shop and Bullpen | 03/31/2017 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Mid-Columbia River Spring ESU |
|
Chinook (O. tshawytscha) - Upper Columbia River Summer/Fall ESU |
|
Coho (O. kisutch) - Unspecified Population |
|
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened) |
|
Lamprey, Pacific (Entosphenus tridentata) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 185 | Periodic Status Reports for BPA | 04/01/2015 | ||||||
B | 119 | Contract Management & Administration | 04/01/2015 | ||||||
C | 165 | Participate in ESA/NEPA Compliance for Klickitat O&M Project | 04/01/2015 | ||||||
D | 186 | Maintain YKFP Klickitat Field Office | 04/01/2015 | ||||||
E | 186 | O&M support of K-MD&H, K-WEP, K-M&E | |||||||
F | 186 | Lyle Fishway & Research Facility O&M | |||||||
G | 186 | Castile Falls Enumeration Facility O&M | |||||||
H | 47 | Lyle Falls Fishway & Research Facility Vegetation Management | 04/01/2015 | ||||||
I | 132 | Lyle Falls and Castile Falls Final Project Report | 04/01/2015 | ||||||
J | 175 | Design system for moving broodstock to transport vehicle | 04/01/2015 | ||||||
K | 171 | Identify and implement an alternative generator cooling water system | 04/01/2015 | ||||||
L | 171 | Facility Upgrades at Castile | 04/01/2015 | ||||||
M | 171 | PLC Upgrades at Castile | 04/01/2015 | ||||||
N | 119 | Year 2: Contract Management & Administration | 04/01/2015 | ||||||
O | 165 | Year 2: Participate in ESA/NEPA Compliance for Klickitat O&M Project | 04/01/2015 | ||||||
P | 186 | Year 2: Maintain YKFP Klickitat Field Office | 04/01/2015 | ||||||
Q | 186 | Year 2: O&M support of K-MD&H, K-WEP, K-M&E | 04/01/2016 | ||||||
R | 186 | Year 2: Lyle Fishway & Research Facility O&M | |||||||
S | 186 | Year 2: Castile Falls Enumeration Facility O&M | |||||||
T | 198 | Year 2: Lyle Falls Fishway & Research Facility Vegetation Management | 04/01/2016 | ||||||
U | 132 | Year 2: Lyle Falls and Castile Falls Construction Final Project Report | 04/01/2015 | ||||||
V | 175 | Year 2: Design system for moving adult salmon to transport vehicle | 04/01/2015 | ||||||
W | 171 | Year 2: Identify and implement an alternative generator cooling water system | 04/01/2015 | ||||||
X | 171 | Year 2: Facility Upgrades at Castile | 04/01/2015 | ||||||
Y | 171 | Year 2: PLC Upgrades at Castile | 04/01/2015 | ||||||
Z | 132 | Year 2: Annual Reports Apr2014-Mar2016 | 04/01/2015 | ||||||
AA | 100 | Year 2: Lyle Falls Maintenance Shop and Bullpen | 04/01/2015 |