55910: 2010-073-00 EXP KANDOLL FARM |
* Expenditures data includes accruals and are based on data through 30-Nov-2024.
Full Name | Organization | Write Permission | Contact Role | Work Phone | |
---|---|---|---|---|---|
Anne Creason | Bonneville Power Administration | Yes | COR | amcreason@bpa.gov | (503) 230-3859 |
Glenn Lamb | Columbia Land Trust | No | Supervisor | glamb@columbialandtrust.org | |
Scott McEwen | Columbia Land Trust | Yes | Interested Party | smcewen@columbialandtrust.org | (360) 213-1210 |
Ian Sinks | Columbia Land Trust | Yes | Contract Manager | isinks@columbialandtrust.org | (503) 799-9505 |
Kristi Van Leuven | Bonneville Power Administration | Yes | Contracting Officer | kjvleuven@bpa.gov | (503) 230-3605 |
Jesse Wilson | Bonneville Power Administration | No | Env. Compliance Lead | jcwilson@bpa.gov | (503) 230-4506 |
Benjamin Zelinsky | Bonneville Power Administration | Yes | F&W Approver | bdzelinsky@bpa.gov | (503) 230-4737 |
Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
---|---|---|---|---|
EC Compliance | A: 165. EC Compliance | 12/31/2013 | 12/31/2013 | |
Remove Dike | B: 180. Kandoll Farm P2 Dike Removal | 10/01/2013 | 09/30/2013 | |
Tidal Channel Restoration | C: 30. Kandoll Farm P2 Channel Restoration | 10/01/2013 | 09/30/2013 | |
Non-Native Vegetation Control and Site Preparation | D: 197. Kandoll Farm Vegetation Control and Site Preparation | 10/01/2013 | 09/30/2013 | |
Fulfill all administrative tasks with quality products and in a timely manner. | E: 119. Manage Kandoll Farms Design Contract | 12/31/2013 | 12/31/2013 | |
Annual report | G: 132. Submit Progress Report for the period (Jan 2012) to (Dec 2012) | 03/01/2013 | 03/01/2013 | |
Submit drawings and/or specifications to BPA | H: 175. Final project restoration design | 07/31/2013 | 07/31/2013 |
Primary Focal Species | Work Statement Elements |
---|---|
Chinook (O. tshawytscha) - Lower Columbia River ESU (Threatened) |
|
Chum (Oncorhynchus keta) - Columbia River ESU (Threatened) |
|
Coho (Oncorhynchus kisutch) - Lower Columbia River ESU (Threatened) |
|
Steelhead (O. mykiss) - Lower Columbia River DPS (Threatened) |
|
Sturgeon, Green (Acipenser medirostris) |
|
Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
---|---|---|---|---|---|---|---|---|---|
A | 165 | EC Compliance | 01/01/2012 | ||||||
B | 180 | Kandoll Farm P2 Dike Removal | 07/17/2013 | ||||||
C | 30 | Kandoll Farm P2 Channel Restoration | 07/17/2013 | ||||||
D | 197 | Kandoll Farm Vegetation Control and Site Preparation | 07/17/2013 | ||||||
E | 119 | Manage Kandoll Farms Design Contract | 01/01/2012 | ||||||
F | 185 | Periodic Status Reports for BPA | 01/01/2012 | ||||||
G | 132 | Submit Progress Report for the period (Jan 2012) to (Dec 2012) | 01/01/2012 | ||||||