Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 59895: 2010-030-00 EXP WDFW PROJECT TO PROVIDE VSP ESTIMATE
Project Number:
Title:
Yakima Steelhead VSP Project
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Yakima 100.00%
Contract Number:
59895
Contract Title:
2010-030-00 EXP WDFW PROJECT TO PROVIDE VSP ESTIMATE
Contract Continuation:
Previous: Next:
54906: 2010-030-00 WDFW PROVIDE VSP ESTIMATE FOR YAKIMA STEELHEAD MPG
  • 64137: 2010-030-00 EXP WDFW PROJECT TO PROVIDE VSP ESTIMATE
Contract Status:
Closed
Contract Description:
This contract reflects WDFW participation and work tasks associated with the co-managed Yakima Steelhead VSP proposal (Yakama Nation as Lead entity; Project 201003000).  The work elements in this contract were designed  to address VSP and RPA data gaps as called for in the FCRPS BiOp and Yakima River Steelhead Recovery Plan.  Establishing robust estimates of steelhead VSP parameters is intended to direct future recovery actions and to provide benchmark values against which progress towards steelhead recovery in the Yakima MPG can be evaluated.  Addressing VSP and RPA data gaps will contribute to the long term recovery objectives presented in the Yakima Sub-basin plan and the Yakima Steelhead Recovery Plan.  In summary, this project seeks to build on the existing programs in all the subbasins and provide information and equipment needed for long term monitoring of VSP parameters with a known level of accuracy and precision.
Account Type(s):
Expense
Contract Start Date:
11/01/2012
Contract End Date:
10/31/2013
Current Contract Value:
$216,325
Expenditures:
$216,325

* Expenditures data includes accruals and are based on data through 30-Nov-2024.

Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
EC documents obtained for this contract B: 165. Provide EC documentation to BPA 10/31/2013 10/30/2013
Fulfill all administrative tasks with quality products and in a timely manner. C: 119. Manage and administer project 10/31/2013 10/30/2013
PIT tag 10,000 O. mykiss in upper Yakima Basin tributaries and mainstem areas D: 158. PIT tag Juvenile O. Mykiss in select locations 10/31/2013 09/30/2013
O. mykiss abundance and bio-sampling E: 157. O. Mykiss abundance and bio sampling 10/15/2013 09/30/2013
Generate VSP metrics considering life history expression F: 162. Generate abundance of life history types in pre selected locations 10/31/2013 10/30/2013
Generate Prespawn population estimates (run escapement) G: 162. Generate pre-spawning steelhead population estimates 10/31/2013 09/30/2013
Produce Annual Report H: 132. Submit Progress Report for the November 1, 2011 to October 31, 2012 period 07/31/2013 07/12/2013
Present resident/anadromous interactions study progress/ findings at the YBS&M conference I: 161. Present resident/anadromous interactions study at YBS&M conference 06/30/2013 06/13/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 11/01/2012
B 165 Provide EC documentation to BPA 11/01/2012
C 119 Manage and administer project 11/01/2012
D 158 PIT tag Juvenile O. Mykiss in select locations 11/18/2013
E 157 O. Mykiss abundance and bio sampling 11/18/2013
F 162 Generate abundance of life history types in pre selected locations 11/01/2012
G 162 Generate pre-spawning steelhead population estimates 11/01/2012
H 132 Submit Progress Report for the November 1, 2011 to October 31, 2012 period 11/01/2012
I 161 Present resident/anadromous interactions study at YBS&M conference 11/01/2012