Contract 60418: 2011-004-00 EXP JOHN R. PALENSKY O&M
Project Number:
Title:
ODFW Operation & Maintenance (O&M)
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Lower Columbia Willamette 100.00%
Contract Number:
60418
Contract Title:
2011-004-00 EXP JOHN R. PALENSKY O&M
Contract Continuation:
Previous: Next:
56036: 2011-004-00 EXP JOHN R. PALENSKY O&M
  • 62170: 2011-004-00 EXP JOHN R. PALENSKY O&M
Contract Status:
Closed
Contract Description:
In 1991, Burlington Bottoms (BB) was the first site in Oregon to be purchased by the Bonneville Power Administration (BPA) under the Willamette and Columbia River Basins Fish and Wildlife Programs, to provide partial mitigation for the impacts associated with the construction of hydroelectric facilities.  The Oregon Department of Fish and Wildlife (ODFW) was contracted by BPA in 1993 to conduct interim management of the BB site, which included completion of a habitat assessment or habitat evaluation procedure (HEP).  In addition, a hydrology and hydraulics assessment was also conducted on the site in 1993. Results of the HEP and hydrology study were incorporated into the Environmental Assessment/ Management Plan written in 1994 (DOE/EA-0928).  Implementation of the EA/Management Plan began in 1995, and included custodial oversight and habitat restoration projects, including non-native vegetation removal.  In 2001, a second management plan was written, titled Five-Year Habitat Management Plan, 2001-2005.  This Plan addresses specific goals and objectives to be carried out over a five-year period, using various enhancement strategies to achieve the overall goal of protecting, maintaining and enhancing wildlife habitat on the site.   This Habitat Management Plan is being revised and will be completed in 2012.  
        
The purpose of this scope of work is to continue implementation of various management activities that include: 1) operate and maintain the water control structure as part of moist soil management for the site; 2) habitat enhancement activities including non-native plant removal and native planting; 3) custodial management of the site; and 4) monitoring and evaluation of past enhancement activities.  In addition, in 2013, one objective of the scope of work is to revise and finalize the Habitat Management Plan to reflect past activities and on-the-ground conditions.        

Coordination of this agreement will include the Oregon Department of Fish and Wildlife and the Bonneville Power Administration.

During the term of the project, project activities and expenditures shall be consistent with BPA's Final Environmental Assessment/Management Plan and Finding of No Significant Impact (December 1994, DOE/EA-0928).  Project activities not considered in the 1994 Environmental Assessment will comply with NEPA requirements in separate documentation.  Consultation with the USFWS and/or NMFS will occur as necessary and the appropriate NEPA compliance and concurrence verification will be obtained.
Account Type(s):
Expense
Contract Start Date:
12/01/2012
Contract End Date:
06/30/2013
Current Contract Value:
$78,920
Expenditures:
$78,920

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract (IGC)
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Funding Package - Submit draft to COTR B: 119. Manage and Administer Projects 03/31/2013 03/31/2013
Complete environmental compliance requirements C: 165. Produce Environmental Compliance Documentation 02/28/2013 02/28/2013
Complete ownership proposal D: 174. Develop proposal for the future ownership of Burlington Bottoms 06/30/2013 06/28/2013
Complete revised Habitat Management Plan E: 141. Revise and update Habitat Management Plan 06/15/2013 06/28/2013
Complete vegetation removal F: 197. Remove invasive, non-native vegetation 06/30/2013 06/28/2013
Complete plantings G: 47. Plant native vegetation 06/30/2013 06/28/2013
Complete operation and maintenance activities H: 186. Operate & maintain water control structure 06/30/2013 06/28/2013
Complete debris removal I: 27. Remove debris 06/30/2013 06/28/2013
Complete site monitoring J: 26. Monitor authorized and unauthorized uses of the site 06/30/2013 06/28/2013
Complete maintenance of roads & trails and replace signage K: 188. Maintain roads & trails for management access & replace signage 06/30/2013 06/28/2013
Conduct outreach & education to various groups L: 99. Conduct meetings, tours, educational activities for Willamette Mitigation Program 06/30/2013 06/28/2013
Conduct site visits to assist in identification of potential mitigation sites M: 114. Conduct site visits to assist in identification of potential mitigation sites 06/30/2013 06/28/2013
Attach Progress Report in Pisces N: 132. Submit Progress Report for December 01, 2011 to November 30, 2012 05/01/2013

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Wildlife
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 26 Investigate Trespass
  • 1 instance of WE 27 Remove Debris
  • 1 instance of WE 186 Operate and Maintain Habitat/Passage/Structure
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 114 Identify and Select Projects
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 12/01/2012
B 119 Manage and Administer Projects 12/01/2012
C 165 Produce Environmental Compliance Documentation 12/01/2012
D 174 Develop proposal for the future ownership of Burlington Bottoms 12/01/2012
E 141 Revise and update Habitat Management Plan 12/01/2012
F 197 Remove invasive, non-native vegetation 07/15/2013
G 47 Plant native vegetation 07/15/2013
H 186 Operate & maintain water control structure 07/15/2013
I 27 Remove debris 12/01/2012
J 26 Monitor authorized and unauthorized uses of the site 12/01/2012
K 188 Maintain roads & trails for management access & replace signage 07/15/2013
L 99 Conduct meetings, tours, educational activities for Willamette Mitigation Program 12/01/2012
M 114 Conduct site visits to assist in identification of potential mitigation sites 12/01/2012
N 132 Submit Progress Report for December 01, 2011 to November 30, 2012 12/01/2012