Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 62758: 2010-001-00 EXP TWISP RIVER FLOODPLAIN
Project Number:
Title:
Upper Columbia Programmatic Habitat
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Entiat 25.00%
Methow 25.00%
Okanogan 25.00%
Wenatchee 25.00%
Contract Number:
62758
Contract Title:
2010-001-00 EXP TWISP RIVER FLOODPLAIN
Contract Continuation:
Previous: Next:
n/a
  • 66397: 2010-001-00 EXP TWISP RIVER FLOODPLAIN
Contract Status:
Closed
Contract Description:
Methow Salmon Recovery Foundation (MSRF) and its partners, including Bureau of Reclamation (Reclamation), Methow Conservancy, and Trout Unlimited (TU), plan to implement a reach-scale salmon habitat enhancement project in the Lower Twisp River between 2014 and 2017. The Twisp River Floodplain Project will conduct project development and environmental compliance activities in advance of the implementation contract for the Twisp River Floodplain Project funded through the UCSRB targeted solicitation process.

Project development activities for this project include on-site vegetation surveys, topographic surveys, hydrologic monitoring and data collection, wetland delineation, fish surveys (presence/absence/use), photo points, pre-implementation weed removal, concept development, landowner/stakeholder outreach and coordination, and related project coordination activities.

Environmental compliance for this project includes Section 106 cultural consultation, limited federal Section 7 ESA consultation (USFWS and NOAA) as needed for pre-implementation activities such as surveying, and the state-required SEPA process.  Other permitting processes completed through the JARPA, including the WDFW Hydraulic Project Authorization, Corps of Engineers Nationwide permits, county shorelines and floodplain development, and water quality permits may also be initiated and/or completed in this contract if sufficient design information is completed during the contract period.  

The goal of this Twisp River Floodplain pre-implementation contract would be to work with BPA, UCSRB, and the Bureau of Reclamation to develop and design a preferred alternative for implementation at the site; and, to complete state, local, and BPA's federal EC requirements as early in the process as feasible in order to ensure completion of these requirements within the respective timelines, to allow construction to proceed in the summer 2015-17 work windows.  Early implementation actions may also be considered for 2014.
Account Type(s):
Expense
Contract Start Date:
09/22/2013
Contract End Date:
09/21/2014
Current Contract Value:
$53,124
Expenditures:
$53,124

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Contract
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Brenda Aguirre Bonneville Power Administration Yes Env. Compliance Lead baguirre@bpa.gov (503) 230-5928
Roy Beaty Bonneville Power Administration Yes F&W Approver rebeaty@bpa.gov (503) 230-5213
Joseph Connor Bonneville Power Administration Yes COR jwconnor@bpa.gov (503) 230-3172
Chris Eliassen Methow Salmon Recovery Foundation Yes Contract Manager chrise@methowsalmon.org (509) 996-2787
Brian Fisher Methow Salmon Recovery Foundation Yes Technical Contact brian@methowsalmon.org (509) 387-1716
Jessica Goldberg Methow Salmon Recovery Foundation Yes Contract Manager jessica@methowsalmon.org (360) 624-3592
Chris Johnson Methow Salmon Recovery Foundation Yes Supervisor chrisj@methowsalmon.org (509) 996-2787
Deb Nickell Methow Salmon Recovery Foundation Yes Interested Party deb@methowsalmon.org (509) 996-2787
Kristi Van Leuven Bonneville Power Administration Yes Contracting Officer kjvleuven@bpa.gov (503) 230-3605


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Complete Environmental Compliance permitting processes A: 165. Obtain Required Permits, Authorizations, and Documentation for the Twisp River Floodplain project 09/21/2014 09/19/2014
Contract Administration B: 119. Manage BPA Contracting Requirements 09/21/2014 09/19/2014
Obtain Data to Support Design C: 115. Obtain Data to Inform Development of Preferred Alternative 09/21/2014 09/19/2014
Vegetation Management D: 197. Manage Vegetation and Remove Weeds Prior to Implementation 09/21/2014
Complete Preferred Alternatives E: 174. Develop Preferred Alternatives for Design Development 09/19/2014 09/19/2014

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 1 instance of WE 197 Maintain/Remove Vegetation
  • 1 instance of WE 115 Produce Inventory or Assessment
  • 1 instance of WE 174 Produce Plan

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Obtain Required Permits, Authorizations, and Documentation for the Twisp River Floodplain project 09/22/2013
B 119 Manage BPA Contracting Requirements 09/22/2013
C 115 Obtain Data to Inform Development of Preferred Alternative 04/14/2014
D 197 Manage Vegetation and Remove Weeds Prior to Implementation 04/14/2014
E 174 Develop Preferred Alternatives for Design Development 04/14/2014
F 185 Periodic Status Reports for BPA 09/22/2013
G 132 Submit Progress Report for the period (Sep 2013) to (Sep 2014) - funded through a separate contract 09/22/2013